Estimating & Costing Online Test - Paper 3 » Ultimate Challenge
GKaim: Measure | Improve | Achieve

Estimating & Costing Online Test – Paper 3

0%
Created by 83a36dcfd5c4caff12bc80f0020c9c749e12cbbbdb7c406dc1dd39996cb85836?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get fresh, new questions in each attempt.

  • Total Questions: 50
  • Time Allotted: 50 minutes
  • Passing Score: 70%
  • Randomization: Yes
  • Certificate: Yes
  • Do not refresh the page!
  • 👍 All the best!

1 / 50

1. The unit of measurement for earthwork in excavation in ordinary soils, earthwork in mixed soil with kankar, bajri, etc., when the depth of excavation does not exceed 30 cm, is

2 / 50

2. When engineering departments undertake the works of other departments, the amount charged toward design, supervision, and execution, etc., is called

3 / 50

3. The unit of measurement for concrete work in R.C.C. is

4 / 50

4. The unit of measurement for woodwork in door and window frame, rafters, beams, roof trusses, etc., is

5 / 50

5. In detailed measurement, the sequence of dimensions is written:

6 / 50

6. When not specified, the volume of steel in R.C.C work is taken as

7 / 50

7. Specifications for the holdfasts are given in terms of

8 / 50

8. Whenever color washing on A.C. corrugated sheets is done, in the estimation, the plan area of the sheets is increased by

9 / 50

9. The weight of cement in one bag is

10 / 50

10. Actual cost of construction plus certain profit is paid to the contractor. Such a contract is known as

11 / 50

11. Specification deals with:

12 / 50

12. The value of the property (without being disassembled) at the end of the useful life period is known as

13 / 50

13. The useful part of the livable area of a building is also known as

14 / 50

14. Bill of quantities is prepared based on:

15 / 50

15. The unit of PVC pipe used in water supply pipeline is

16 / 50

16. One metric horsepower is equal to

17 / 50

17. The tender is:

18 / 50

18. Which of the following is known as job overhead?

19 / 50

19. The value of the dismantled material less the cost of dismantling is called

20 / 50

20. Plinth area estimate is an approximate estimate mostly used for the estimation of:

21 / 50

21. Contractor profit is added to

22 / 50

22. The measurement of steel grills is taken in terms of

23 / 50

23. The rate of an item of work depends

24 / 50

24. During the calculation of RCC, the amount of steel deducted is

25 / 50

25. Of the total estimated cost of a building, the cost of electrification usually accounts for

26 / 50

26. Steel formwork can be used up to about.........times.

27 / 50

27. The standard width of an asbestos cement corrugated sheet is

28 / 50

28. The standard width of the galvanized iron sheet is

29 / 50

29. The method of valuation of a building as used by commercial banks is based on:

30 / 50

30. The unit of payment for excavation trenches for pipes, cables, etc., up to 1.5 m depth in ordinary rock/hard rock is

31 / 50

31. The value shown in the account book after allowing necessary depreciation is known as

32 / 50

32. Normally which one contract gives the maximum value of the project

33 / 50

33. Compound amount of Rs. 100 in 4 years @ 4% interest

34 / 50

34. In the analysis of rates, the profit and overhead for the contractor are generally taken as

35 / 50

35. The number of corrugations in an asbestos cement sheet is usually

36 / 50

36. A layer of dry bricks put below the foundation concrete, in the case of soft soils, is called

37 / 50

37. In the case of a roof truss made of steel, rivets, bolts, nuts, etc., normally account for

38 / 50

38. To account for the corrugation, the plain area of the semi-corrugated asbestos sheet is increased by (for whitewashing)

39 / 50

39. A document showing the list of quantity of various items of works required for the completion of any project is known as

40 / 50

40. The unit of payment for fixing of glass panes or cleaning is in

41 / 50

41. For electric wiring such as a fan, light, plug, etc., the estimate is made in terms of

42 / 50

42. The process of calculating the amount of material, labor, and equipment for a unit of work together with overhead and profit for the contractor is:

43 / 50

43. Providing and assembling in position false work for the construction of RCC superstructure is measured in:

44 / 50

44. The gradual accumulation of amounts by way of annual periodic deposits, which is meant for the replacement of the structure at the end of its useful life period, is known as

45 / 50

45. Which of the following is not a common size of reinforcement bars?

46 / 50

46. The number of corrugations in a galvanized corrugated sheet is usually

47 / 50

47. Valuation is done for:

48 / 50

48. The approximate weight of one cubic meter of mild steel is

49 / 50

49. The depreciation of the value of the building costs are generally not considered for the initial:

50 / 50

50. Which one information is not found in specification?

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Scroll to Top