Estimating & Costing Online Test - Paper 3 » Ultimate Challenge
GKaim: Measure. Improve. Achieve.

Estimating & Costing Online Test – Paper 3

0%
Created by 83a36dcfd5c4caff12bc80f0020c9c749e12cbbbdb7c406dc1dd39996cb85836?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get fresh, new questions in each attempt.

  • Total Questions: 50
  • Time Allotted: 50 minutes
  • Passing Score: 70%
  • Randomization: Yes
  • Certificate: Yes
  • Do not refresh the page!
  • 👍 All the best!

1 / 50

1. 1 He=......Ropani.

2 / 50

2. For small residential buildings, the cost installation and electrification are made as:

3 / 50

3. 1 British gallon=.........litres.

4 / 50

4. The value of the property or structures becomes less by its becoming out of date in style is known as

5 / 50

5. Which one area must be greater at any floor of a building?

6 / 50

6. How many kilo-liters are in one cubic meter?

7 / 50

7. Arrange the specific weights of wood (w), cement (c), steel (s), and coarse aggregate (A) in increasing order

8 / 50

8. The information that can't be included in drawings is conveyed to the estimator through

9 / 50

9. When additional works are added to the original works, the estimate is called:

10 / 50

10. Plinth area estimate is an approximate estimate mostly used for the estimation of:

11 / 50

11. Normally which one contract gives the maximum value of the project

12 / 50

12. The capacity of a flushing cistern is normally

13 / 50

13. A document showing the list of quantity of various items of works required for the completion of any project is known as

14 / 50

14. Whenever color washing on A.C. corrugated sheets is done, in the estimation, the plan area of the sheets is increased by

15 / 50

15. The depreciation of the value of the building costs are generally not considered for the initial:

16 / 50

16. End lap provided in asbestos cements is equal to

17 / 50

17. The unit of payment for excavation trenches for pipes, cables, etc., up to 1.5 m depth in ordinary rock/hard rock is

18 / 50

18. The weight of 10 mm diameter mild steel rod per meter length is equal to

19 / 50

19. Due to a change in the price level, a revised estimate is prepared if the sanctioned estimate exceeds:

20 / 50

20. Which method is easiest for the estimation of the quantity of material?

21 / 50

21. The document showing the account of work done or supply of material, including the particulars and quantities, is called

22 / 50

22. The explosive for blasting is usually expressed in terms of

23 / 50

23. A layer of dry bricks put below the foundation concrete, in the case of soft soils, is called

24 / 50

24. A document containing a detailed description of all types of work (but their quantities are not mentioned) together with their current rates is called

25 / 50

25. The unit of payment for fixing of glass panes or cleaning is in

26 / 50

26. The order of booking dimension is:

27 / 50

27. Working out the exact quantities of various items of work is known as

28 / 50

28. When engineering departments undertake the works of other departments, the amount charged toward design, supervision, and execution, etc., is called

29 / 50

29. In the case of steel rolling shutters, for the estimation of the painted area, the plain area is multiplied by

30 / 50

30. The process of calculating the amount of material, labor, and equipment for a unit of work together with overhead and profit for the contractor is:

31 / 50

31. The number of corrugations in a galvanized corrugated sheet is usually

32 / 50

32. The fundamental units in the metric system are:

33 / 50

33. In the analysis of rates, what percentage of total cost is provided towards water charges?

34 / 50

34. The chairman of the material rate fixation committee in the district is

35 / 50

35. The unit of measurement for woodwork in door and window frame, rafters, beams, roof trusses, etc., is

36 / 50

36. The thickness of 25 gauge sheet is

37 / 50

37. The value shown in the account book after allowing necessary depreciation is known as

38 / 50

38. The approximate weight of one cubic meter of mild steel is

39 / 50

39. A fixed stipulated sum of penalty payable by the contractor having no relationship with real damage is known as

40 / 50

40. If the payment of annuity begins after some years in future, it is known as

41 / 50

41. The minimum number of hinges provided in a door and window shutter should be

42 / 50

42. Specifications of any works are required only when the work is carried out by:

43 / 50

43. When it is not specified, the number of holdfasts for a door is usually taken as

44 / 50

44. The amount of cement required per cubic meter having mix (1:3:6) is

45 / 50

45. The unit of measurement for electric wiring or electrification light, fan plug points is

46 / 50

46. Evaluation of building is done based on

47 / 50

47. According to ISI method of measurement, the order is in the sequence

48 / 50

48. The useful part of the livable area of a building is also known as

49 / 50

49. The building material brick

50 / 50

50. According to ISI method of measurement, the order of sequence is:

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Scroll to Top