Home» Online Test » Civil Engineering » Construction Management Online Test » Paper 1 » Paper 2 » Paper 3 0% Sorry, time's up. To complete the online test, please restart it. Created by Vikash chaudhary This is a FREE online test. Beware of scammers who ask for money to attend this test. Get New Questions in Each Attempt Total Questions: 30 Time Allotted: 30 minutes Passing Score: 50% Randomization: Yes Certificate: No Do not refresh the page! 👍 All the best! 1 / 30 1. On a bar chart, the various activities of a project are shown by: a) Shaded area b) Horizontal lines c) Vertical lines d) Dot marks 2 / 30 2. Indirect cost of the project: a) Decreases with duration b) Decreases up to optimum duration and then increases with duration c) Increases with duration d) All of the above 3 / 30 3. Which of the following is not a part of a contract agreement? a) Price schedule b) Work schedule c) Manning schedule d) Cost Estimate 4 / 30 4. PERT technique of network analysis is useful for: a) Small projects b) Large projects c) Research and development projects d) All of the above 5 / 30 5. If the probability factor is zero, the chances of completing the project in scheduled time are: a) 0% b) 50% c) 75% d) 100% 6 / 30 6. The activity which neither takes time nor cost for its completion but is logically required to start the succeeding activity is known as: a) Dummy activity b) Fictitious activity c) Redundant activity d) All of the above 7 / 30 7. Free float is the: a) Portion of independent float b) Portion of positive total float c) Portion of interfering float d) All of the above 8 / 30 8. A guarantee amount that is provided by the contractor to the employer towards the successful execution of the contract is known as: a) Tender security b) Bid security c) Performance security d) Advance security 9 / 30 9. 'Wait' in CPM belongs to the category of: a) Node b) Motion c) Event d) Activity 10 / 30 10. In PERT analysis, the actual performance of the task is known as: a) Activity b) Event c) Task d) Work 11 / 30 11. Free float for any activity is defined as the difference between: a) Its latest start time and earliest start time for its successor activity b) Its latest start time and earliest start time c) Its latest finish time and earliest start time for its successor activity d) Its earliest finish time and earliest start time for its successor activity 12 / 30 12. Who is responsible for accidents occurring at the site? a) Petty contractor b) Himself c) Consultant d) Contractor 13 / 30 13. The pictorial representation of activities and events of a project is known as: a) Net work b) Flow net c) Flow chart d) Algorithm 14 / 30 14. If the completion time for a particular project is 6 weeks and its expected time is 8 weeks, then the slack time for the project is: a) 2 weeks b) -2 weeks c) 0 d) None of the above 15 / 30 15. Power stations are generally treated as: a) Light construction b) Heavy construction c) Industrial construction d) None of the above 16 / 30 16. Muster rolls are used for: a) To pay wages of workers employed on a daily basis b) To record the daily construction activities c) To evaluate the construction activities d) To evaluate the performance of workers 17 / 30 17. If a is the optimistic time, b is the pessimistic time, and m is the most likely time, then the average time is equal to: a) (a + b + m) / 6 b) (a + 2b + m) / 6 c) (a + 2b + 4m) / 6 d) (a + 4m + b) / 6 18 / 30 18. The difference between total float and free float is called interfering float which is nothing but the: a) Float of the head event b) Float of the tail event c) Slack of the head event d) Slack of the tail event 19 / 30 19. The time below which the duration cannot be further reduced is known as: a) Normal time b) Crash time c) Optimistic time d) Standard time 20 / 30 20. An event is indicated on the network by a number enclosed in: a) A circle b) A square c) A triangle d) All of the above 21 / 30 21. The dispute in construction is resolved through discussion of all parties on their respective stands leading to consensus. The process is called: a) Amicable settlement b) Arbitration c) Dispute resolution board d) Dispute adjudication board 22 / 30 22. The time by which the particular activity can be delayed without affecting the preceding and succeeding activities is known as: a) Interfering float b) Independent float c) Total float d) Free float 23 / 30 23. In CPM method, the earliest finish is indicated by time on: a) Top right, outside the circle, in a triangle b) Top right, outside the circle, in a rectangle c) Both of the above d) None of the above 24 / 30 24. The mean of squared deviation from the mean of the distribution is known as: a) Mode b) Standard deviation c) Deviation d) Variance 25 / 30 25. The weakness in bar charts is: a) The various activities are interdependent b) Uncertainty in duration for various activities c) The sequence of activities is not very clear d) All of the above 26 / 30 26. The maximum amount for the approval of tender by Gazetted 3rd class officer is: a) Three crore b) Seven crore c) Fifteen crore d) More than fifteen crore 27 / 30 27. The benefit of the PERT network is taken by the management in: a) Formulating a new schedule b) Coordinating various tasks c) Readjusting the time to meet the target d) All of the above 28 / 30 28. The maximum amount of project cost after the price adjustment should not exceed: a) 15% b) 20% c) 25% d) 30% 29 / 30 29. The upper portion of horizontal bars in a bar chart indicates: a) Total duration for completion of an activity b) Progress of work in the specified time c) Due duration for the completion of an activity d) All of the above 30 / 30 30. Which of the following techniques is advanced and more indicative in modern construction progress review? a) Earned value b) S-curve c) Histogram d) Milestones Your score is Share your achievement! LinkedIn Facebook Twitter 0% Restart Test Please provide your feedback. Thank you for your valuable feedback. Send feedback Buy Construction Management MCQ PDF for Offline Study Share the above MCQs: Click to share on Facebook (Opens in new window) Facebook Click to share on WhatsApp (Opens in new window) WhatsApp Click to share on X (Opens in new window) X Click to share on LinkedIn (Opens in new window) LinkedIn Click to share on Reddit (Opens in new window) Reddit