Home» Online Test » Civil Engineering » Construction Management Online Test » Paper 1 » Paper 2 » Paper 3 0% Sorry, time's up. To complete the online test, please restart it. Created by Vikash chaudhary This is a FREE online test. Beware of scammers who ask for money to attend this test. Get fresh, new questions in each attempt. Total Questions: 50 Time Allotted: 50 minutes Passing Score: 70% Randomization: Yes Certificate: Yes Do not refresh the page! 👍 All the best! 1 / 50 1. The main principle of an organization is: a) Unity of command & coherency b) Effective command and control c) Delegation of authority d) All of the above 2 / 50 2. Positive float can occur when it is: a) Sub-critical activity b) Critical activity c) Super-critical activity d) Normal activity 3 / 50 3. If a is the optimistic time, b is the pessimistic time, and m is the most likely time, then the average time is equal to: a) (a + b + m) / 6 b) (a + 2b + m) / 6 c) (a + 2b + 4m) / 6 d) (a + 4m + b) / 6 4 / 50 4. Which of the following time estimates is related to PERT? a) Most likely time estimate b) Pessimistic time estimate c) Optimistic time estimate d) All of the above 5 / 50 5. In PERT technique, completion of an activity is called: a) Head activity b) Head event c) Tail activity d) Tail event 6 / 50 6. Line of balance technique is used for: a) Planning of a project b) Planning of an activity c) Planning of an event d) Comparison of actual progress with the scheduled progress 7 / 50 7. Which of the following is an activity in a CPM network: a) Concrete cured b) Walls plastered c) Excavation for foundation d) All of the above 8 / 50 8. Line & staff organization is mostly suitable for: a) Simple work b) Complicated work c) Both (a) and (b) above d) None of the above 9 / 50 9. Mobilization advance up to 10% of the cost of work is given to a contractor: a) On commencement of work at the site for payment of a loan taken by him b) For the purchase of construction materials c) For the payment of advances to labor and staff d) For all activities required to start the work at the site 10 / 50 10. The square root of the variance is known as: a) Deviation b) Standard deviation c) Mode d) None of the above 11 / 50 11. Inspection of construction works for quality control is carried out and covers: a) Sampling, examination, and field testing of materials b) Testing specimens in the laboratory c) Observation of construction equipment and plant d) All of the above 12 / 50 12. Critical path network helps the engineer to: a) Concentrate his attention on critical activities b) Divert the different resources from non-critical activities to critical activities c) Be cautious for avoiding any delay in the critical activities d) All of the above 13 / 50 13. Critical path: a) Is the shortest path b) Is the bad path c) Has the maximum slack d) Has the minimum slack 14 / 50 14. The owner gets assurance of work progress and quality from: a) Supervisor b) Contractor c) Engineer d) Labours 15 / 50 15. Critical path is: a) Shortest path for the earliest completion of the project b) Longest path of the network from the first event to the last event c) Ideal path by preceding along which the project can be completed as per the schedule. d) The path that takes into account the completion of all the parallel activities 16 / 50 16. The time corresponding to the minimum total project cost is: a) Normal time b) Crash time c) Optimistic time d) Between normal and crash time 17 / 50 17. No agreement is between: a) Client, engineer b) Engineer, contractor c) Client, contractor d) Contractor, sub-contractor 18 / 50 18. In CPM method, the earliest finish is indicated by time on: a) Top right, outside the circle, in a triangle b) Top right, outside the circle, in a rectangle c) Both of the above d) None of the above 19 / 50 19. Indirect cost of the project: a) Decreases with duration b) Decreases up to optimum duration and then increases with duration c) Increases with duration d) All of the above 20 / 50 20. Restraint is a restriction having: a) Both (a) and (b) above b) Zero duration c) Positive duration d) Negative duration 21 / 50 21. A construction schedule is prepared after collecting: a) Number of operations b) Output of labor and machinery c) Quantity of various items d) All of the above 22 / 50 22. If the height of the frequency-distribution underneath it is equal to unity, then the curve is known as: a) Normal distribution curve b) Skew curve c) Probability distribution curve d) All of the above 23 / 50 23. In PERT, the most likely time is: a) The minimum time in which any activity can possibly be accomplished b) The maximum time which an activity might require c) The time which has the highest probability of occurrence d) None of the above 24 / 50 24. Insurance provision in GCC is applicable for: a) Loss of damaged material, plants b) Loss of damaged equipment c) Personal