Construction Management Online Test - Paper 3 » Quiz Test
GKaim: Measure | Improve | Achieve

Construction Management Online Test – Paper 3

0%
Created by 83a36dcfd5c4caff12bc80f0020c9c749e12cbbbdb7c406dc1dd39996cb85836?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get fresh, new questions in each attempt.

  • Total Questions: 50
  • Time Allotted: 50 minutes
  • Passing Score: 70%
  • Randomization: Yes
  • Certificate: Yes
  • Do not refresh the page!
  • 👍 All the best!

1 / 50

1. A milestone chart:

2 / 50

2. The scheduled completion time of an operation in CPM chart is mentioned on:

3 / 50

3. Earliest finish time of an activity is always:

4 / 50

4. The final technical authority of a project is:

5 / 50

5. Gantt chart indicates:

6 / 50

6. Crashing of the project means:

7 / 50

7. Which operation must complete first?

8 / 50

8. Latest start time is the:

9 / 50

9. Muster rolls are used for:

10 / 50

10. The most critical stage of construction is the construction of:

11 / 50

11. Which type of tender generally prefers the schedule of rate?

12 / 50

12. Total project time is the:

13 / 50

13. Negative float can occur when it is:

14 / 50

14. Codes used in Nepal for building construction/design are:

15 / 50

15. CPM network is:

16 / 50

16. The Force Account or AMANAT, a method of carrying out the construction work is done by:

17 / 50

17. CPM family includes:

18 / 50

18. For the construction of a project, a contractor is a:

19 / 50

19. If an activity has its optimistic, most likely, and pessimistic times as 2, 4, and 6, respectively, then its expected time and variance are respectively:

20 / 50

20. Gantt chart is drawn for:

21 / 50

21. Latest start of the activity is always:

22 / 50

22. The maximum amount of project cost after the price adjustment should not exceed:

23 / 50

23. Tender documents do not contain:

24 / 50

24. Of the following, the PERT event is:

25 / 50

25. The amount of earnest money deposited at the time of submission of tender is:

26 / 50

26. The post-operations in CPM are marked:

27 / 50

27. Positive float can occur when it is:

28 / 50

28. For the execution of work in time, a work plan is prepared by:

29 / 50

29. Negative slack indicates:

30 / 50

30. The amount of VAT for the purchase of steel having an amount of NRs. 6000/- should be:

31 / 50

31. Critical path network helps the engineer to:

32 / 50

32. Choose the most correct statement from the following:

33 / 50

33. In a CPM/PERT network, the number of events is:

34 / 50

34. Bar charts are considered suitable for:

35 / 50

35. The cost corresponding to crash time is:

36 / 50

36. For a curve, larger the variance:

37 / 50

37. The salient feature of functional organization is:

38 / 50

38. Construction team means:

39 / 50

39. If the height of the frequency-distribution underneath it is equal to unity, then the curve is known as:

40 / 50

40. PERT technique of network analysis is useful for:

41 / 50

41. For a safe working environment in the working site, "Tool Box Talk" is conducted:

42 / 50

42. For completion of a project, the critical path of the network represents:

43 / 50

43. The time below which the duration cannot be further reduced is known as:

44 / 50

44. The amount of money paid to the contractor by the client after the agreement and before the execution of work is known as:

45 / 50

45. In time cost optimization using CPM, the crashing of activities along the critical path is done starting with the activity having:

46 / 50

46. No agreement is between:

47 / 50

47. Time and progress chart of construction is known as:

48 / 50

48. Line & staff organization is mostly suitable for:

49 / 50

49. Which of the following is an activity in a CPM network:

50 / 50

50. PERT is:

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Scroll to Top