Construction Management Online Test – Paper 2

0%
Created by 37fdd4228dab83e2f2bdee26b19f1560?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get New Questions in Each Attempt

  • Total Questions: 30
  • Time Allotted: 30 minutes
  • Passing Score: 50%
  • Randomization: Yes
  • Certificate: No
  • Do not refresh the page!
  • 👍 All the best!

1 / 30

1. A construction schedule is prepared after collecting:

2 / 30

2. The weakness in bar charts is:

3 / 30

3. Negative slack indicates:

4 / 30

4. The term CPM in construction management is an abbreviation of:

5 / 30

5. The final technical authority of a project is:

6 / 30

6. The reduction in project time normally results in:

7 / 30

7. The figure indicates:

8 / 30

8. In CPM, the actual performance of a task is called:

9 / 30

9. Insurance provision in GCC is applicable for:

10 / 30

10. If, for an activity, the optimistic time is 1 day, pessimistic time is 11 days, and the most likely time is 3 days, then the expected time is:

11 / 30

11. Line of balance technique is used for:

12 / 30

12. The minimum number of consulting firms for the direct purchase of services is:

13 / 30

13. Milestone charts are developed in:

14 / 30

14. In CPM:

15 / 30

15. The main responsibility of an overseer/Sub-Engineer is:

16 / 30

16. Inspection of construction works for quality control is carried out and covers:

17 / 30

17. No agreement is between:

18 / 30

18. Muster rolls are used for:

19 / 30

19. Restraint is a restriction having:

20 / 30

20. Crash project duration is obtained by adding the:

21 / 30

21. A dummy activity in CPM:

22 / 30

22. Completion of an activity on the CPM network diagram is generally known as:

23 / 30

23. Policy is:

24 / 30

24. Higher standard deviations mean:

25 / 30

25. The estimated time required to complete an activity is termed as:

26 / 30

26. Negative float can occur when it is:

27 / 30

27. The probability of completion of any activity within its expected time in PERT is:

28 / 30

28. Aggregate planning is planning for:

29 / 30

29. The time by which the particular activity can be delayed without affecting the preceding and succeeding activities is known as:

30 / 30

30. It means the offering, giving, receiving, or soliciting, directly or indirectly, anything of value to influence improperly the actions of another party:

Your score is

Share your achievement!

LinkedIn Facebook Twitter
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments
0
Join Discussionsx
()
x
Scroll to Top