Estimating & Costing Online Test – Paper 3

0%
Created by 83a36dcfd5c4caff12bc80f0020c9c749e12cbbbdb7c406dc1dd39996cb85836?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get New Questions in Each Attempt

  • Total Questions: 50
  • Time Allotted: 50 minutes
  • Passing Score: 70%
  • Randomization: Yes
  • Certificate: Yes
  • Do not refresh the page!
  • 👍 All the best!

1 / 50

1. The life of teak wood doors and windows is usually taken to be

2 / 50

2. Which of the following is the most correct estimate

3 / 50

3. The value of property that can be obtained when the property is put for sale is known as:

4 / 50

4. The essential requirements to prepare a good estimate are

5 / 50

5. In the center line method of working out volumes, for cross walls, what deductions must be made from the center line length at each junction?

6 / 50

6. One metric horsepower is equal to

7 / 50

7. Which one information is found through specification?

8 / 50

8. If the payment of annuity begins after some years in the future, it is known as

9 / 50

9. Whenever color washing on A.C. corrugated sheets is done, in the estimation, the plan area of the sheets is increased by

10 / 50

10. The unit of PVC pipe used in water supply pipeline is

11 / 50

11. What is the minimum period for which the lime concrete in the foundation be left wet without the construction of masonry over it?

12 / 50

12. The unit of measurement for woodwork in door and window frame, rafters, beams, roof trusses, etc., is

13 / 50

13. In detailed measurement, the sequence of dimensions is written:

14 / 50

14. Plinth area estimate is an approximate estimate mostly used for the estimation of:

15 / 50

15. In the long and short wall method of estimation, the length of the long wall is the center to center space between walls plus

16 / 50

16. Specification is the

17 / 50

17. How many kilo-liters are in one cubic meter?

18 / 50

18. The concealed faces of the frames of doors and windows are painted with

19 / 50

19. During the calculation of RCC, the amount of steel deducted is

20 / 50

20. Specification deals with:

21 / 50

21. Actual cost of construction plus certain profit is paid to the contractor. Such a contract is known as

22 / 50

22. The main target of a contractor is to

23 / 50

23. The useful part of the livable area of a building is also known as

24 / 50

24. Payment of the steel is done by

25 / 50

25. Compound amount of Rs. 100 in 4 years @ 4% interest

26 / 50

26. A document containing a detailed description of all types of work (but their quantities are not mentioned) together with their current rates is called

27 / 50

27. The weight of 10 mm diameter mild steel rod per meter length is equal to

28 / 50

28. For brick construction, the lime-sand mortar is

29 / 50

29. The number of standard bricks in one cubic meter of masonry is:

30 / 50

30. Which of the following is not a common size of reinforcement bars?

31 / 50

31. The unit of payment for fixing of glass panes or cleaning is in

32 / 50

32. The standard width of the galvanized iron sheet is

33 / 50

33. Carpet area does not include the area of

34 / 50

34. According to ISI method of measurement, the order of sequence is:

35 / 50

35. In the analysis of rates, what percentage of total cost is provided towards water charges?

36 / 50

36. The minimum number of hinges provided in a door and window shutter should be

37 / 50

37. A document showing the list of quantity of various items of works required for the completion of any project is known as

38 / 50

38. The nominal lead and lift allowed for the earthwork in the excavations of the foundations are

39 / 50

39. To account for the corrugation, the plain area of the semi-corrugated asbestos sheet is increased by (for whitewashing)

40 / 50

40. The minimum space left from the property line (In Kathmandu valley) for the provision of window/door is

41 / 50

41. The unit of measurement for electric wiring or electrification light, fan plug points is

42 / 50

42. In the specification of earthwork in foundation trenches, drains, etc. lift ordinarily specified is

43 / 50

43. The area of the segmental portion of an arch with span I and rise r is approximately given by

44 / 50

44. Approximate weight of 1 cubic meter of sand is

45 / 50

45. The gradual accumulation of amounts by way of annual periodic deposits, which is meant for the replacement of the structure at the end of its useful life period, is known as

46 / 50

46. Valuation is done for:

47 / 50

47. Which of the following is known as general overhead?

48 / 50

48. Specifications of any works are required only when the work is carried out by:

49 / 50

49. Due to a change in the price level, a revised estimate is prepared if the sanctioned estimate exceeds:

50 / 50

50. In CGI sheet roofing, the overlap along the length of the sheet should not be less than?

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook Twitter
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments
0
Join Discussionsx
()
x
Scroll to Top