Home» Online Test » Civil Engineering » Estimating & Costing Online Test » Paper 1 » Paper 2 » Paper 3 0% Sorry, time's up. To complete the online test, please restart it. Created by Vikash chaudhary This is a FREE online test. Beware of scammers who ask for money to attend this test. Get fresh, new questions in each attempt. Total Questions: 50 Time Allotted: 50 minutes Passing Score: 70% Randomization: Yes Certificate: Yes Do not refresh the page! 👍 All the best! 1 / 50 1. The chairman of the material rate fixation committee in the district is a) CDO b) LDO c) Chairman of DDC d) SP 2 / 50 2. The number of corrugations in an asbestos cement sheet is usually a) 5 b) 7 c) 10 d) 12 3 / 50 3. The weight of cement in one bag is a) 45 kg b) 50 kg c) 60 kg d) 65 kg 4 / 50 4. Estimate is a) the actual cost of construction of a structure b) the probable cost arrived at before the commencement of the structure c) a random guess of the cost of the structure d) none of the above 5 / 50 5. Minimum size of the pipe connected to the septic tank is a) 50 mm b) 100 mm c) 150 mm d) 200 mm 6 / 50 6. If the payment of annuity begins after some years in the future, it is known as a) Substitute agency b) Debitable agency c) Secondary agency d) Creditable agency 7 / 50 7. In the case of a roof truss made of steel, rivets, bolts, nuts, etc., normally account for a) 5% b) 10% c) 15% d) 20% 8 / 50 8. The unit rate of items written by the contractor in BOQ is in numeral as well as alphabetical form. Which one is preferred? a) numeral b) alphabetical c) both of the above d) none of the above 9 / 50 9. In the long and short wall method of estimation, the length of the long wall is the center to center space between walls plus a) breadth of the wall b) half of the breadth of the wall on each side c) one-fourth of the breadth of the wall on each side d) none of the above 10 / 50 10. The order of booking dimension is: a) Length, breadth, height b) Breadth, height, length c) Length, height, breadth d) Height, breadth, length 11 / 50 11. Payment of the steel is done by a) per quintal b) per MT c) per thousand d) per bundle 12 / 50 12. The thickness of slabs and beams must be measured to the nearest a) 0.001 m b) 0.005 m c) 0.01 m d) 0.05 m 13 / 50 13. The amount of cement required per cubic meter having mix (1:3:6) is a) 4.3 bags b) 3.3 bags c) 6.3 bags d) 5.3 bags 14 / 50 14. A layer of dry bricks put below the foundation concrete, in the case of soft soils, is called a) Soling b) Dead man c) D.P.C. d) None of the above 15 / 50 15. The unit of measurement for earthwork in excavation in ordinary soils, earthwork in mixed soil with kankar, bajri, etc., when the depth of excavation does not exceed 30 cm, is a) r.m b) cu m c) sq m d) 100 sq. m 16 / 50 16. The most reliable estimate is: a) Preliminary estimate b) Plinth area estimate c) Detailed estimate d) Cube rate estimate 17 / 50 17. The gradual accumulation of amounts by way of annual periodic deposits, which is meant for the replacement of the structure at the end of its useful life period, is known as a) Annuity depreciation b) Depreciation c) Sinking fund d) Solatium 18 / 50 18. During the calculation of RCC, the amount of steel deducted is a) 3% of the total steel b) 5% of the total steel c) 10% of the total steel d) 0% of the total steel 19 / 50 19. In which of the following works, the work turned in cu.m per mason per day will be the least? a) Random rubble masonry in lime mortar b) Stone arch work c) Brick masonry in superstructure d) Brick masonry in parapet wall 20 / 50 20. The amount of money deposited along with the submission of tender is known as a) Security money b) Performance bond c) Retention money d) Earnest money 21 / 50 21. A document containing a detailed description of all types of work (but their quantities are not mentioned) together with their current rates is called a) Tender b) Schedule of rates c) Analysis of rate d) Abstract estimate 22 / 50 22. Which of the following is not a common size of reinforcement bars? a) 16 mm b) 20 mm c) 25 mm d) 32 mm 23 / 50 23. Plinth area of a building does not include: a) Area of the wall at floor level b) Area of stair cover c) Internal shaft for sanitary installations up to 2 sq.m. in area d) Area of the cantilevered porch 24 / 50 24. Centre line method is specially adopted for estimating... Buildings. a) circular buildings b) hexagonal buildings c) octagonal buildings d) all of the above 25 / 50 25. The unit of payment for