Estimating & Costing Online Test - Paper 3 » Ultimate Challenge
GKaim: Measure. Improve. Achieve.

Estimating & Costing Online Test – Paper 3

0%
Created by 83a36dcfd5c4caff12bc80f0020c9c749e12cbbbdb7c406dc1dd39996cb85836?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get fresh, new questions in each attempt.

  • Total Questions: 50
  • Time Allotted: 50 minutes
  • Passing Score: 70%
  • Randomization: Yes
  • Certificate: Yes
  • Do not refresh the page!
  • 👍 All the best!

1 / 50

1. In the specification of earthwork in foundation trenches, drains, etc. lead specified is (IS code)

2 / 50

2. The unit of PVC pipe used in water supply pipeline is

3 / 50

3. 1 He=......Ropani.

4 / 50

4. Valuation is done for:

5 / 50

5. Contractor tax

6 / 50

6. An estimate is:

7 / 50

7. The types of work done by the use of labor but not material, equipment, etc., are known as:

8 / 50

8. Volume is measured correct to the nearest:

9 / 50

9. When it is not specified, the number of holdfasts for a door is usually taken as

10 / 50

10. The unit of payment for A.C. sheet roofing is in

11 / 50

11. The essential requirements to prepare a good estimate are

12 / 50

12. The value of the dismantled material less the cost of dismantling is called

13 / 50

13. Indicating works left in excavated trenches to facilitate the measurement of borrow pits are known as

14 / 50

14. Specifications for the holdfasts are given in terms of

15 / 50

15. The information that can't be included in drawings is conveyed to the estimator through

16 / 50

16. The appropriate cost to the complete labor as a percentage of the total cost of the building is

17 / 50

17. In the long and short wall method of estimation, the length of the long wall is the center to center space between walls plus

18 / 50

18. The unit of payment for blasting of rock including stacking is

19 / 50

19. The building material brick

20 / 50

20. One metric horsepower is equal to

21 / 50

21. The capacity of a flushing cistern is normally

22 / 50

22. The measurement of steel grills is taken in terms of

23 / 50

23. According to ISI method of measurement, the order is in the sequence

24 / 50

24. The weight of cement in one bag is

25 / 50

25. Compound amount of Rs. 100 in 4 years @ 4% interest

26 / 50

26. In CGI sheet roofing, the overlap along the length of the sheet should not be less than?

27 / 50

27. If the payment of annuity begins after some years in future, it is known as

28 / 50

28. According to ISI method of measurement, the order of sequence is:

29 / 50

29. In which of the following works, the work turned in cu.m per mason per day will be the least?

30 / 50

30. Demolition means

31 / 50

31. Due to a change in the price level, a revised estimate is prepared if the sanctioned estimate exceeds:

32 / 50

32. During the calculation of RCC, the amount of steel deducted is

33 / 50

33. The unit of measurement for steel works in trussed and its parts is

34 / 50

34. In the analysis of rates, what percentage of total cost is provided towards water charges?

35 / 50

35. The number of corrugations in an asbestos cement sheet is usually

36 / 50

36. Working out the exact quantities of various items of work is known as

37 / 50

37. The area of the segmental portion of an arch with span I and rise r is approximately given by

38 / 50

38. Plinth area of a building does not include:

39 / 50

39. The explosive for blasting is usually expressed in terms of

40 / 50

40. A fixed stipulated sum of penalty payable by the contractor having no relationship with real damage is known as

41 / 50

41. The unit of payment for fixing of glass panes or cleaning is in

42 / 50

42. In the analysis of rates, the profit and overhead for the contractor are generally taken as

43 / 50

43. Payment of the steel is done by

44 / 50

44. If valuable properties are found during excavation, it becomes the property of

45 / 50

45. Plinth area estimate is an approximate estimate mostly used for the estimation of:

46 / 50

46. The process of calculating the amount of material, labor, and equipment for a unit of work together with overhead and profit for the contractor is:

47 / 50

47. Steel formwork can be used up to about.........times.

48 / 50

48. The expenses of items that do not come under any regular head of items and the cost of unforeseen items are called

49 / 50

49. The value shown in the account book after allowing necessary depreciation is known as

50 / 50

50. The unit of measurement for earthwork in excavation in ordinary soils, earthwork in mixed soil with kankar, bajri, etc., when the depth of excavation does not exceed 30 cm, is

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Scroll to Top