Home» Online Test » Civil Engineering » Construction Management Online Test » Paper 1 » Paper 2 » Paper 3 0% Sorry, time's up. To complete the online test, please restart it. Created by Vikash chaudhary This is a FREE online test. Beware of scammers who ask for money to attend this test. Get fresh, new questions in each attempt. Total Questions: 30 Time Allotted: 30 minutes Passing Score: 50% Randomization: Yes Certificate: No Do not refresh the page! 👍 All the best! 1 / 30 1. The district rate finalizing committee does not include the representative of: a) Nepal Engineer's Association, district unit b) District Development Committee c) Contractor's Association d) District Technical Office 2 / 30 2. Insurance provision in GCC is applicable for: a) Loss of damaged material, plants b) Loss of damaged equipment c) Personal death or injury d) All of the above 3 / 30 3. Probability factor in PERT is given by: a) (Scheduled time - Earliest expected time) / Standard deviation b) (Scheduled time - Latest allowable time) / Standard deviation c) (Latest allowable time - Scheduled time) / Standard deviation d) (Latest allowable time - Earliest expected time) / Variance 4 / 30 4. The independent float affects only: a) Preceding activities b) Succeeding activities c) The particular activity d) None of the above 5 / 30 5. The interrelationship between the functional elements of a program is achieved through: a) Work Breakdown Structure b) Bar charts c) Gantt chart d) All of the above 6 / 30 6. CPM family includes: a) Critical Path Analysis (CPA) b) Critical Path Plotted (CPP) c) Critical Path Scheduling (CPS) d) All of the above 7 / 30 7. Frederick W. Taylor introduced a system of working known as: a) Line organization b) Line and staff organization c) Functional organization d) None of the above 8 / 30 8. PERT is: a) Activity-oriented b) Event-oriented c) Time-oriented d) Resources-oriented 9 / 30 9. Line organization is mostly suitable for: a) Simple work b) Complicated work c) Both (a) and (b) above d) None of the above 10 / 30 10. The term CPM in construction management is an abbreviation of: a) Construction Project Management b) Critical Path Method c) Controlling Planning and Maintenance d) Crucial project management 11 / 30 11. The area under the B-curve is divided into two equal parts by: a) Expected time b) Optimistic time c) Pessimistic time d) Most likely time 12 / 30 12. Power stations are generally treated as: a) Light construction b) Heavy construction c) Industrial construction d) None of the above 13 / 30 13. The maximum amount of project cost after the price adjustment should not exceed: a) 15% b) 20% c) 25% d) 30% 14 / 30 14. No agreement is between: a) Client, engineer b) Engineer, contractor c) Client, contractor d) Contractor, sub-contractor 15 / 30 15. Positive float can occur when it is: a) Sub-critical activity b) Critical activity c) Super-critical activity d) Normal activity 16 / 30 16. The duration of time which an activity can be delayed without affecting the succeeding activity is called free float which affects only: a) Preceding activities b) Succeeding activities c) The particular activity d) None of the above 17 / 30 17. When all the paths are arranged according to the descending order of the float, the path which is next to the critical path is known as: a) Under-critical path b) Sub-critical path c) Semi-critical path d) All of the above 18 / 30 18. The time corresponding to the minimum total project cost is: a) Normal time b) Crash time c) Optimistic time d) Between normal and crash time 19 / 30 19. What are the key dates of a standard contracting procedure for a project? a) Call for bidding and contract award b) Call for bidding, bid submission, and bid evaluation c) call for bidding, bid submission, bid evaluation and contract award d) call for bidding, bid submission and contract award 20 / 30 20. Which of the following is not a part of a contract agreement? a) Price schedule b) Work schedule c) Manning schedule d) Cost Estimate 21 / 30 21. The variance will be zero if: a) Each individual deviation is zero b) Sum of deviation is zero c) Standard deviation is zero d) None of the above 22 / 30 22. The dual-role event is: a) Head as well as tail event b) Sum of head and tail event c) Any event other than head and tail event d) None of the above 23 / 30 23. Bar chart is used for minor projects, CPM is used for repetitive work while PERT is used for: a) Repetitive types of work b) Limited time and unlimited resources types of work c) Uncertainty time and resources types of work d) All of the above 24 / 30 24. Which operation must complete first? a) Right of the line joining two circles b) Left of the line joining two circles c) Both of the above d) None of the above 25 / 30 25. The constraint in the case of resource smoothing operation would be: a) On the resources b) Project duration time c) Both (a) and (b) above d) None of the above 26 / 30 26. A drawback of a bar chart is: a) It is difficult to judge whether an activity is completed or not b) All the activities represented are independent of each other c) The sequence of activities is not clearly defined d) It is not possible to judge whether the activity is ahead or behind the schedule. 27 / 30 27. If the completion time for a particular project is 6 weeks and its expected time is 8 weeks, then the slack time for the project is: a) 2 weeks b) -2 weeks c) 0 d) None of the above 28 / 30 28. Choose the incorrect statement: a) Arrow representing activity in CPM network is drawn without any scale b) Head of an activity represents the finish of an activity c) Tail of an activity represents the start of an activity d) None of the above 29 / 30 29. Crash project duration is obtained by adding the: a) Crash durations for all the activities b) Normal duration for all the activities c) Normal duration for all the activities along the critical path d) Crash durations for all the activities along the critical path 30 / 30 30. Total cost of the project is: a) Direct cost and outage loss of project b) Direct cost and overheads c) Direct cost and indirect cost d) None of the above Please provide accurate information so we can send your Achievement Certificate by mail. NameEmailPhone Number Your score isShare your achievement! LinkedIn Facebook 0% Restart Test Please provide your feedback. Thank you for your valuable feedback. Send feedback Buy Construction Management MCQ PDF for Offline Study