Home» Online Test » Civil Engineering » Construction Management Online Test » Paper 1 » Paper 2 » Paper 3 0% Sorry, time's up. To complete the online test, please restart it. Created by GKaim This is a FREE online test. Beware of scammers who ask for money to attend this test. Get fresh, new questions in each attempt. Total Questions: 30 Time Allotted: 30 minutes Passing Score: 50% Randomization: Yes Certificate: No Do not refresh the page! 👍 All the best! 1 / 30 1. The main responsibility of an overseer/Sub-Engineer is: a) To teach the subordinates b) To plan and execute the work c) To understand the duties d) All of the above 2 / 30 2. Negative slack indicates: a) Ahead of schedule condition b) Behind the schedule condition c) On schedule condition d) None of the above 3 / 30 3. Free float is the: a) Portion of independent float b) Portion of positive total float c) Portion of interfering float d) All of the above 4 / 30 4. No agreement is between: a) Client, engineer b) Engineer, contractor c) Client, contractor d) Contractor, sub-contractor 5 / 30 5. For the execution of work in time, a work plan is prepared by: a) Contractor b) Consultant c) Petty contractor d) Financial institution 6 / 30 6. The direct cost of a project with respect to normal time is: a) Maximum b) Minimum c) Zero d) Infinite 7 / 30 7. The upper portion of horizontal bars in a bar chart indicates: a) Total duration for completion of an activity b) Progress of work in the specified time c) Due duration for the completion of an activity d) All of the above 8 / 30 8. Gantt chart is used for: a) Scheduling a project b) Planning a project c) Implementation of a project d) None of the above 9 / 30 9. Latest start of the activity is always: a) Less than or equal to the latest event time of the preceding node b) More than or equal to the latest event time of the preceding node c) Equal to the latest event time of the preceding node d) None of the above 10 / 30 10. Which of the following techniques is advanced and more indicative in modern construction progress review? a) Earned value b) S-curve c) Histogram d) Milestones 11 / 30 11. The benefit of the PERT network is taken by the management in: a) Formulating a new schedule b) Coordinating various tasks c) Readjusting the time to meet the target d) All of the above 12 / 30 12. Type of organization used in the construction industry is: a) Line organization b) Line and staff organization c) Functional organization d) None of the above 13 / 30 13. CPM family includes: a) Critical Path Analysis (CPA) b) Critical Path Plotted (CPP) c) Critical Path Scheduling (CPS) d) All of the above 14 / 30 14. Military organization is known as: a) Line organization b) Line and staff organization c) Functional organization d) None of the above 15 / 30 15. For completion of a project, the critical path of the network represents: a) Minimum time b) Maximum time c) Maximum cost d) Minimum cost 16 / 30 16. Insurance provision in GCC is applicable for: a) Loss of damaged material, plants b) Loss of damaged equipment c) Personal death or injury d) All of the above 17 / 30 17. In PERT, optimistic time is: a) The minimum time in which any activity can possibly be accomplished b) The maximum time which an activity might require c) The time which has the highest probability of occurrence d) None of the above 18 / 30 18. Crash project duration is obtained by adding the: a) Crash durations for all the activities b) Normal duration for all the activities c) Normal duration for all the activities along the critical path d) Crash durations for all the activities along the critical path 19 / 30 19. The final technical authority of a project is: a) Chief engineer (DG) b) Assistant engineer c) Executive engineer d) Superintending engineer 20 / 30 20. The dispute in construction is resolved through discussion of all parties on their respective stands leading to consensus. The process is called: a) Amicable settlement b) Arbitration c) Dispute resolution board d) Dispute adjudication board 21 / 30 21. An event is: a) A definite job b) A definite time interval c) The terminals of an activity d) A definite position of an activity 22 / 30 22. The time below which the duration cannot be further reduced is known as: a) Normal time b) Crash time c) Optimistic time d) Standard time 23 / 30 23. Henry Gantt developed the bar chart technique in: a) 1900 AD b) 1940 AD c) 1957 AD d) 1974 AD 24 / 30 24. The estimated time required to complete an activity is termed as: a) Event b) Duration c) Active time d) Float 25 / 30 25. Critical activities having total float are: a) Positive b) Negative c) Zero d) Equal 26 / 30 26. At an event other than the final event, if no activity emerges, it results in an error called: a) Looping b) Dangling c) Interfacing d) Splicing 27 / 30 27. The total cost versus time curve of an activity is: a) A straight line b) A parabola c) U-shaped curve d) Γê⌐-shaped curve 28 / 30 28. The duration of time which an activity can be delayed without affecting the succeeding activity is called free float which affects only: a) Preceding activities b) Succeeding activities c) The particular activity d) None of the above 29 / 30 29. PERT technique of network analysis is useful for: a) Small projects b) Large projects c) Research and development projects d) All of the above 30 / 30 30. Inspection of construction works for quality control is carried out and covers: a) Sampling, examination, and field testing of materials b) Testing specimens in the laboratory c) Observation of construction equipment and plant d) All of the above Please provide accurate information so we can send your Achievement Certificate by mail. NameEmailPhone Number Your score isShare your achievement! LinkedIn Facebook 0% Restart Test Please provide your feedback. Thank you for your valuable feedback. Send feedback Buy Construction Management MCQ PDF for Offline Study