Construction Management Online Test - Paper 2 » Quiz Test
GKaim: Measure | Improve | Achieve

Construction Management Online Test – Paper 2

0%
Created by 83a36dcfd5c4caff12bc80f0020c9c749e12cbbbdb7c406dc1dd39996cb85836?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get fresh, new questions in each attempt.

  • Total Questions: 30
  • Time Allotted: 30 minutes
  • Passing Score: 50%
  • Randomization: Yes
  • Certificate: No
  • Do not refresh the page!
  • 👍 All the best!

1 / 30

1. Who is responsible for accidents occurring at the site?

2 / 30

2. The occurrence of the starting of an activity is called its:

3 / 30

3. Time and progress chart of construction is known as:

4 / 30

4. The upper portion of horizontal bars in a bar chart indicates:

5 / 30

5. A project is:

6 / 30

6. The cost corresponding to crash time is:

7 / 30

7. The figure indicates:

8 / 30

8. Inspection of construction works for quality control is carried out and covers:

9 / 30

9. Indirect cost of the project:

10 / 30

10. CPM network is:

11 / 30

11. Standard deviation when the optimistic time is 1 day, pessimistic time is 11 days, and most likely time is 3 days:

12 / 30

12. What are the key dates of a standard contracting procedure for a project?

13 / 30

13. Power stations are generally treated as:

14 / 30

14. The reduction in project time normally results in:

15 / 30

15. The time corresponding to the minimum total project cost is:

16 / 30

16. Milestone charts are developed in:

17 / 30

17. Completion of an activity on the CPM network diagram is generally known as:

18 / 30

18. Which of the following is not a part of a contract agreement?

19 / 30

19. Line & staff organization is mostly suitable for:

20 / 30

20. Which operation must complete first?

21 / 30

21. In PERT technique, completion of an activity is called:

22 / 30

22. Whenever an activity has zero total float, then:

23 / 30

23. A golden rule for the procurement of construction work suggests:

24 / 30

24. The difference between the total float and the free float is termed as:

25 / 30

25. Which of the following does not represent an activity?

26 / 30

26. Gantt chart indicates:

27 / 30

27. The number of pre-operations associated with an operation may be:

28 / 30

28. The dispute in construction is resolved through discussion of all parties on their respective stands leading to consensus. The process is called:

29 / 30

29. A contractor can start the construction works following the receipt of:

30 / 30

30. The constraint in the case of resource smoothing operation would be:

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Scroll to Top