Construction Management Online Test – Paper 2

0%
Created by 83a36dcfd5c4caff12bc80f0020c9c749e12cbbbdb7c406dc1dd39996cb85836?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get New Questions in Each Attempt

  • Total Questions: 30
  • Time Allotted: 30 minutes
  • Passing Score: 50%
  • Randomization: Yes
  • Certificate: No
  • Do not refresh the page!
  • 👍 All the best!

1 / 30

1. On a bar chart, the various activities of a project are shown by:

2 / 30

2. Indirect cost of the project:

3 / 30

3. Which of the following is not a part of a contract agreement?

4 / 30

4. PERT technique of network analysis is useful for:

5 / 30

5. If the probability factor is zero, the chances of completing the project in scheduled time are:

6 / 30

6. The activity which neither takes time nor cost for its completion but is logically required to start the succeeding activity is known as:

7 / 30

7. Free float is the:

8 / 30

8. A guarantee amount that is provided by the contractor to the employer towards the successful execution of the contract is known as:

9 / 30

9. 'Wait' in CPM belongs to the category of:

10 / 30

10. In PERT analysis, the actual performance of the task is known as:

11 / 30

11. Free float for any activity is defined as the difference between:

12 / 30

12. Who is responsible for accidents occurring at the site?

13 / 30

13. The pictorial representation of activities and events of a project is known as:

14 / 30

14. If the completion time for a particular project is 6 weeks and its expected time is 8 weeks, then the slack time for the project is:

15 / 30

15. Power stations are generally treated as:

16 / 30

16. Muster rolls are used for:

17 / 30

17. If a is the optimistic time, b is the pessimistic time, and m is the most likely time, then the average time is equal to:

18 / 30

18. The difference between total float and free float is called interfering float which is nothing but the:

19 / 30

19. The time below which the duration cannot be further reduced is known as:

20 / 30

20. An event is indicated on the network by a number enclosed in:

21 / 30

21. The dispute in construction is resolved through discussion of all parties on their respective stands leading to consensus. The process is called:

22 / 30

22. The time by which the particular activity can be delayed without affecting the preceding and succeeding activities is known as:

23 / 30

23. In CPM method, the earliest finish is indicated by time on:

24 / 30

24. The mean of squared deviation from the mean of the distribution is known as:

25 / 30

25. The weakness in bar charts is:

26 / 30

26. The maximum amount for the approval of tender by Gazetted 3rd class officer is:

27 / 30

27. The benefit of the PERT network is taken by the management in:

28 / 30

28. The maximum amount of project cost after the price adjustment should not exceed:

29 / 30

29. The upper portion of horizontal bars in a bar chart indicates:

30 / 30

30. Which of the following techniques is advanced and more indicative in modern construction progress review?

Your score is

Share your achievement!

LinkedIn Facebook Twitter
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments
Scroll to Top
0
Join Discussionsx
()
x