Construction Management Online Test - Paper 2 » Quiz Test

Construction Management Online Test – Paper 2

0%
Created by 83a36dcfd5c4caff12bc80f0020c9c749e12cbbbdb7c406dc1dd39996cb85836?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get fresh, new questions in each attempt.

  • Total Questions: 30
  • Time Allotted: 30 minutes
  • Passing Score: 50%
  • Randomization: Yes
  • Certificate: No
  • Do not refresh the page!
  • 👍 All the best!

1 / 30

1. The total cost versus time curve of an activity is:

2 / 30

2. Mobilization advance up to 10% of the cost of work is given to a contractor:

3 / 30

3. Restraint is a restriction having:

4 / 30

4. A golden rule for the procurement of construction work suggests:

5 / 30

5. Tender documents do not contain:

6 / 30

6. Muster rolls are used for:

7 / 30

7. SLACK time refers to:

8 / 30

8. Total cost of the project is:

9 / 30

9. The upper portion of horizontal bars in a bar chart indicates:

10 / 30

10. A drawback of a bar chart is:

11 / 30

11. Line organization is mostly suitable for:

12 / 30

12. For a curve, larger the variance:

13 / 30

13. Which of the following is not a part of a contract agreement?

14 / 30

14. The time corresponding to the minimum total project cost is:

15 / 30

15. Which of the following time estimates is related to PERT?

16 / 30

16. Free float is mainly used to:

17 / 30

17. The independent float affects only:

18 / 30

18. Probability factor in PERT is given by:

19 / 30

19. The owner gets assurance of work progress and quality from:

20 / 30

20. When all the paths are arranged according to the descending order of the float, the path which is next to the critical path is known as:

21 / 30

21. The minimum number of critical paths in a network should be:

22 / 30

22. In PERT, pessimistic time is:

23 / 30

23. The duration of time which an activity can be delayed without affecting the succeeding activity is called free float which affects only:

24 / 30

24. The amount of money paid to the contractor by the client after the agreement and before the execution of work is known as:

25 / 30

25. In CPM analysis:

26 / 30

26. Critical path:

27 / 30

27. If D is the duration, ES and EF are the earliest start and earliest finish time, LS and LF are the latest start and latest finish time, then the following relation holds good:

28 / 30

28. The main principle of an organization is:

29 / 30

29. In PERT analysis, the actual performance of the task is known as:

30 / 30

30. The post-operations in CPM are marked:

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook Twitter
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments
Scroll to Top