Estimating & Costing Online Test - Paper 3 » Ultimate Challenge
GKaim: Measure | Improve | Achieve

Estimating & Costing Online Test – Paper 3

0%
Created by 83a36dcfd5c4caff12bc80f0020c9c749e12cbbbdb7c406dc1dd39996cb85836?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get fresh, new questions in each attempt.

  • Total Questions: 50
  • Time Allotted: 50 minutes
  • Passing Score: 70%
  • Randomization: Yes
  • Certificate: Yes
  • Do not refresh the page!
  • 👍 All the best!

1 / 50

1. Minimum side lap required for asbestos cement sheets is

2 / 50

2. In the analysis of rates, what percentage of total cost is provided towards water charges?

3 / 50

3. 1 He=......Ropani.

4 / 50

4. The estimated quantity of cement required in cement mortar (1:6) per cubic meter will be

5 / 50

5. The rate of an item of work depends

6 / 50

6. The main target of a contractor is to

7 / 50

7. In the case of a roof truss made of steel, rivets, bolts, nuts, etc., normally account for

8 / 50

8. Work-charged establishment

9 / 50

9. Due to a change in the price level, a revised estimate is prepared if the sanctioned estimate exceeds:

10 / 50

10. Specifications of any works are required only when the work is carried out by:

11 / 50

11. The unit of measurement for electric wiring or electrification light, fan plug points is

12 / 50

12. The process of calculating the amount of material, labor, and equipment for a unit of work together with overhead and profit for the contractor is:

13 / 50

13. The nominal lead and lift allowed for the earthwork in the excavations of the foundations are

14 / 50

14. The minimum space left from the property line (In Kathmandu valley) for the provision of window/door is

15 / 50

15. The appropriate cost to the complete labor as a percentage of the total cost of the building is

16 / 50

16. The minimum number of hinges provided in a door and window shutter should be

17 / 50

17. When it is not specified, the number of holdfasts for a door is usually taken as

18 / 50

18. A layer of dry bricks put below the foundation concrete, in the case of soft soils, is called

19 / 50

19. One metric horsepower is equal to

20 / 50

20. Indicating works left in excavated trenches to facilitate the measurement of borrow pits are known as

21 / 50

21. Working out the exact quantities of various items of work is known as

22 / 50

22. In the specification of earthwork in foundation trenches, drains, etc. lead specified is (IS code)

23 / 50

23. As per norms prepared by the ministry of transport & works, one porter can carry a weight of

24 / 50

24. The unit of PVC pipe used in water supply pipeline is

25 / 50

25. The information that can't be included in drawings is conveyed to the estimator through

26 / 50

26. In detailed measurement, the sequence of dimensions is written:

27 / 50

27. Approximate weight of 1 cubic meter of sand is

28 / 50

28. Which of the following is not a common size of reinforcement bars?

29 / 50

29. End lap provided in asbestos cements is equal to

30 / 50

30. Specification is the

31 / 50

31. The approximate weight of one cubic meter of mild steel is

32 / 50

32. The unit of measurement for concrete work in R.C.C. is

33 / 50

33. The net annual letting out value of a property, which is obtained after deducting the amount of yearly repairs from the gross income, is known as

34 / 50

34. The explosive for blasting is usually expressed in terms of

35 / 50

35. During the excavation of soil, some portion is left without disturbing, which is known as

36 / 50

36. Which one area must be greater at any floor of a building?

37 / 50

37. To account for the corrugation, the plain area of the semi-corrugated asbestos sheet is increased by (for whitewashing)

38 / 50

38. According to ISI method of measurement, the order of sequence is:

39 / 50

39. The actual size of the modular brick (as per IS Code) is

40 / 50

40. Pick up the correct statement

41 / 50

41. Arrange the specific weights of wood (w), cement (c), steel (s), and coarse aggregate (A) in increasing order

42 / 50

42. The weight of 10 mm diameter mild steel rod per meter length is equal to

43 / 50

43. The number of skilled and unskilled manpower required for the fabrication of one metric ton steel (Norms prepared by DoR) is

44 / 50

44. If the payment of annuity begins after some years in the future, it is known as

45 / 50

45. How many kilo-liters are in one cubic meter?

46 / 50

46. According to ISI method of measurement, the order is in the sequence

47 / 50

47. The depreciation of the value of the building costs are generally not considered for the initial:

48 / 50

48. The useful part of the livable area of a building is also known as

49 / 50

49. The annual periodic payments made for the repayment of the capital invested are known as

50 / 50

50. Generally, the unit of measurement for partition walls is

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Scroll to Top