Home» Online Test » Civil Engineering » Construction Management Online Test » Paper 1 » Paper 2 » Paper 3 0% Sorry, time's up. To complete the online test, please restart it. Created by Vikash chaudhary This is a FREE online test. Beware of scammers who ask for money to attend this test. Get fresh, new questions in each attempt. Total Questions: 50 Time Allotted: 50 minutes Passing Score: 70% Randomization: Yes Certificate: Yes Do not refresh the page! 👍 All the best! 1 / 50 1. The probability of completion of any activity within its expected time in PERT is: a) 0% b) 50% c) 75% d) 100% 2 / 50 2. The occurrence of the starting of an activity is called its: a) Head event b) Tail event c) Dual-role event d) All of the above 3 / 50 3. In PERT analysis, the start and end of activity are represented by: a) Activity b) Event c) Task d) Work 4 / 50 4. The completion report includes: a) The details of the final bill paid to the contractor b) The details of all the bills paid to the contractor c) The details of all the bills, variations along with as-built drawings d) The compilation of all the documents during project implementation 5 / 50 5. The variance will be zero if: a) Each individual deviation is zero b) Sum of deviation is zero c) Standard deviation is zero d) None of the above 6 / 50 6. Bar charts are considered suitable for: a) Major projects b) Minor projects c) Large projects d) All of the above 7 / 50 7. SLACK time refers to: a) Activity b) Event c) Both d) None of the above 8 / 50 8. Indirect cost of the project: a) Decreases with duration b) Decreases up to optimum duration and then increases with duration c) Increases with duration d) All of the above 9 / 50 9. Inspection of construction works for quality control is carried out and covers: a) Sampling, examination, and field testing of materials b) Testing specimens in the laboratory c) Observation of construction equipment and plant d) All of the above 10 / 50 10. Power stations are generally treated as: a) Light construction b) Heavy construction c) Industrial construction d) None of the above 11 / 50 11. An EPC contract means: a) End of planning and construction b) Evaluation, planning, and construction c) Engineering, planning, and construction d) Engineering, procurement, and construction 12 / 50 12. A drawback of a bar chart is: a) It is difficult to judge whether an activity is completed or not b) All the activities represented are independent of each other c) The sequence of activities is not clearly defined d) It is not possible to judge whether the activity is ahead or behind the schedule. 13 / 50 13. In CPM: a) Time optimization is given prime importance b) Cost optimization is given prime importance c) Cost is directly proportional to time d) All of the above 14 / 50 14. Which of the following is an activity in a CPM network: a) Concrete cured b) Walls plastered c) Excavation for foundation d) All of the above 15 / 50 15. The minimum number of critical paths in a network should be: a) 0 b) 1 c) 2 d) 3 16 / 50 16. The final technical authority of a project is: a) Chief engineer (DG) b) Assistant engineer c) Executive engineer d) Superintending engineer 17 / 50 17. The time with which direct cost does not reduce with the increase in time is known as: a) Normal time b) Crash time c) Optimistic time d) Standard time 18 / 50 18. The independent float affects only: a) Preceding activities b) Succeeding activities c) The particular activity d) None of the above 19 / 50 19. The difference between the total float and the free float is termed as: a) Start float b) Finish float c) Independent float d) Interfering float 20 / 50 20. On a bar chart, the various activities of a project are shown by: a) Shaded area b) Horizontal lines c) Vertical lines d) Dot marks 21 / 50 21. The scheduled completion time of an operation in CPM chart is mentioned on: a) Left top corner outside the circle b) Left top corner inside the circle c) Both of the above d) None of the above 22 / 50 22. Which of the following does not represent an activity? a) Site located b) Foundation is being dug c) The office area is being cleaned d) The invitations are being sent 23 / 50 23. Float is: a) The earliest time by which an activity may commence b) Latest time by which an activity can be delayed without hampering the completion of the project c) Latest allowable time-earliest expected time d) Time available-time required for an activity 24 / 50 24. In CPM, the actual performance of a task is called: a) An event b) An activity c) A duration d) Critical task 25 / 50 25. Henry Gantt developed the bar chart technique in: a) 1900 AD b) 1940 AD c) 1957 AD d) 1974 AD 26 / 50 26. What are the key dates of a standard contracting procedure for a project? a) Call for