Estimating & Costing Online Test - Paper 3 » Ultimate Challenge
GKaim: Measure | Improve | Achieve

Estimating & Costing Online Test – Paper 3

0%
Created by 83a36dcfd5c4caff12bc80f0020c9c749e12cbbbdb7c406dc1dd39996cb85836?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get fresh, new questions in each attempt.

  • Total Questions: 50
  • Time Allotted: 50 minutes
  • Passing Score: 70%
  • Randomization: Yes
  • Certificate: Yes
  • Do not refresh the page!
  • 👍 All the best!

1 / 50

1. The unit of payment for roadside brick edging to increase the pavement width is

2 / 50

2. In the long and short wall method of estimation, the length of the long wall is the center to center space between walls plus

3 / 50

3. A layer of dry bricks put below the foundation concrete, in the case of soft soils, is called

4 / 50

4. Arrange the specific weights of wood (w), cement (c), steel (s), and coarse aggregate (A) in increasing order

5 / 50

5. Compound amount of Rs. 100 in 4 years @ 4% interest

6 / 50

6. The weight of 10 mm diameter mild steel rod per meter length is equal to

7 / 50

7. The thickness of slabs and beams must be measured to the nearest

8 / 50

8. The building material brick

9 / 50

9. Which of the following is known as job overhead?

10 / 50

10. The rate of an item of work depends

11 / 50

11. Minimum size of the pipe connected to the septic tank is

12 / 50

12. Centre line method is specially adopted for estimating... Buildings.

13 / 50

13. Liquidated damage is directly related to

14 / 50

14. The number of corrugations in an asbestos cement sheet is usually

15 / 50

15. Specifications of any works are required only when the work is carried out by:

16 / 50

16. Evaluation of building is done based on

17 / 50

17. In which of the following works, the work turned in cu.m per mason per day will be the least?

18 / 50

18. An estimate is:

19 / 50

19. When not specified, the volume of steel in R.C.C work is taken as

20 / 50

20. In the specification of earthwork in foundation trenches, drains, etc. lead specified is (IS code)

21 / 50

21. In the specification of earthwork in foundation trenches, drains, etc. lift ordinarily specified is

22 / 50

22. The unit of measurement for electric wiring or electrification light, fan plug points is

23 / 50

23. Full payment of the contractor is done

24 / 50

24. Payment of the steel is done by

25 / 50

25. How many kilo-liters are in one cubic meter?

26 / 50

26. The value shown in the account book after allowing necessary depreciation is known as

27 / 50

27. The weight of cement in one bag is

28 / 50

28. Dismantle means

29 / 50

29. When additional works are added to the original works, the estimate is called:

30 / 50

30. In CGI sheet roofing, the overlap along the length of the sheet should not be less than?

31 / 50

31. The gradual accumulation of amounts by way of annual periodic deposits, which is meant for the replacement of the structure at the end of its useful life period, is known as

32 / 50

32. The life of teak wood doors and windows is usually taken to be

33 / 50

33. Pick up the correct statement

34 / 50

34. According to ISI method of measurement, the order of sequence is:

35 / 50

35. The number of skilled and unskilled manpower required for the fabrication of one metric ton steel (Norms prepared by DoR) is

36 / 50

36. Generally, the unit of measurement for partition walls is

37 / 50

37. The area of the segmental portion of an arch with span I and rise r is approximately given by

38 / 50

38. Which one area must be greater at any floor of a building?

39 / 50

39. According to ISI method of measurement, the order is in the sequence

40 / 50

40. Specification deals with:

41 / 50

41. Plinth area of a building does not include:

42 / 50

42. The thickness of 25 gauge sheet is

43 / 50

43. The nominal lead and lift allowed for the earthwork in the excavations of the foundations are

44 / 50

44. The chairman of the material rate fixation committee in the district is

45 / 50

45. The value of the property (without being disassembled) at the end of the useful life period is known as

46 / 50

46. Indicating works left in excavated trenches to facilitate the measurement of borrow pits are known as

47 / 50

47. Specification is the

48 / 50

48. If valuable properties are found during excavation, it becomes the property of

49 / 50

49. The actual size of the modular brick (as per IS Code) is

50 / 50

50. Which one information is found through specification?

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Scroll to Top