Construction Management Online Test – Paper 3

0%
Created by 83a36dcfd5c4caff12bc80f0020c9c749e12cbbbdb7c406dc1dd39996cb85836?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get New Questions in Each Attempt

  • Total Questions: 50
  • Time Allotted: 50 minutes
  • Passing Score: 70%
  • Randomization: Yes
  • Certificate: Yes
  • Do not refresh the page!
  • 👍 All the best!

1 / 50

1. Policy is:

2 / 50

2. The estimated time required to complete an activity is termed as:

3 / 50

3. In PERT, optimistic time is:

4 / 50

4. The reduction in project time normally results in:

5 / 50

5. The minimum number of consulting firms for the direct purchase of services is:

6 / 50

6. No agreement is between:

7 / 50

7. Negative slack indicates:

8 / 50

8. Gantt chart is drawn for:

9 / 50

9. The variance will be zero if:

10 / 50

10. Performance security is necessary:

11 / 50

11. In PERT, the most likely time is:

12 / 50

12. The probability of completion of any activity within its expected time in PERT is:

13 / 50

13. In time cost optimization using CPM, the crashing of activities along the critical path is done starting with the activity having:

14 / 50

14. Free float is mainly used to:

15 / 50

15. Frederick W. Taylor introduced a system of working known as:

16 / 50

16. For completion of a project, the critical path of the network represents:

17 / 50

17. The Force Account or AMANAT, a method of carrying out the construction work is done by:

18 / 50

18. Type of organization used in the construction industry is:

19 / 50

19. If D is the duration, ES and EF are the earliest start and earliest finish time, LS and LF are the latest start and latest finish time, then the following relation holds good:

20 / 50

20. In PERT analysis, the time estimates of activities and the probability of their occurrence follow:

21 / 50

21. The expected project duration in CPM follows:

22 / 50

22. Most of the works related to measurement of items and making entry to the measurement book is initiated by:

23 / 50

23. A fictitious activity with zero duration and no cost used to maintain the sequential order of the activities in the network is known as a:

24 / 50

24. CPM network is:

25 / 50

25. If an activity has its optimistic, most likely, and pessimistic times as 2, 4, and 6, respectively, then its expected time and variance are respectively:

26 / 50

26. In CPM, the actual performance of a task is called:

27 / 50

27. The mean coincides with the node if the frequency distribution curve is:

28 / 50

28. The number of pre-operations associated with an operation may be:

29 / 50

29. A contractor can start the construction works following the receipt of:

30 / 50

30. When the times of earliest finish and the latest finish are equal in an operation, the operation is called:

31 / 50

31. Earliest finish time of an activity is always:

32 / 50

32. The main disadvantage of line organization is:

33 / 50

33. A construction schedule is prepared after collecting:

34 / 50

34. The amount of VAT for the purchase of steel having an amount of NRs. 6000/- should be:

35 / 50

35. The dispute in construction is resolved through discussion of all parties on their respective stands leading to consensus. The process is called:

36 / 50

36. Free float for any activity is defined as the difference between:

37 / 50

37. Railway projects are treated as:

38 / 50

38. The interrelationship between the functional elements of a program is achieved through:

39 / 50

39. Residential buildings are treated as:

40 / 50

40. Of the following, the PERT event is:

41 / 50

41. Completion of an activity on the CPM network diagram is generally known as:

42 / 50

42. The pictorial representation of activities and events of a project is known as:

43 / 50

43. Jobs going ahead of schedule are conveniently shown in:

44 / 50

44. The square root of the variance is known as:

45 / 50

45. CPM family includes:

46 / 50

46. If the completion time for a particular project is 6 weeks and its expected time is 8 weeks, then the slack time for the project is:

47 / 50

47. The salient feature of functional organization is:

48 / 50

48. The amount of earnest money deposited at the time of submission of tender is:

49 / 50

49. The main responsibility of an overseer/Sub-Engineer is:

50 / 50

50. The upper portion of horizontal bars in a bar chart indicates:

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook Twitter
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments
Scroll to Top
0
Join Discussionsx
()
x