Construction Management Online Test - Paper 3 » Quiz Test

Construction Management Online Test – Paper 3

0%
Created by 83a36dcfd5c4caff12bc80f0020c9c749e12cbbbdb7c406dc1dd39996cb85836?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get New Questions in Each Attempt

  • Total Questions: 50
  • Time Allotted: 50 minutes
  • Passing Score: 70%
  • Randomization: Yes
  • Certificate: Yes
  • Do not refresh the page!
  • 👍 All the best!

1 / 50

1. In CPM analysis:

2 / 50

2. Of the following, the PERT event is:

3 / 50

3. PERT technique of network analysis is useful for:

4 / 50

4. Restraint is a restriction having:

5 / 50

5. The owner gets assurance of work progress and quality from:

6 / 50

6. Which of the following is an event in a CPM network:

7 / 50

7. The post-operations in CPM are marked:

8 / 50

8. Total project time is the:

9 / 50

9. The difference between the total float and the free float is termed as:

10 / 50

10. An event is indicated on the network by a number enclosed in:

11 / 50

11. Latest start time is the:

12 / 50

12. The time by which the particular activity can be delayed without affecting the preceding and succeeding activities is known as:

13 / 50

13. Direct cost of a project is due to:

14 / 50

14. Time and progress chart of construction is known as:

15 / 50

15. In PERT, the most likely time is:

16 / 50

16. In a CPM/PERT network, the number of events is:

17 / 50

17. CPM family includes:

18 / 50

18. The interrelationship between the functional elements of a program is achieved through:

19 / 50

19. Positive float can occur when it is:

20 / 50

20. The dispute in construction is resolved through discussion of all parties on their respective stands leading to consensus. The process is called:

21 / 50

21. The district rate finalizing committee does not include the representative of:

22 / 50

22. The upper portion of horizontal bars in a bar chart indicates:

23 / 50

23. Gantt chart indicates:

24 / 50

24. Free float for any activity is defined as the difference between:

25 / 50

25. Choose the incorrect statement:

26 / 50

26. The pictorial representation of activities and events of a project is known as:

27 / 50

27. The benefit of the PERT network is taken by the management in:

28 / 50

28. Henry Gantt developed the bar chart technique in:

29 / 50

29. A dummy activity in CPM:

30 / 50

30. The duration of time which an activity can be delayed without affecting the succeeding activity is called free float which affects only:

31 / 50

31. The main principle of an organization is:

32 / 50

32. Which of the following time estimates is related to PERT?

33 / 50

33. Probability factor in PERT is given by:

34 / 50

34. According to Fulkerson's, the correct event numbers corresponding to events A, B, C, D, E of the network shown in figure 1 are:

35 / 50

35. In PERT, pessimistic time is:

36 / 50

36. The Force Account or AMANAT, a method of carrying out the construction work is done by:

37 / 50

37. If, for an activity, the optimistic time is 1 day, pessimistic time is 11 days, and the most likely time is 3 days, then the expected time is:

38 / 50

38. At an event other than the final event, if no activity emerges, it results in an error called:

39 / 50

39. The occurrence of the completion of an activity is called its:

40 / 50

40. Bar chart is used for minor projects, CPM is used for repetitive work while PERT is used for:

41 / 50

41. If D is the duration, ES and EF are the earliest start and earliest finish time, LS and LF are the latest start and latest finish time, then the following relation holds good:

42 / 50

42. Completion of an activity on the CPM network diagram is generally known as:

43 / 50

43. Critical path network helps the engineer to:

44 / 50

44. The relation between jobs of a particular type and various durations they have consumed for completion is expressed by:

45 / 50

45. The direct cost of a project with respect to normal time is:

46 / 50

46. The technique for establishing and maintaining priorities among various jobs of a project is known as:

47 / 50

47. Residential buildings are treated as:

48 / 50

48. The meaning of modular coordination in construction is:

49 / 50

49. Policy is:

50 / 50

50. Insurance provision in GCC is applicable for:

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook Twitter
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments
Scroll to Top