Home» Online Test » Civil Engineering » Estimating & Costing Online Test » Paper 1 » Paper 2 » Paper 3 0% Sorry, time's up. To complete the online test, please restart it. Created by Vikash chaudhary This is a FREE online test. Beware of scammers who ask for money to attend this test. Get fresh, new questions in each attempt. Total Questions: 50 Time Allotted: 50 minutes Passing Score: 70% Randomization: Yes Certificate: Yes Do not refresh the page! 👍 All the best! 1 / 50 1. Estimate is a) the actual cost of construction of a structure b) the probable cost arrived at before the commencement of the structure c) a random guess of the cost of the structure d) none of the above 2 / 50 2. The volume of concrete for a reinforced concrete isolated sloped footing with top and bottom areas equal to A1 and A2 and with a height equal to h is given by: a) V = h/2 [A1+A2+(√A1A2)] b) V = h/3 [A1+A2+(√A1A2)] c) V = h/3 [A1+A2] d) V = h/3 [A1+A2+2A1A2] 3 / 50 3. Pick up the correct statement a) pointing is measured in sq. m. b) plastering is measured in sq. m. c) glazing is measured in sq. m. d) all of the above 4 / 50 4. Plinth area estimate is an approximate estimate mostly used for the estimation of: a) Bridges b) Irrigation channel c) Building d) Road 5 / 50 5. In which of the following works, the work turned in cu.m per mason per day will be the least? a) Random rubble masonry in lime mortar b) Stone arch work c) Brick masonry in superstructure d) Brick masonry in parapet wall 6 / 50 6. The unit of measurement for beading provided in door and window frame, rafters, etc., is a) metre b) cm c) quintal d) cu m 7 / 50 7. In the analysis of rates, the profit and overhead for the contractor are generally taken as a) 20% b) 15% c) 10% d) 5% 8 / 50 8. Liquidated damage is directly related to a) Terms of condition b) Real damages c) Cost of the project d) Depreciation 9 / 50 9. Steel formwork can be used up to about.........times. a) 35 b) 40 c) 45 d) 50 10 / 50 10. Which one area must be greater at any floor of a building? a) Carpet area b) Plinth area c) Floor area d) None of the above 11 / 50 11. Dismantle means a) Same as dismantle b) Breaking up the structure c) Breaking up the structure with care d) All of the above 12 / 50 12. If the payment of annuity begins after some years in future, it is known as a) deferred annuity b) Delayed annuity c) readjusted annuity d) Regulated annuity 13 / 50 13. 1 British gallon=.........litres. a) 4.546 b) 3.785 c) 5.456 d) 7.385 14 / 50 14. The information that can't be included in drawings is conveyed to the estimator through a) Specifications b) Cover note c) Progress chart d) None of the above 15 / 50 15. One metric horsepower is equal to a) 1.36 kW b) 0.736 kW c) 1.736 kW d) 0.746 kW 16 / 50 16. The unit of payment for excavation trenches for pipes, cables, etc., up to 1.5 m depth in ordinary rock/hard rock is a) cu m b) sq m c) metre d) tonne 17 / 50 17. The number of corrugations in a galvanized corrugated sheet is usually a) 6 b) 8 c) 10 d) 12 18 / 50 18. Which one information is found through specification? a) Nature of works b) Quality of materials c) Types of workmanship d) All of the above 19 / 50 19. In the long and short wall method of estimation, the length of the long wall is the center to center space between walls plus a) breadth of the wall b) half of the breadth of the wall on each side c) one-fourth of the breadth of the wall on each side d) none of the above 20 / 50 20. During the excavation of soil, some portion is left without disturbing, which is known as a) Dead man b) Motam c) Tell-tale d) All of the above 21 / 50 21. Specifications for the holdfasts are given in terms of a) Number b) Weight c) Volume d) Length 22 / 50 22. Specification deals with: a) Quantity of materials b) Quantity of materials with procedures c) Quality of material, measurement system & working procedures d) Quality of material with compact condition located in the heart of the city 23 / 50 23. The minimum number of hinges provided in a door and window shutter should be a) 2 and 1 b) 2 and 2 c) 2 and 3 d) 3 and 2 24 / 50 24. The order of booking dimension is: a) Length, breadth, height b) Breadth, height, length c) Length, height, breadth d) Height, breadth, length 25 / 50 25. The number of skilled and unskilled manpower required for the fabrication of one metric ton steel (Norms prepared by DoR) is a) 2,9 b) 3,9 c) 