Estimating & Costing Online Test - Paper 3 » Ultimate Challenge
GK Aim: A Treasure of MCQs

Estimating & Costing Online Test – Paper 3

0%
Created by 83a36dcfd5c4caff12bc80f0020c9c749e12cbbbdb7c406dc1dd39996cb85836?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get fresh, new questions in each attempt.

  • Total Questions: 50
  • Time Allotted: 50 minutes
  • Passing Score: 70%
  • Randomization: Yes
  • Certificate: Yes
  • Do not refresh the page!
  • 👍 All the best!

1 / 50

1. Providing and assembling in position false work for the construction of RCC superstructure is measured in:

2 / 50

2. Payment of the steel is done by

3 / 50

3. The number of standard bricks in one cubic meter of masonry is:

4 / 50

4. In the analysis of rates, the profit and overhead for the contractor are generally taken as

5 / 50

5. Which one information is found through specification?

6 / 50

6. The unit of payment for A.C. sheet roofing is in

7 / 50

7. For small residential buildings, the cost installation and electrification are made as:

8 / 50

8. Which of the following is known as job overhead?

9 / 50

9. Minimum side lap required for asbestos cement sheets is

10 / 50

10. Following items of earthwork are not measured separately

11 / 50

11. The unit rate of items written by the contractor in BOQ is in numeral as well as alphabetical form. Which one is preferred?

12 / 50

12. The concealed faces of the frames of doors and windows are painted with

13 / 50

13. When engineering departments undertake the works of other departments, the amount charged toward design, supervision, and execution, etc., is called

14 / 50

14. Of the total estimated cost of a building, the cost of electrification usually accounts for

15 / 50

15. The unit of measurement for concrete work in R.C.C. is

16 / 50

16. The process of calculating the amount of material, labor, and equipment for a unit of work together with overhead and profit for the contractor is:

17 / 50

17. Steel formwork can be used up to about.........times.

18 / 50

18. The quantity of work of any item which is the output of a skilled labor in a day is known as

19 / 50

19. For brick construction, the lime-sand mortar is

20 / 50

20. Specifications of any works are required only when the work is carried out by:

21 / 50

21. The actual weight of cement bag is more in case of

22 / 50

22. Rate analysis prepared by the ministry of transport and work includes

23 / 50

23. The main target of a contractor is to

24 / 50

24. The rate of an item of work depends

25 / 50

25. Salvage value of any structure is

26 / 50

26. In the center line method of working out volumes, for cross walls, what deductions must be made from the center line length at each junction?

27 / 50

27. The full form of VAT is

28 / 50

28. The weight of cement in one bag is

29 / 50

29. The most reliable estimate is:

30 / 50

30. The number of corrugations in an asbestos cement sheet is usually

31 / 50

31. According to ISI method of measurement, the order is in the sequence

32 / 50

32. The volume of concrete for a reinforced concrete isolated sloped footing with top and bottom areas equal to A1 and A2 and with a height equal to h is given by:

33 / 50

33. The portion which is wrongly excavated by the contractor is to be filled

34 / 50

34. What is the minimum period for which the lime concrete in the foundation be left wet without the construction of masonry over it?

35 / 50

35. The technique of finding the fair price of an existing building or property is known as

36 / 50

36. The unit of measurement for woodwork in door and window frame, rafters, beams, roof trusses, etc., is

37 / 50

37. In CGI sheet roofing, the overlap along the length of the sheet should not be less than?

38 / 50

38. The fundamental units in the metric system are:

39 / 50

39. The minimum space left from the property line (In Kathmandu valley) for the provision of window/door is

40 / 50

40. The number of skilled and unskilled manpower required for the fabrication of one metric ton steel (Norms prepared by DoR) is

41 / 50

41. Normally which one contract gives the maximum value of the project

42 / 50

42. In which of the following works, the work turned in cu.m per mason per day will be the least?

43 / 50

43. Minimum size of the pipe connected to the septic tank is

44 / 50

44. One metric horsepower is equal to

45 / 50

45. For estimating painting area for iron grillwork over a door or window opening, the area measured will be:

46 / 50

46. In a sanitary pipeline for 3 m length, how many skilled labor are required

47 / 50

47. The unit of measurement for steel works in trussed and its parts is

48 / 50

48. The appropriate cost to the complete labor as a percentage of the total cost of the building is

49 / 50

49. The amount of money deposited along with the submission of tender is known as

50 / 50

50. Tender does not contain

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook Twitter
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments
Scroll to Top