bidding and contract award b) Call for bidding, bid submission, and bid evaluation c) call for bidding, bid submission, bid evaluation and contract award d) call for bidding, bid submission and contract award 27 / 50 27. CPM adopts: a) Deterministic approach b) Probabilistic approach c) Fantastic approach d) All of the above 28 / 50 28. Milestone charts are developed in: a) 1900 AD b) 1940 AD c) 1957 AD d) 1974 AD 29 / 50 29. The number of pre-operations associated with an operation may be: a) One only b) Two only c) More than one d) Three only 30 / 50 30. When all the paths are arranged according to the descending order of the float, the path which is next to the critical path is known as: a) Under-critical path b) Sub-critical path c) Semi-critical path d) All of the above 31 / 50 31. If a is the optimistic time, b is the pessimistic time, and m is the most likely time, then the average time is equal to: a) (a + b + m) / 6 b) (a + 2b + m) / 6 c) (a + 2b + 4m) / 6 d) (a + 4m + b) / 6 32 / 50 32. Restraint is a restriction having: a) Both (a) and (b) above b) Zero duration c) Positive duration d) Negative duration 33 / 50 33. Construction team means: a) An engineer b) An owner c) A contractor d) All of the above 34 / 50 34. Updating may result in: a) Change of the critical path b) Decrease of project completion time c) Increase of project completion time d) All of the above 35 / 50 35. In PERT, optimistic time is: a) The minimum time in which any activity can possibly be accomplished b) The maximum time which an activity might require c) The time which has the highest probability of occurrence d) None of the above 36 / 50 36. Of the following, the PERT event is: a) Fixing of doors b) Plastering of walls c) Concrete cured d) Selection of sites 37 / 50 37. Performance security is necessary: a) After contract agreement to a successful bidder b) Before bid opening to all bidders c) During bid opening to all bidders d) Before contract agreement to successful bidders 38 / 50 38. Latest finish time in CPM technique is indicated by: a) Triangle b) Circle c) Rectangle d) Line 39 / 50 39. The dual-role event is: a) Head as well as tail event b) Sum of head and tail event c) Any event other than head and tail event d) None of the above 40 / 50 40. The upper portion of horizontal bars in a bar chart indicates: a) Total duration for completion of an activity b) Progress of work in the specified time c) Due duration for the completion of an activity d) All of the above 41 / 50 41. In time cost optimization using CPM, the crashing of activities along the critical path is done starting with the activity having: a) Highest cost slope b) Least cost slope c) Crashing has no relation with cost slope d) None of the above 42 / 50 42. 'Wait' in CPM belongs to the category of: a) Node b) Motion c) Event d) Activity 43 / 50 43. Force majeure in a contract is: a) Occurrence of an act beyond the control of both the parties in contract agreement b) Preventing both parties to perform the respective obligation agreed c) Both of the above d) None of the above 44 / 50 44. Slack time in PERT analysis: a) Can never be greater than zero b) Is always zero for critical activities c) Can never be less than zero d) Is minimum for critical events 45 / 50 45. Which operation must complete first? a) Right of the line joining two circles b) Left of the line joining two circles c) Both of the above d) None of the above 46 / 50 46. The weakness in bar charts is: a) The various activities are interdependent b) Uncertainty in duration for various activities c) The sequence of activities is not very clear d) All of the above 47 / 50 47. Tender documents do not contain: a) Tender form b) BOQ c) Amount of earnest money d) Unit rate 48 / 50 48. Choose the incorrect statement: a) Arrow representing activity in CPM network is drawn without any scale b) Head of an activity represents the finish of an activity c) Tail of an activity represents the start of an activity d) None of the above 49 / 50 49. The area under the B-curve is divided into two equal parts by: a) Expected time b) Optimistic time c) Pessimistic time d) Most likely time 50 / 50 50. An example of a parallel activity is: a) Completing ground floor and starting first floor construction b) Wall construction and carpentry work of doors and windows c) Completion of flooring and initiating whitewashing d) Digging of a well and construction of a septic tank Please provide accurate information so we can send your Achievement Certificate by mail. NameEmailPhone Number Your score is Share your achievement! LinkedIn Facebook Twitter 0% Restart Test Please provide your feedback. Thank you for your valuable feedback. Send feedback Buy Construction Management MCQ PDF for Offline Study