Estimating & Costing Online Test – Paper 3

0%
Created by 83a36dcfd5c4caff12bc80f0020c9c749e12cbbbdb7c406dc1dd39996cb85836?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get New Questions in Each Attempt

  • Total Questions: 50
  • Time Allotted: 50 minutes
  • Passing Score: 70%
  • Randomization: Yes
  • Certificate: Yes
  • Do not refresh the page!
  • 👍 All the best!

1 / 50

1. The actual size of the modular brick (as per IS Code) is

2 / 50

2. In which of the following works, the work turned in cu.m per mason per day will be the least?

3 / 50

3. Approximate weight of 1 cubic meter of sand is

4 / 50

4. The capacity of a flushing cistern is normally

5 / 50

5. The value of the property (without being disassembled) at the end of the useful life period is known as

6 / 50

6. In the specification of earthwork in foundation trenches, drains, etc. lift ordinarily specified is

7 / 50

7. A document showing the list of quantity of various items of works required for the completion of any project is known as

8 / 50

8. Demolition means

9 / 50

9. The document showing the account of work done or supply of material, including the particulars and quantities, is called

10 / 50

10. When it is not specified, the number of holdfasts for a door is usually taken as

11 / 50

11. The unit of PVC pipe used in water supply pipeline is

12 / 50

12. Which of the following is known as job overhead?

13 / 50

13. The types of work done by the use of labor but not material, equipment, etc., are known as:

14 / 50

14. Centre line method is specially adopted for estimating... Buildings.

15 / 50

15. Minimum side lap required for asbestos cement sheets is

16 / 50

16. The unit rate of items written by the contractor in BOQ is in numeral as well as alphabetical form. Which one is preferred?

17 / 50

17. The thickness of 25 gauge sheet is

18 / 50

18. Working out the exact quantities of various items of work is known as

19 / 50

19. What is the minimum period for which the lime concrete in the foundation be left wet without the construction of masonry over it?

20 / 50

20. The main target of a contractor is to

21 / 50

21. Work-charged establishment

22 / 50

22. The unit of payment for excavation trenches for pipes, cables, etc., up to 1.5 m depth in ordinary rock/hard rock is

23 / 50

23. End lap provided in asbestos cements is equal to

24 / 50

24. A fixed stipulated sum of penalty payable by the contractor having no relationship with real damage is known as

25 / 50

25. The necessary elements of the estimate are:

26 / 50

26. The number of standard bricks in one cubic meter of masonry is:

27 / 50

27. When additional works are added to the original works, the estimate is called:

28 / 50

28. The method of valuation of a building as used by commercial banks is based on:

29 / 50

29. The chairman of the material rate fixation committee in the district is

30 / 50

30. Estimate is

31 / 50

31. As per norms prepared by the ministry of transport & works, one porter can carry a weight of

32 / 50

32. Liquidated damage is directly related to

33 / 50

33. The value shown in the account book after allowing necessary depreciation is known as

34 / 50

34. In the case of a roof truss made of steel, rivets, bolts, nuts, etc., normally account for

35 / 50

35. Which of the following is the most correct estimate

36 / 50

36. According to ISI method of measurement, the order of sequence is:

37 / 50

37. Actual cost of construction plus certain profit is paid to the contractor. Such a contract is known as

38 / 50

38. The area of the segmental portion of an arch with span I and rise r is approximately given by

39 / 50

39. Providing and assembling in position false work for the construction of RCC superstructure is measured in:

40 / 50

40. The approximate weight of one cubic meter of mild steel is

41 / 50

41. Of the total estimated cost of a building, the cost of electrification usually accounts for

42 / 50

42. The order of booking dimension is:

43 / 50

43. In the case of steel rolling shutters, for the estimation of the painted area, the plain area is multiplied by

44 / 50

44. For electric wiring such as a fan, light, plug, etc., the estimate is made in terms of

45 / 50

45. In the long and short wall method of estimation, the length of the long wall is the center to center space between walls plus

46 / 50

46. Plinth area of a building does not include:

47 / 50

47. Bill of quantities is prepared based on:

48 / 50

48. The fundamental units in the metric system are:

49 / 50

49. If the payment of annuity begins after some years in future, it is known as

50 / 50

50. Which of the following is not an essential part of the general specification of public works?

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook Twitter
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments
0
Join Discussionsx
()
x
Scroll to Top