Construction Management Online Test - Paper 3 » Quiz Test
GKaim: Measure | Improve | Achieve

Construction Management Online Test – Paper 3

0%
Created by 83a36dcfd5c4caff12bc80f0020c9c749e12cbbbdb7c406dc1dd39996cb85836?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get fresh, new questions in each attempt.

  • Total Questions: 50
  • Time Allotted: 50 minutes
  • Passing Score: 70%
  • Randomization: Yes
  • Certificate: Yes
  • Do not refresh the page!
  • 👍 All the best!

1 / 50

1. Milestone charts are developed in:

2 / 50

2. When all the paths are arranged according to the descending order of the float, the path which is next to the critical path is known as:

3 / 50

3. The total cost versus time curve of an activity is:

4 / 50

4. The cost corresponding to crash time is:

5 / 50

5. A drawback of a bar chart is:

6 / 50

6. The time corresponding to the minimum total project cost is:

7 / 50

7. Crashing of the project means:

8 / 50

8. The minimum number of consulting firms for the direct purchase of services is:

9 / 50

9. Choose the most correct statement from the following:

10 / 50

10. PERT means:

11 / 50

11. Jobs going ahead of schedule are conveniently shown in:

12 / 50

12. Indirect cost of the project:

13 / 50

13. It means the offering, giving, receiving, or soliciting, directly or indirectly, anything of value to influence improperly the actions of another party:

14 / 50

14. The independent float affects only:

15 / 50

15. If, for an activity, the optimistic time is 1 day, pessimistic time is 11 days, and the most likely time is 3 days, then the expected time is:

16 / 50

16. If the height of the frequency-distribution underneath it is equal to unity, then the curve is known as:

17 / 50

17. The objective of technical planning is:

18 / 50

18. The pictorial representation of activities and events of a project is known as:

19 / 50

19. The interrelationship between the functional elements of a program is achieved through:

20 / 50

20. Critical path:

21 / 50

21. An EPC contract means:

22 / 50

22. The minimum number of critical paths in a network should be:

23 / 50

23. The figure indicates:

24 / 50

24. The scheduled completion time of an operation in CPM chart is mentioned on:

25 / 50

25. The occurrence of the starting of an activity is called its:

26 / 50

26. The amount of VAT for the purchase of steel having an amount of NRs. 6000/- should be:

27 / 50

27. Higher standard deviations mean:

28 / 50

28. The square root of the variance is known as:

29 / 50

29. Of the following, the PERT event is:

30 / 50

30. Frederick W. Taylor introduced a system of working known as:

31 / 50

31. SLACK time refers to:

32 / 50

32. The figure indicates:

33 / 50

33. Time and progress chart of construction is known as:

34 / 50

34. If the path of activities leads back into itself, the resulting error in the network is known as:

35 / 50

35. Henry Gantt developed the bar chart technique in:

36 / 50

36. A frequency distribution curve:

37 / 50

37. The area under the B-curve is divided into two equal parts by:

38 / 50

38. The meaning of modular coordination in construction is:

39 / 50

39. The mean of squared deviation from the mean of the distribution is known as:

40 / 50

40. Latest start time is the:

41 / 50

41. Standard deviation when the optimistic time is 1 day, pessimistic time is 11 days, and most likely time is 3 days:

42 / 50

42. For completion of a project, the critical path of the network represents:

43 / 50

43. Which type of tender generally prefers the schedule of rate?

44 / 50

44. The benefit of the PERT network is taken by the management in:

45 / 50

45. In PERT, pessimistic time is:

46 / 50

46. The time below which the duration cannot be further reduced is known as:

47 / 50

47. Most of the works related to measurement of items and making entry to the measurement book is initiated by:

48 / 50

48. The most critical stage of construction is the construction of:

49 / 50

49. Total project time is the:

50 / 50

50. The difference between the total float and the free float is termed as:

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Scroll to Top