Home» Online Test » Civil Engineering » Construction Management Online Test » Paper 1 » Paper 2 » Paper 3 0% Sorry, time's up. To complete the online test, please restart it. Created by Vikash chaudhary This is a FREE online test. Beware of scammers who ask for money to attend this test. Get New Questions in Each Attempt Total Questions: 50 Time Allotted: 50 minutes Passing Score: 70% Randomization: Yes Certificate: Yes Do not refresh the page! 👍 All the best! 1 / 50 1. Policy is: a) A rule or a set of rules never to be violated b) A definite rule along which one has to proceed c) A procedure for preparing the project report d) A set of broad guidelines stipulated by management 2 / 50 2. The estimated time required to complete an activity is termed as: a) Event b) Duration c) Active time d) Float 3 / 50 3. In PERT, optimistic time is: a) The minimum time in which any activity can possibly be accomplished b) The maximum time which an activity might require c) The time which has the highest probability of occurrence d) None of the above 4 / 50 4. The reduction in project time normally results in: a) Decreasing the direct cost and increasing indirect cost b) Increasing the direct cost and decreasing the indirect cost c) Increasing the direct cost and indirect cost both d) Decreasing the direct cost and indirect cost both 5 / 50 5. The minimum number of consulting firms for the direct purchase of services is: a) 2 b) 3 c) 4 d) 5 6 / 50 6. No agreement is between: a) Client, engineer b) Engineer, contractor c) Client, contractor d) Contractor, sub-contractor 7 / 50 7. Negative slack indicates: a) Ahead of schedule condition b) Behind the schedule condition c) On schedule condition d) None of the above 8 / 50 8. Gantt chart is drawn for: a) Time versus activity b) Activity versus activity c) Resources versus progress d) Progress versus time 9 / 50 9. The variance will be zero if: a) Each individual deviation is zero b) Sum of deviation is zero c) Standard deviation is zero d) None of the above 10 / 50 10. Performance security is necessary: a) After contract agreement to a successful bidder b) Before bid opening to all bidders c) During bid opening to all bidders d) Before contract agreement to successful bidders 11 / 50 11. In PERT, the most likely time is: a) The minimum time in which any activity can possibly be accomplished b) The maximum time which an activity might require c) The time which has the highest probability of occurrence d) None of the above 12 / 50 12. The probability of completion of any activity within its expected time in PERT is: a) 0% b) 50% c) 75% d) 100% 13 / 50 13. In time cost optimization using CPM, the crashing of activities along the critical path is done starting with the activity having: a) Highest cost slope b) Least cost slope c) Crashing has no relation with cost slope d) None of the above 14 / 50 14. Free float is mainly used to: a) Identify the activities which can be delayed without affecting the total float of preceding activity b) Identify the activities which can be delayed without affecting the total float of succeeding activity c) Establish priorities d) Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities 15 / 50 15. Frederick W. Taylor introduced a system of working known as: a) Line organization b) Line and staff organization c) Functional organization d) None of the above 16 / 50 16. For completion of a project, the critical path of the network represents: a) Minimum time b) Maximum time c) Maximum cost d) Minimum cost 17 / 50 17. The Force Account or AMANAT, a method of carrying out the construction work is done by: a) Contractor using his own tools, staff, equipment, etc. b) Owner using his own tools, staff, equipment, etc. c) Sub-contractor using his own tools, staff, equipment, etc. d) None of the above 18 / 50 18. Type of organization used in the construction industry is: a) Line organization b) Line and staff organization c) Functional organization d) None of the above 19 / 50 19. If D is the duration, ES and EF are the earliest start and earliest finish time, LS and LF are the latest start and latest finish time, then the following relation holds good: a) EF = ES + D b) LS = LF - D c) LF = LS + D d) All of the above 20 / 50 20. In PERT analysis, the time estimates of activities and the probability of their occurrence follow: a) Normal distribution curve b) Beta distribution curve c) Poisson distribution curve d) Binomial distribution curve 21 / 50 21. The expected project duration in CPM follows: a) Normal distribution curve b) Beta distribution curve c) Poisson's distribution curve d) Binomial distribution curve 22 / 50 22. Most of the works related to measurement of items and making entry to the measurement book is initiated by: a) Site supervisor b) Site engineer c) Resident engineer d) Project in charge 23 / 50 23. A fictitious activity with zero duration and no cost used to maintain the sequential order of the activities in the network is known as a: a) Restraint b) Dummy activity c) Event d) All of the above 24 / 50 24. CPM network is: a) Event-oriented b) Activity-oriented c) Slack-oriented d) Float-oriented 25 / 50 25. If an activity has its