Estimating & Costing Online Test - Paper 3 » Ultimate Challenge
GKaim: Measure. Improve. Achieve.

Estimating & Costing Online Test – Paper 3

0%
Created by 83a36dcfd5c4caff12bc80f0020c9c749e12cbbbdb7c406dc1dd39996cb85836?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get fresh, new questions in each attempt.

  • Total Questions: 50
  • Time Allotted: 50 minutes
  • Passing Score: 70%
  • Randomization: Yes
  • Certificate: Yes
  • Do not refresh the page!
  • 👍 All the best!

1 / 50

1. The measurement of steel grills is taken in terms of

2 / 50

2. A document containing a detailed description of all types of work (but their quantities are not mentioned) together with their current rates is called

3 / 50

3. The standard width of an asbestos cement corrugated sheet is

4 / 50

4. Which one information is found through specification?

5 / 50

5. In a sanitary pipeline for 3 m length, how many skilled labor are required

6 / 50

6. Working out the exact quantities of various items of work is known as

7 / 50

7. The actual weight of cement bag is more in case of

8 / 50

8. A fixed stipulated sum of penalty payable by the contractor having no relationship with real damage is known as

9 / 50

9. The rate of an item of work depends

10 / 50

10. Due to a change in the price level, a revised estimate is prepared if the sanctioned estimate exceeds:

11 / 50

11. During the excavation of soil, some portion is left without disturbing, which is known as

12 / 50

12. During the calculation of RCC, the amount of steel deducted is

13 / 50

13. One metric horsepower is equal to

14 / 50

14. The amount of cement required per cubic meter having mix (1:3:6) is

15 / 50

15. What is the minimum period for which the lime concrete in the foundation be left wet without the construction of masonry over it?

16 / 50

16. Evaluation of building is done based on

17 / 50

17. Rate analysis prepared by the ministry of transport and work includes

18 / 50

18. In the long and short wall method of estimation, the length of the long wall is the center to center space between walls plus

19 / 50

19. The thickness of 25 gauge sheet is

20 / 50

20. The capacity of a flushing cistern is normally

21 / 50

21. The unit of measurement for steel works in trussed and its parts is

22 / 50

22. The unit rate of items written by the contractor in BOQ is in numeral as well as alphabetical form. Which one is preferred?

23 / 50

23. The method of valuation of a building as used by commercial banks is based on:

24 / 50

24. In the case of unsewered areas, an additional provision for a septic tank is usually

25 / 50

25. Which of the following is not considered while preparing the item rate estimate?

26 / 50

26. Specification deals with:

27 / 50

27. The amount of money deposited along with the submission of tender is known as

28 / 50

28. The weight of 10 mm diameter mild steel rod per meter length is equal to

29 / 50

29. Dismantle means

30 / 50

30. A layer of dry bricks put below the foundation concrete, in the case of soft soils, is called

31 / 50

31. For small residential buildings, the cost installation and electrification are made as:

32 / 50

32. Pick up the correct statement

33 / 50

33. Indicating works left in excavated trenches to facilitate the measurement of borrow pits are known as

34 / 50

34. Method of calculating the quantity if which out to out and in to in lengths are considered regardless of calculating through the total center line of the walls, and useful of different thicknesses is called:

35 / 50

35. To account for the corrugation, the plain area of the semi-corrugated asbestos sheet is increased by (for whitewashing)

36 / 50

36. The value of property that can be obtained when the property is put for sale is known as:

37 / 50

37. Compound amount of Rs. 100 in 4 years @ 4% interest

38 / 50

38. The area of the segmental portion of an arch with span I and rise r is approximately given by

39 / 50

39. How many kilo-liters are in one cubic meter?

40 / 50

40. If the payment of annuity begins after some years in future, it is known as

41 / 50

41. The fundamental units in the metric system are:

42 / 50

42. The concealed faces of the frames of doors and windows are painted with

43 / 50

43. When engineering departments undertake the works of other departments, the amount charged toward design, supervision, and execution, etc., is called

44 / 50

44. The unit of payment for excavation trenches for pipes, cables, etc., up to 1.5 m depth in ordinary rock/hard rock is

45 / 50

45. Which one information is not found in specification?

46 / 50

46. The main target of a contractor is to

47 / 50

47. In the center line method of working out volumes, for cross walls, what deductions must be made from the center line length at each junction?

48 / 50

48. Minimum side lap required for asbestos cement sheets is

49 / 50

49. The document showing the account of work done or supply of material, including the particulars and quantities, is called

50 / 50

50. 1 British gallon=.........litres.

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Scroll to Top