Home» Online Test » Civil Engineering » Construction Management Online Test » Paper 1 » Paper 2 » Paper 3 0% Sorry, time's up. To complete the online test, please restart it. Created by Vikash chaudhary This is a FREE online test. Beware of scammers who ask for money to attend this test. Total Questions: 20 Time Allotted: 30 minutes Passing Score: 40% Randomization: No Certificate: No Do not refresh the page! 👍 All the best! 1 / 20 1. Direct cost of a project is due to: a) Establishment charges such as salaries to administrative staff b) Loss or gain of revenue c) Penalty imposed d) Cost of materials and wages of labor 2 / 20 2. The total cost versus time curve of an activity is: a) A straight line b) A parabola c) U-shaped curve d) Γê⌐-shaped curve 3 / 20 3. Assuming that the cost varies with time, the cost-slope is defined as: a) Crash cost - Normal cost / Crash time b) Crash cost - Normal cost / Normal time c) Crash cost - Normal cost / Normal time - Crash time d) None of the above 4 / 20 4. The reduction in project time normally results in: a) Decreasing the direct cost and increasing indirect cost b) Increasing the direct cost and decreasing the indirect cost c) Increasing the direct cost and indirect cost both d) Decreasing the direct cost and indirect cost both 5 / 20 5. The direct cost of a project with respect to normal time is: a) Maximum b) Minimum c) Zero d) Infinite 6 / 20 6. If the path of activities leads back into itself, the resulting error in the network is known as: a) Looping b) Dangling c) Interfacing d) Splicing 7 / 20 7. At an event other than the final event, if no activity emerges, it results in an error called: a) Looping b) Dangling c) Interfacing d) Splicing 8 / 20 8. In a CPM/PERT network, the number of events is: a) Less than the number of activities b) More than the number of activities c) Equal to the number of activities d) All of the above 9 / 20 9. Which of the following does not represent an activity? a) Site located b) Foundation is being dug c) The office area is being cleaned d) The invitations are being sent 10 / 20 10. Slack time in PERT analysis: a) Can never be greater than zero b) Is always zero for critical activities c) Can never be less than zero d) Is minimum for critical events 11 / 20 11. The square root of the variance is known as: a) Deviation b) Standard deviation c) Mode d) None of the above 12 / 20 12. In PERT analysis, the time estimates of activities and the probability of their occurrence follow: a) Normal distribution curve b) Beta distribution curve c) Poisson distribution curve d) Binomial distribution curve 13 / 20 13. In PERT, the most likely time is: a) The minimum time in which any activity can possibly be accomplished b) The maximum time which an activity might require c) The time which has the highest probability of occurrence d) None of the above 14 / 20 14. In PERT, pessimistic time is: a) The minimum time in which any activity can possibly be accomplished b) The maximum time which an activity might require c) The time which has the highest probability of occurrence d) None of the above 15 / 20 15. In PERT, optimistic time is: a) The minimum time in which any activity can possibly be accomplished b) The maximum time which an activity might require c) The time which has the highest probability of occurrence d) None of the above 16 / 20 16. The pictorial representation of activities and events of a project is known as: a) Net work b) Flow net c) Flow chart d) Algorithm 17 / 20 17. Updating may result in: a) Change of the critical path b) Decrease of project completion time c) Increase of project completion time d) All of the above 18 / 20 18. Policy is: a) A rule or a set of rules never to be violated b) A definite rule along which one has to proceed c) A procedure for preparing the project report d) A set of broad guidelines stipulated by management 19 / 20 19. A construction schedule is prepared after collecting: a) Number of operations b) Output of labor and machinery c) Quantity of various items d) All of the above 20 / 20 20. The most critical stage of construction is the construction of: a) Foundation b) Plinth level c) Beam and slab d) All of the above Your score is Share your achievement! LinkedIn Facebook Twitter 0% Restart Test Please provide your feedback. Thank you for your valuable feedback. Send feedback Share the above MCQs:Click to share on Facebook (Opens in new window)Click to share on WhatsApp (Opens in new window)Click to share on X (Opens in new window)Click to share on LinkedIn (Opens in new window)Click to share on Reddit (Opens in new window)