excavation trenches for pipes, cables, etc., up to 1.5 m depth in ordinary rock/hard rock is a) cu m b) sq m c) metre d) tonne 26 / 50 26. The quantity of work of any item which is the output of a skilled labor in a day is known as a) Basic work b) Daily work c) Target work d) Task work 27 / 50 27. Which of the following is not considered while preparing the item rate estimate? a) Inflation on material and wage of manpower b) The unit rate of materials c) The wage of manpower d) The charge of equipment and tools 28 / 50 28. According to ISI method of measurement, the order of sequence is: a) Length, breadth, height b) Breadth, height, length c) Height, length, breadth d) Length, height, breadth 29 / 50 29. The building material brick a) Absorbs more heat than stone b) Absorbs less heat than stone c) Absorbs equal heat as the stone d) May be less or more 30 / 50 30. The number of skilled and unskilled manpower required for the fabrication of one metric ton steel (Norms prepared by DoR) is a) 2,9 b) 3,9 c) 4,9 d) 5,9 31 / 50 31. Which of the following is not an essential part of the general specification of public works? a) Material details b) Work methodology c) Illustrative sketches d) Mode of measurement for payment 32 / 50 32. The volume of concrete for a reinforced concrete isolated sloped footing with top and bottom areas equal to A1 and A2 and with a height equal to h is given by: a) V = h/2 [A1+A2+(√A1A2)] b) V = h/3 [A1+A2+(√A1A2)] c) V = h/3 [A1+A2] d) V = h/3 [A1+A2+2A1A2] 33 / 50 33. Providing and assembling in position false work for the construction of RCC superstructure is measured in: a) Meter b) Square meter c) Cubic meter d) Kg 34 / 50 34. The rate of an item of work depends a) Specifications of works b) Specifications of materials c) Method of construction d) All of the above 35 / 50 35. The portion which is wrongly excavated by the contractor is to be filled a) The earth excavated from the same pit b) the earth excavated from a borrow pit for away from the site c) concrete as specified d) brick masonry 36 / 50 36. Of the total estimated cost of a building, the cost of electrification usually accounts for a) 3% b) 8% c) 13% d) 18% 37 / 50 37. The unit of payment for roadside brick edging to increase the pavement width is a) cu m b) metre c) sq m d) kg 38 / 50 38. Following items of earthwork are not measured separately a) setting out of work b) site clearance c) dead man d) all of the above 39 / 50 39. The full form of VAT is a) Variation at tax b) Voucher and tax c) Value-added tax d) Violation and taxation 40 / 50 40. Due to a change in the price level, a revised estimate is prepared if the sanctioned estimate exceeds: a) 2% b) 3% c) 4% d) 5% 41 / 50 41. When additional works are added to the original works, the estimate is called: a) Plinth area estimate b) Surface area estimate c) Cubical content estimate d) Supplementary estimate 42 / 50 42. For brick construction, the lime-sand mortar is a) 1:01 b) 1:02 c) 2:01 d) 1:03 43 / 50 43. Volume is measured correct to the nearest: a) 0.01 cum b) 0.02 cum c) 0.03 cum d) 0.04 cum 44 / 50 44. Normally which one contract gives the maximum value of the project a) labor contract b) item rate contract c) LS contract d) all of the above 45 / 50 45. Bill of quantities is prepared based on: a) Actual construction quantities b) Estimated quantities c) Variation in estimated quantities d) None of the above 46 / 50 46. Contractor profit is added to a) Detailed estimate b) Rate analysis c) Valuation d) Salvage 47 / 50 47. Demolition means a) Same as dismantle b) Breaking up the structure c) Breaking up the structure with care d) None of the above 48 / 50 48. In CGI sheet roofing, the overlap along the length of the sheet should not be less than? a) One corrugation b) One and a half corrugation c) Two corrugation d) None of the above 49 / 50 49. The standard width of the galvanized iron sheet is a) 32" b) 36" c) 41" d) 46" 50 / 50 50. In the case of unsewered areas, an additional provision for a septic tank is usually a) 1% of the building cost b) 3 to 4% of the building cost c) 10% of the building cost d) 12 to 15% of the building cost Please provide accurate information so we can send your Achievement Certificate by mail. NameEmailPhone Number Your score is Share your achievement! LinkedIn Facebook Twitter 0% Restart Test Please provide your feedback. Thank you for your valuable feedback. Send feedback Buy Estimating & Costing MCQ PDF for Offline Study