Construction Management Online Test - Paper 3 » Quiz Test
GKaim: Measure. Improve. Achieve.

Construction Management Online Test – Paper 3

0%
Created by 83a36dcfd5c4caff12bc80f0020c9c749e12cbbbdb7c406dc1dd39996cb85836?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get fresh, new questions in each attempt.

  • Total Questions: 50
  • Time Allotted: 50 minutes
  • Passing Score: 70%
  • Randomization: Yes
  • Certificate: Yes
  • Do not refresh the page!
  • 👍 All the best!

1 / 50

1. If, for an activity, the optimistic time is 1 day, pessimistic time is 11 days, and the most likely time is 3 days, then the expected time is:

2 / 50

2. The difference between total float and free float is called interfering float which is nothing but the:

3 / 50

3. An event is indicated on the network by a number enclosed in:

4 / 50

4. SLACK time refers to:

5 / 50

5. The scheduled completion time of an operation in CPM chart is mentioned on:

6 / 50

6. The figure indicates:

7 / 50

7. Whenever an activity has zero total float, then:

8 / 50

8. Indirect cost of the project:

9 / 50

9. Railway projects are treated as:

10 / 50

10. The time with which direct cost does not reduce with the increase in time is known as:

11 / 50

11. An event is:

12 / 50

12. Codes used in Nepal for building construction/design are:

13 / 50

13. Force majeure in a contract is:

14 / 50

14. Time and progress chart of construction is known as:

15 / 50

15. Policy is:

16 / 50

16. Aggregate planning is planning for:

17 / 50

17. The constraint in the case of resource smoothing operation would be:

18 / 50

18. The estimated time required to complete an activity is termed as:

19 / 50

19. Insurance provision in GCC is applicable for:

20 / 50

20. 'Wait' in CPM belongs to the category of:

21 / 50

21. Total cost of the project is:

22 / 50

22. It means the offering, giving, receiving, or soliciting, directly or indirectly, anything of value to influence improperly the actions of another party:

23 / 50

23. CPM family includes:

24 / 50

24. Slack time in PERT analysis:

25 / 50

25. Residential buildings are treated as:

26 / 50

26. The mean of squared deviation from the mean of the distribution is known as:

27 / 50

27. Line organization is mostly suitable for:

28 / 50

28. The technique for establishing and maintaining priorities among various jobs of a project is known as:

29 / 50

29. The post-operations in CPM are marked:

30 / 50

30. What are the key dates of a standard contracting procedure for a project?

31 / 50

31. Crash project duration is obtained by adding the:

32 / 50

32. The cost corresponding to crash time is:

33 / 50

33. Which of the following does not represent an activity?

34 / 50

34. Standard deviation when the optimistic time is 1 day, pessimistic time is 11 days, and most likely time is 3 days:

35 / 50

35. A project is:

36 / 50

36. The maximum amount of project cost after the price adjustment should not exceed:

37 / 50

37. The main principle of an organization is:

38 / 50

38. The completion report includes:

39 / 50

39. For completion of a project, the critical path of the network represents:

40 / 50

40. The mean coincides with the node if the frequency distribution curve is:

41 / 50

41. Which of the following time estimates is related to PERT?

42 / 50

42. Latest start of the activity is always:

43 / 50

43. The time below which the duration cannot be further reduced is known as:

44 / 50

44. Latest finish time in CPM technique is indicated by:

45 / 50

45. Critical path network helps the engineer to:

46 / 50

46. The Force Account or AMANAT, a method of carrying out the construction work is done by:

47 / 50

47. Henry Gantt developed the bar chart technique in:

48 / 50

48. Float is:

49 / 50

49. A contractor can start the construction works following the receipt of:

50 / 50

50. The expected project duration in CPM follows:

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Scroll to Top