optimistic, most likely, and pessimistic times as 2, 4, and 6, respectively, then its expected time and variance are respectively: a) 4 and 2/3 b) 4 and 4/9 c) 5 and 4/9 d) 5 and 2/3 26 / 50 26. In CPM, the actual performance of a task is called: a) An event b) An activity c) A duration d) Critical task 27 / 50 27. The mean coincides with the node if the frequency distribution curve is: a) Normal b) None of the above c) Symmetrical d) Unsymmetrical 28 / 50 28. The number of pre-operations associated with an operation may be: a) One only b) Two only c) More than one d) Three only 29 / 50 29. A contractor can start the construction works following the receipt of: a) Award of construct b) Contract agreement c) Notice to proceed d) Variation order 30 / 50 30. When the times of earliest finish and the latest finish are equal in an operation, the operation is called: a) Critical b) Float c) Free float d) All of the above 31 / 50 31. Earliest finish time of an activity is always: a) Equal to or more than the earliest event time of the following node b) Equal to or less than the earliest event time of the following node c) More than the earliest time of the following node d) None of the above 32 / 50 32. The main disadvantage of line organization is: a) Monopoly at the top level b) Rigid structure c) Delay in communications d) All of the above 33 / 50 33. A construction schedule is prepared after collecting: a) Number of operations b) Output of labor and machinery c) Quantity of various items d) All of the above 34 / 50 34. The amount of VAT for the purchase of steel having an amount of NRs. 6000/- should be: a) 300/- b) 600/- c) 780/- d) 960/- 35 / 50 35. The dispute in construction is resolved through discussion of all parties on their respective stands leading to consensus. The process is called: a) Amicable settlement b) Arbitration c) Dispute resolution board d) Dispute adjudication board 36 / 50 36. Free float for any activity is defined as the difference between: a) Its latest start time and earliest start time for its successor activity b) Its latest start time and earliest start time c) Its latest finish time and earliest start time for its successor activity d) Its earliest finish time and earliest start time for its successor activity 37 / 50 37. Railway projects are treated as: a) Light construction b) Heavy construction c) Industrial construction d) None of the above 38 / 50 38. The interrelationship between the functional elements of a program is achieved through: a) Work Breakdown Structure b) Bar charts c) Gantt chart d) All of the above 39 / 50 39. Residential buildings are treated as: a) Light construction b) Heavy construction c) Industrial construction d) None of the above 40 / 50 40. Of the following, the PERT event is: a) Fixing of doors b) Plastering of walls c) Concrete cured d) Selection of sites 41 / 50 41. Completion of an activity on the CPM network diagram is generally known as: a) Event b) Node c) Connector d) All of the above 42 / 50 42. The pictorial representation of activities and events of a project is known as: a) Net work b) Flow net c) Flow chart d) Algorithm 43 / 50 43. Jobs going ahead of schedule are conveniently shown in: a) Gantt chart b) Milestone chart c) Pi chart d) None of the above 44 / 50 44. The square root of the variance is known as: a) Deviation b) Standard deviation c) Mode d) None of the above 45 / 50 45. CPM family includes: a) Critical Path Analysis (CPA) b) Critical Path Plotted (CPP) c) Critical Path Scheduling (CPS) d) All of the above 46 / 50 46. If the completion time for a particular project is 6 weeks and its expected time is 8 weeks, then the slack time for the project is: a) 2 weeks b) -2 weeks c) 0 d) None of the above 47 / 50 47. The salient feature of functional organization is: a) Strict adherence to specifications b) Separation of planning and deficiency c) Each individual maintains a functional design part d) All of the above 48 / 50 48. The amount of earnest money deposited at the time of submission of tender is: a) 2-3% of the estimated amount b) 1-2% of the estimated amount c) 0.5-1% of the estimated amount d) None of the above 49 / 50 49. The main responsibility of an overseer/Sub-Engineer is: a) To teach the subordinates b) To plan and execute the work c) To understand the duties d) All of the above 50 / 50 50. The upper portion of horizontal bars in a bar chart indicates: a) Total duration for completion of an activity b) Progress of work in the specified time c) Due duration for the completion of an activity d) All of the above Please provide accurate information so we can send your Achievement Certificate by mail. NameEmailPhone Number Your score is Share your achievement! LinkedIn Facebook Twitter 0% Restart Test Please provide your feedback. Thank you for your valuable feedback. Send feedback Buy Construction Management MCQ PDF for Offline Study Share the above MCQs: Click to share on Facebook (Opens in new window) Facebook Click to share on WhatsApp (Opens in new window) WhatsApp Click to share on X (Opens in new window) X Click to share on LinkedIn (Opens in new window) LinkedIn Click to share on Reddit (Opens in new window) Reddit