4,9 d) 5,9 26 / 50 26. The minimum space left from the property line (In Kathmandu valley) for the provision of window/door is a) 1 m b) 3 ft c) 5 ft d) 7 ft 27 / 50 27. In detailed measurement, the sequence of dimensions is written: a) L x B x H b) B x H x L c) H x L x B d) B x L x H 28 / 50 28. In the specification of earthwork in foundation trenches, drains, etc. lift ordinarily specified is a) 30 m b) 1.5 m c) 5 m d) 3 m 29 / 50 29. An estimate is: a) The calculation of quantities required item construction of a work b) The computation of expenditure likely to be incurred in the construction of a work c) Both of the above d) None of the above 30 / 50 30. The measurement of steel grills is taken in terms of a) weight b) none of the above c) area d) volume 31 / 50 31. Which of the following is known as general overhead? a) Losses on advance b) Interest on investment c) Traveling Express d) Amenities to the labor 32 / 50 32. Contractor profit is added to a) Detailed estimate b) Rate analysis c) Valuation d) Salvage 33 / 50 33. The value of the property (without being disassembled) at the end of the useful life period is known as a) Scrap value b) Salvage value c) Junk value d) Book value 34 / 50 34. A fixed stipulated sum of penalty payable by the contractor having no relationship with real damage is known as a) Fixed penalty b) Liquidated damages c) Damage charges d) Compensatory payment 35 / 50 35. Providing and assembling in position false work for the construction of RCC superstructure is measured in: a) Meter b) Square meter c) Cubic meter d) Kg 36 / 50 36. The tender is: a) A notice inviting bids b) A written offer submitted by a contractor to execute works c) An agreement enforceable by law d) None of the above 37 / 50 37. Compound amount of Rs. 100 in 4 years @ 4% interest a) Rs.116 b) Rs.114 c) Rs.117 d) Rs.120 38 / 50 38. Salvage value of any structure is a) Less than the scrap value b) More than the scrap value c) Equal to the scrap value d) All of the above 39 / 50 39. Method of calculating the quantity if which out to out and in to in lengths are considered regardless of calculating through the total center line of the walls, and useful of different thicknesses is called: a) Center line method b) Crossing method c) Long wall and short wall method d) Differentiated method 40 / 50 40. How many kilo-liters are in one cubic meter? a) 0.5 b) 1 c) 10 d) 100 41 / 50 41. The expenses of items that do not come under any regular head of items and the cost of unforeseen items are called a) Lump-sum b) Extras c) Customary charges d) Contingencies 42 / 50 42. Volume is measured correct to the nearest: a) 0.01 cum b) 0.02 cum c) 0.03 cum d) 0.04 cum 43 / 50 43. During the calculation of RCC, the amount of steel deducted is a) 3% of the total steel b) 5% of the total steel c) 10% of the total steel d) 0% of the total steel 44 / 50 44. The standard width of an asbestos cement corrugated sheet is a) 0.9 m b) 1.05 m c) 1.2 m d) 1.35 m 45 / 50 45. The value of the dismantled material less the cost of dismantling is called a) Scrap value b) Salvation value c) Rateable value d) None of the above 46 / 50 46. For estimating painting area for iron grillwork over a door or window opening, the area measured will be: a) 1.00 × the area of the opening between door/window frame b) 1.25 × the area of the opening between door/window frame c) 1.50 × the area of the opening between door/window frame d) 2.00 × the area of the opening between door/window frame 47 / 50 47. In the analysis of rates, what percentage of total cost is provided towards water charges? a) 5% b) 7.50% c) 1.50% d) 10% 48 / 50 48. The gradual accumulation of amounts by way of annual periodic deposits, which is meant for the replacement of the structure at the end of its useful life period, is known as a) Annuity depreciation b) Depreciation c) Sinking fund d) Solatium 49 / 50 49. For brick construction, the lime-sand mortar is a) 1:01 b) 1:02 c) 2:01 d) 1:03 50 / 50 50. The full form of VAT is a) Variation at tax b) Voucher and tax c) Value-added tax d) Violation and taxation Please provide accurate information so we can send your Achievement Certificate by mail. NameEmailPhone Number Your score isShare your achievement! LinkedIn Facebook 0% Restart Test Please provide your feedback. Thank you for your valuable feedback. Send feedback Buy Estimating & Costing MCQ PDF for Offline Study