Home» Online Test » Civil Engineering » Construction Management Online Test » Paper 1 » Paper 2 » Paper 3 0% Sorry, time's up. To complete the online test, please restart it. Created by Vikash chaudhary This is a FREE online test. Beware of scammers who ask for money to attend this test. Get fresh, new questions in each attempt. Total Questions: 30 Time Allotted: 30 minutes Passing Score: 50% Randomization: Yes Certificate: No Do not refresh the page! 👍 All the best! 1 / 30 1. Mobilization advance up to 10% of the cost of work is given to a contractor: a) On commencement of work at the site for payment of a loan taken by him b) For the purchase of construction materials c) For the payment of advances to labor and staff d) For all activities required to start the work at the site 2 / 30 2. An example of a parallel activity is: a) Completing ground floor and starting first floor construction b) Wall construction and carpentry work of doors and windows c) Completion of flooring and initiating whitewashing d) Digging of a well and construction of a septic tank 3 / 30 3. In PERT analysis, the time estimates of activities and the probability of their occurrence follow: a) Normal distribution curve b) Beta distribution curve c) Poisson distribution curve d) Binomial distribution curve 4 / 30 4. Type of organization used in the construction industry is: a) Line organization b) Line and staff organization c) Functional organization d) None of the above 5 / 30 5. The weakness in bar charts is: a) The various activities are interdependent b) Uncertainty in duration for various activities c) The sequence of activities is not very clear d) All of the above 6 / 30 6. Muster rolls are used for: a) To pay wages of workers employed on a daily basis b) To record the daily construction activities c) To evaluate the construction activities d) To evaluate the performance of workers 7 / 30 7. When the times of earliest finish and the latest finish are equal in an operation, the operation is called: a) Critical b) Float c) Free float d) All of the above 8 / 30 8. The maximum amount for the approval of tender by Gazetted 3rd class officer is: a) Three crore b) Seven crore c) Fifteen crore d) More than fifteen crore 9 / 30 9. Economic saving of time is obtained by crashing: a) Cheapest critical activity b) Cheapest non-critical activity c) Costliest critical activity d) Costliest non-critical activity 10 / 30 10. The mean of squared deviation from the mean of the distribution is known as: a) Mode b) Standard deviation c) Deviation d) Variance 11 / 30 11. If the probability factor is zero, the chances of completing the project in scheduled time are: a) 0% b) 50% c) 75% d) 100% 12 / 30 12. Negative slack occurs: a) When a deficiency of resources exists b) When the latest allowable time is greater than the earliest expected time c) When events stick to their schedule d) None of the above 13 / 30 13. Codes used in Nepal for building construction/design are: a) National Building Codes (NBC) b) Indian Standard Codes (ISC) c) American Standard Codes (ASC) d) British Standard Codes (BSC) 14 / 30 14. Henry Gantt developed the bar chart technique in: a) 1900 AD b) 1940 AD c) 1957 AD d) 1974 AD 15 / 30 15. The completion report includes: a) The details of the final bill paid to the contractor b) The details of all the bills paid to the contractor c) The details of all the bills, variations along with as-built drawings d) The compilation of all the documents during project implementation 16 / 30 16. Restraint is a restriction having: a) Both (a) and (b) above b) Zero duration c) Positive duration d) Negative duration 17 / 30 17. The duration of time which an activity can be delayed without affecting the succeeding activity is called free float which affects only: a) Preceding activities b) Succeeding activities c) The particular activity d) None of the above 18 / 30 18. Force majeure in a contract is: a) Occurrence of an act beyond the control of both the parties in contract agreement b) Preventing both parties to perform the respective obligation agreed c) Both of the above d) None of the above 19 / 30 19. PERT is: a) Activity-oriented b) Event-oriented c) Time-oriented d) Resources-oriented 20 / 30 20. Indirect cost of the project: a) Decreases with duration b) Decreases up to optimum duration and then increases with duration c) Increases with duration d) All of the above 21 / 30 21. Bar chart is used for minor projects, CPM is used for repetitive work while PERT is used for: a) Repetitive types of work b) Limited time and unlimited resources types of work c) Uncertainty time and resources types of work d) All of the above 22 / 30 22. The time corresponding to the minimum total project cost is: a) Normal time b) Crash time c) Optimistic time d) Between normal and crash time 23 / 30 23. A dummy activity in CPM: a) Has no tail event but has only a head event b) Has only a head event but no tail event c) Does not require any resources or any time d) Has no sequence and can be fitted anywhere 24 / 30 24. Total project cost: a) Increases with time b) Decreases with time c) Initially reduces with time and then increases with further increases d) Constant 25 / 30 25. Gantt chart indicates: a) Balance of work to be done b) Comparison of actual progress with the scheduled progress c) Efficiency progress d) Progressive cost of the project 26 / 30 26. In PERT, the most likely time is: a) The minimum time in which any activity can possibly be accomplished b) The maximum time which an activity might require c) The time which has the highest probability of occurrence d) None of the above 27 / 30 27. Latest start time is the: a) Latest time by which an activity can be started without delaying the project b) Latest time by which an activity can be completed without delaying the project c) Latest time the event can occur d) Any of the above 28 / 30 28. In PERT analysis, the actual performance of the task is known as: a) Activity b) Event c) Task d) Work 29 / 30 29. Direct cost of a project is due to: a) Establishment charges such as salaries to administrative staff b) Loss or gain of revenue c) Penalty imposed d) Cost of materials and wages of labor 30 / 30 30. For the construction of a project, a contractor is a: a) A person b) A firm c) An agency d) All of the above Please provide accurate information so we can send your Achievement Certificate by mail. NameEmailPhone Number Your score isShare your achievement! LinkedIn Facebook 0% Restart Test Please provide your feedback. Thank you for your valuable feedback. Send feedback Buy Construction Management MCQ PDF for Offline Study