Construction Management Online Test - Paper 3 » Quiz Test
GKaim: Measure. Improve. Achieve.

Construction Management Online Test – Paper 3

0%
Created by 83a36dcfd5c4caff12bc80f0020c9c749e12cbbbdb7c406dc1dd39996cb85836?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get fresh, new questions in each attempt.

  • Total Questions: 50
  • Time Allotted: 50 minutes
  • Passing Score: 70%
  • Randomization: Yes
  • Certificate: Yes
  • Do not refresh the page!
  • 👍 All the best!

1 / 50

1. The figure indicates:

2 / 50

2. Probability factor in PERT is given by:

3 / 50

3. The technique for establishing and maintaining priorities among various jobs of a project is known as:

4 / 50

4. The upper portion of horizontal bars in a bar chart indicates:

5 / 50

5. Restraint is a restriction having:

6 / 50

6. An EPC contract means:

7 / 50

7. A guarantee amount that is provided by the contractor to the employer towards the successful execution of the contract is known as:

8 / 50

8. Bar chart is drawn for:

9 / 50

9. The number of pre-operations associated with an operation may be:

10 / 50

10. The main disadvantage of line organization is:

11 / 50

11. The relation between jobs of a particular type and various durations they have consumed for completion is expressed by:

12 / 50

12. It means the offering, giving, receiving, or soliciting, directly or indirectly, anything of value to influence improperly the actions of another party:

13 / 50

13. CPM network is:

14 / 50

14. Mobilization advance up to 10% of the cost of work is given to a contractor:

15 / 50

15. Negative float can occur when it is:

16 / 50

16. Positive float can occur when it is:

17 / 50

17. If the path of activities leads back into itself, the resulting error in the network is known as:

18 / 50

18. Time and progress chart of construction is known as:

19 / 50

19. If, for an activity, the optimistic time is 1 day, pessimistic time is 11 days, and the most likely time is 3 days, then the expected time is:

20 / 50

20. Total cost of the project is:

21 / 50

21. The main responsibility of an overseer/Sub-Engineer is:

22 / 50

22. According to Fulkerson's, the correct event numbers corresponding to events A, B, C, D, E of the network shown in figure 1 are:

23 / 50

23. In time cost optimization using CPM, the crashing of activities along the critical path is done starting with the activity having:

24 / 50

24. If an activity has its optimistic, most likely, and pessimistic times as 2, 4, and 6, respectively, then its expected time and variance are respectively:

25 / 50

25. In a CPM/PERT network, the number of events is:

26 / 50

26. The most critical stage of construction is the construction of:

27 / 50

27. The completion report includes:

28 / 50

28. The independent float affects only:

29 / 50

29. The interrelationship between the functional elements of a program is achieved through:

30 / 50

30. Muster rolls are used for:

31 / 50

31. The amount of money paid to the contractor by the client after the agreement and before the execution of work is known as:

32 / 50

32. The 1st stage of construction is:

33 / 50

33. Total project cost:

34 / 50

34. Residential buildings are treated as:

35 / 50

35. Direct cost of a project is due to:

36 / 50

36. In resource leveling, the main constraint would be:

37 / 50

37. The minimum number of consulting firms for the direct purchase of services is:

38 / 50

38. Insurance provision in GCC is applicable for:

39 / 50

39. The time below which the duration cannot be further reduced is known as:

40 / 50

40. Latest start time is the:

41 / 50

41. If the probability factor is zero, the chances of completing the project in scheduled time are:

42 / 50

42. In PERT analysis, the start and end of activity are represented by:

43 / 50

43. The pictorial representation of activities and events of a project is known as:

44 / 50

44. Gantt chart indicates:

45 / 50

45. CPM adopts:

46 / 50

46. Inspection of construction works for quality control is carried out and covers:

47 / 50

47. Free float is the:

48 / 50

48. Performance security is necessary:

49 / 50

49. 'Wait' in CPM belongs to the category of:

50 / 50

50. The figure indicates:

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Scroll to Top