Surveying Online Test – Paper 2

0%
Created by 83a36dcfd5c4caff12bc80f0020c9c749e12cbbbdb7c406dc1dd39996cb85836?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get fresh, new questions in each attempt.

  • Total Questions: 30
  • Time Allotted: 30 minutes
  • Passing Score: 50%
  • Randomization: Yes
  • Certificate: No
  • Do not refresh the page!
  • 👍 All the best!

1 / 30

1. The surface of zero elevation around the earth, which is slightly irregular and curved, is known as

2 / 30

2. If the bearing of AB is N 30° W and the bearing of BC is N 40° E, then find the angle < ABC

3 / 30

3. A traverse survey can be plotted

4 / 30

4. The two-point problem as compared to the three-point problem is:

5 / 30

5. The position of a point can be fixed more accurately by

6 / 30

6. A level line is a

7 / 30

7. In survey, it was recorded that Σfall = 0 then

8 / 30

8. If a chain is found too short on testing, it can be adjusted by

9 / 30

9. The accuracy of measurement in chain surveying does not depend upon

10 / 30

10. In the scale of a map is 1:25000, what does it mean:

11 / 30

11. The best method of interpolation of contours in the direct method of contouring is by

12 / 30

12. The elevation (BM) of point A is 100 m. Backsight reading at A is 20, and foresight reading at B is 30 m. Find the RL of point B

13 / 30

13. Instrumental error in leveling is an error due to

14 / 30

14. The length of the perpendicular offset from a tangent to the junction of a transition curve and circular curve is equal to

15 / 30

15. Ranging is the process of

16 / 30

16. The observed reading on a leveling staff was 3.525 m. If the staff was 0.125m off from the original ground level, what should be the correct reading?

17 / 30

17. An operation for determining the relative elevations of different points on the surface of the earth is known as

18 / 30

18. Error in tacheometric surveying is due to

19 / 30

19. Leveling across a river is done by

20 / 30

20. Least count is given by

21 / 30

21. In plane table instrument for horizontal & vertical measurement without chaining

22 / 30

22. If the included angle is less than 180°, the deflection angle is

23 / 30

23. Placing the table over the station such that the station plotted on the sheet is exactly above the corresponding station on the ground is:

24 / 30

24. A discrepancy is the difference between

25 / 30

25. A poor fix of the table is:

26 / 30

26. *Total station measures

27 / 30

27. For Y level, Cooke's, and Cushing levels, the line of collimation should coincide with

28 / 30

28. The angle of intersection of the horizon mirror and the index mirror of an optical square is

29 / 30

29. The "point of tangency" of a simple circular curve is

30 / 30

30. In compass surveying

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Scroll to Top