death or injury d) All of the above 25 / 50 25. For a safe working environment in the working site, "Tool Box Talk" is conducted: a) During the work b) At the end of the day's work c) Before the start of the day's work d) During lunch hour 26 / 50 26. The difference between the total float and the free float is termed as: a) Start float b) Finish float c) Independent float d) Interfering float 27 / 50 27. Total float for any activity is defined as the difference between: a) Its latest finish time and earliest start time for its successor activity b) Its latest start time and earliest start time c) Its latest start time and earliest finish time d) Its earliest finish time and earliest start time for its successor activity 28 / 50 28. It means the offering, giving, receiving, or soliciting, directly or indirectly, anything of value to influence improperly the actions of another party: a) Corrupt practice b) Fraudulent practice c) Coercive practice d) Collusive practice 29 / 50 29. The dual-role event is: a) Head as well as tail event b) Sum of head and tail event c) Any event other than head and tail event d) None of the above 30 / 50 30. Type of organization used in the construction industry is: a) Line organization b) Line and staff organization c) Functional organization d) None of the above 31 / 50 31. In a CPM/PERT network, the number of events is: a) Less than the number of activities b) More than the number of activities c) Equal to the number of activities d) All of the above 32 / 50 32. For a curve, larger the variance: a) Greater will be the uncertainty b) Smaller will be the uncertainty c) Not related to uncertainty d) All of the above 33 / 50 33. A stage or point where all previous jobs merging in it are completed and all further jobs bursting out are still to be completed is known as: a) Activity b) Event c) Duration d) None of the above 34 / 50 34. Slack time in PERT analysis: a) Can never be greater than zero b) Is always zero for critical activities c) Can never be less than zero d) Is minimum for critical events 35 / 50 35. Military organization is known as: a) Line organization b) Line and staff organization c) Functional organization d) None of the above 36 / 50 36. An EPC contract means: a) End of planning and construction b) Evaluation, planning, and construction c) Engineering, planning, and construction d) Engineering, procurement, and construction 37 / 50 37. Tender documents do not contain: a) Tender form b) BOQ c) Amount of earnest money d) Unit rate 38 / 50 38. Gantt chart is drawn for: a) Time versus activity b) Activity versus activity c) Resources versus progress d) Progress versus time 39 / 50 39. Choose the most correct statement from the following: a) Muster Roll is a document showing the payment record of workers b) Daywork is a means by which a contractor is paid for specifically instructed work-cost of labor, materials, and plant c) As per PPA/PPR, the bid security shall be 15% if the bid is 33% below. d) Expression of interest is a call for a financial proposal from contractors 40 / 50 40. The variance will be zero if: a) Each individual deviation is zero b) Sum of deviation is zero c) Standard deviation is zero d) None of the above 41 / 50 41. The objective of technical planning is: a) Preparation of specifications and estimates b) Initiating the procurement action of resources c) Taking remedial action about bottleneck in execution d) All of the above 42 / 50 42. The independent float affects only: a) Preceding activities b) Succeeding activities c) The particular activity d) None of the above 43 / 50 43. Milestone charts are developed in: a) 1900 AD b) 1940 AD c) 1957 AD d) 1974 AD 44 / 50 44. Latest finish time in CPM technique is indicated by: a) Triangle b) Circle c) Rectangle d) Line 45 / 50 45. SLACK time refers to: a) Activity b) Event c) Both d) None of the above 46 / 50 46. The meaning of modular coordination in construction is: a) Planning b) Designing c) Execution d) All of the above 47 / 50 47. Aggregate planning is planning for: a) Single activity b) Double activities c) Whole project d) Events 48 / 50 48. The direct cost of a project with respect to normal time is: a) Maximum b) Minimum c) Zero d) Infinite 49 / 50 49. CPM adopts: a) Deterministic approach b) Probabilistic approach c) Fantastic approach d) All of the above 50 / 50 50. The upper portion of horizontal bars in a bar chart indicates: a) Total duration for completion of an activity b) Progress of work in the specified time c) Due duration for the completion of an activity d) All of the above Please provide accurate information so we can send your Achievement Certificate by mail. NameEmailPhone Number Your score isShare your achievement! LinkedIn Facebook 0% Restart Test Please provide your feedback. Thank you for your valuable feedback. Send feedback Buy Construction Management MCQ PDF for Offline Study