Estimating & Costing Online Test - Paper 3 » Ultimate Challenge
GK Aim: A Treasure of MCQs

Estimating & Costing Online Test – Paper 3

0%
Created by 83a36dcfd5c4caff12bc80f0020c9c749e12cbbbdb7c406dc1dd39996cb85836?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get fresh, new questions in each attempt.

  • Total Questions: 50
  • Time Allotted: 50 minutes
  • Passing Score: 70%
  • Randomization: Yes
  • Certificate: Yes
  • Do not refresh the page!
  • 👍 All the best!

1 / 50

1. The explosive for blasting is usually expressed in terms of

2 / 50

2. The actual size of the modular brick (as per IS Code) is

3 / 50

3. Carpet area does not include the area of

4 / 50

4. The unit of measurement for electric wiring or electrification light, fan plug points is

5 / 50

5. The method of valuation of a building as used by commercial banks is based on:

6 / 50

6. The area of the segmental portion of an arch with span I and rise r is approximately given by

7 / 50

7. Valuation is done for:

8 / 50

8. The estimated quantity of cement required in cement mortar (1:6) per cubic meter will be

9 / 50

9. Evaluation of building is done based on

10 / 50

10. The unit of measurement for earthwork in excavation in ordinary soils, earthwork in mixed soil with kankar, bajri, etc., when the depth of excavation does not exceed 30 cm, is

11 / 50

11. The minimum number of hinges provided in a door and window shutter should be

12 / 50

12. The unit of payment for blasting of rock including stacking is

13 / 50

13. What is the minimum period for which the lime concrete in the foundation be left wet without the construction of masonry over it?

14 / 50

14. Centre line method is specially adopted for estimating... Buildings.

15 / 50

15. In the case of steel rolling shutters, for the estimation of the painted area, the plain area is multiplied by

16 / 50

16. The volume of concrete for a reinforced concrete isolated sloped footing with top and bottom areas equal to A1 and A2 and with a height equal to h is given by:

17 / 50

17. In CGI sheet roofing, the overlap along the length of the sheet should not be less than?

18 / 50

18. Which of the following is known as general overhead?

19 / 50

19. The value of the property (without being disassembled) at the end of the useful life period is known as

20 / 50

20. The unit of payment for A.C. sheet roofing is in

21 / 50

21. Which of the following is the most correct estimate

22 / 50

22. Which of the followings is not an essential part of the general specification of public works?

23 / 50

23. Volume is measured correct to the nearest:

24 / 50

24. Specification is the

25 / 50

25. The unit of measurement for beading provided in door and window frame, rafters, etc., is

26 / 50

26. For estimating painting area for iron grillwork over a door or window opening, the area measured will be:

27 / 50

27. The unit of measurement for woodwork in door and window frame, rafters, beams, roof trusses, etc., is

28 / 50

28. Working out the exact quantities of various items of work is known as

29 / 50

29. 1 British gallon=.........litres.

30 / 50

30. Arrange the specific weights of wood (w), cement (c), steel (s), and coarse aggregate (A) in increasing order

31 / 50

31. Which method is easiest for the estimation of the quantity of material?

32 / 50

32. In which of the following works, the work turned in cu.m per mason per day will be the least?

33 / 50

33. The appropriate cost to the complete labor as a percentage of the total cost of the building is

34 / 50

34. Tender does not contain

35 / 50

35. The most reliable estimate is:

36 / 50

36. In the center line method of working out volumes, for cross walls, what deductions must be made from the center line length at each junction?

37 / 50

37. If the payment of annuity begins after some years in future, it is known as

38 / 50

38. The annual periodic payments made for the repayment of the capital invested are known as

39 / 50

39. Following items of earthwork are not measured separately

40 / 50

40. The full form of VAT is

41 / 50

41. A document containing a detailed description of all types of work (but their quantities are not mentioned) together with their current rates is called

42 / 50

42. The value shown in the account book after allowing necessary depreciation is known as

43 / 50

43. The technique of finding the fair price of an existing building or property is known as

44 / 50

44. Pick up the correct statement

45 / 50

45. The portion which is wrongly excavated by the contractor is to be filled

46 / 50

46. Which one information is not found in specification?

47 / 50

47. In the analysis of rates, what percentage of total cost is provided towards water charges?

48 / 50

48. The types of work done by the use of labor but not material, equipment, etc., are known as:

49 / 50

49. Of the total estimated cost of a building, the cost of electrification usually accounts for

50 / 50

50. For small residential buildings, the cost installation and electrification are made as:

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook Twitter
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments
Scroll to Top