Construction Management Online Test – Paper 3

0%
Created by 37fdd4228dab83e2f2bdee26b19f1560?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get New Questions in Each Attempt

  • Total Questions: 50
  • Time Allotted: 50 minutes
  • Passing Score: 70%
  • Randomization: Yes
  • Certificate: Yes
  • Do not refresh the page!
  • 👍 All the best!

1 / 50

1. Which of the following time estimates is related to PERT?

2 / 50

2. The maximum amount of project cost after the price adjustment should not exceed:

3 / 50

3. In CPM:

4 / 50

4. Which of the following is not a part of a contract agreement?

5 / 50

5. The number of pre-operations associated with an operation may be:

6 / 50

6. Which method is known as the minimum cost or maximum time schedule method:

7 / 50

7. In PERT technique, completion of an activity is called:

8 / 50

8. For the execution of work in time, a work plan is prepared by:

9 / 50

9. Henry Gantt developed the bar chart technique in:

10 / 50

10. Slack time in PERT analysis:

11 / 50

11. Assuming that the cost varies with time, the cost-slope is defined as:

12 / 50

12. The minimum number of consulting firms for the direct purchase of services is:

13 / 50

13. The constraint in the case of resource smoothing operation would be:

14 / 50

14. Positive float can occur when it is:

15 / 50

15. A project is:

16 / 50

16. Direct cost of a project is due to:

17 / 50

17. When the times of earliest finish and the latest finish are equal in an operation, the operation is called:

18 / 50

18. The variance will be zero if:

19 / 50

19. The district rate finalizing committee does not include the representative of:

20 / 50

20. For a safe working environment in the working site, "Tool Box Talk" is conducted:

21 / 50

21. Indirect cost of the project:

22 / 50

22. An event is:

23 / 50

23. SLACK time refers to:

24 / 50

24. Construction team means:

25 / 50

25. In resource leveling, the main constraint would be:

26 / 50

26. In PERT analysis, the start and end of activity are represented by:

27 / 50

27. Codes used in Nepal for building construction/design are:

28 / 50

28. Free float for any activity is defined as the difference between:

29 / 50

29. A frequency distribution curve:

30 / 50

30. The minimum number of critical paths in a network should be:

31 / 50

31. Gantt chart is drawn for:

32 / 50

32. Which operation must complete first?

33 / 50

33. The main disadvantage of line organization is:

34 / 50

34. The 1st stage of construction is:

35 / 50

35. Negative float can occur when it is:

36 / 50

36. The occurrence of the starting of an activity is called its:

37 / 50

37. An EPC contract means:

38 / 50

38. Most of the works related to measurement of items and making entry to the measurement book is initiated by:

39 / 50

39. If the probability factor is zero, the chances of completing the project in scheduled time are:

40 / 50

40. Gantt chart is used for:

41 / 50

41. Policy is:

42 / 50

42. The cost corresponding to crash time is:

43 / 50

43. Critical path:

44 / 50

44. A contractor can start the construction works following the receipt of:

45 / 50

45. Line of balance technique is used for:

46 / 50

46. Critical activities having total float are:

47 / 50

47. The post-operations in CPM are marked:

48 / 50

48. In PERT, pessimistic time is:

49 / 50

49. Insurance provision in GCC is applicable for:

50 / 50

50. The duration of time which an activity can be delayed without affecting the succeeding activity is called free float which affects only:

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook Twitter
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments
0
Join Discussionsx
()
x
Scroll to Top