Home» Online Test » Civil Engineering » Construction Management Online Test » Paper 1 » Paper 2 » Paper 3 0% Sorry, time's up. To complete the online test, please restart it. Created by Vikash chaudhary This is a FREE online test. Beware of scammers who ask for money to attend this test. Get New Questions in Each Attempt Total Questions: 30 Time Allotted: 30 minutes Passing Score: 50% Randomization: Yes Certificate: No Do not refresh the page! 👍 All the best! 1 / 30 1. Restraint is a restriction having: a) Both (a) and (b) above b) Zero duration c) Positive duration d) Negative duration 2 / 30 2. Line of balance technique is used for: a) Planning of a project b) Planning of an activity c) Planning of an event d) Comparison of actual progress with the scheduled progress 3 / 30 3. Gantt chart indicates: a) Balance of work to be done b) Comparison of actual progress with the scheduled progress c) Efficiency progress d) Progressive cost of the project 4 / 30 4. The technique for establishing and maintaining priorities among various jobs of a project is known as: a) Event flow scheduling technique b) Critical ratio scheduling c) Slotting technique for scheduling d) Short interval scheduling 5 / 30 5. Power stations are generally treated as: a) Light construction b) Heavy construction c) Industrial construction d) None of the above 6 / 30 6. Critical activities having total float are: a) Positive b) Negative c) Zero d) Equal 7 / 30 7. The variance will be zero if: a) Each individual deviation is zero b) Sum of deviation is zero c) Standard deviation is zero d) None of the above 8 / 30 8. In time cost optimization using CPM, the crashing of activities along the critical path is done starting with the activity having: a) Highest cost slope b) Least cost slope c) Crashing has no relation with cost slope d) None of the above 9 / 30 9. Jobs going ahead of schedule are conveniently shown in: a) Gantt chart b) Milestone chart c) Pi chart d) None of the above 10 / 30 10. If, for an activity, the optimistic time is 1 day, pessimistic time is 11 days, and the most likely time is 3 days, then the expected time is: a) 3 days b) 4 days c) 5 days d) 6 days 11 / 30 11. In CPM method, the earliest finish is indicated by time on: a) Top right, outside the circle, in a triangle b) Top right, outside the circle, in a rectangle c) Both of the above d) None of the above 12 / 30 12. No agreement is between: a) Client, engineer b) Engineer, contractor c) Client, contractor d) Contractor, sub-contractor 13 / 30 13. Assuming that the cost varies with time, the cost-slope is defined as: a) Crash cost - Normal cost / Crash time b) Crash cost - Normal cost / Normal time c) Crash cost - Normal cost / Normal time - Crash time d) None of the above 14 / 30 14. Railway projects are treated as: a) Light construction b) Heavy construction c) Industrial construction d) None of the above 15 / 30 15. If the path of activities leads back into itself, the resulting error in the network is known as: a) Looping b) Dangling c) Interfacing d) Splicing 16 / 30 16. In CPM analysis: a) Emphasis is given to activities b) Uncertainties are not allowed c) Activities are represented by arrows d) All of the above 17 / 30 17. Insurance provision in GCC is applicable for: a) Loss of damaged material, plants b) Loss of damaged equipment c) Personal death or injury d) All of the above 18 / 30 18. A drawback of a bar chart is: a) It is difficult to judge whether an activity is completed or not b) All the activities represented are independent of each other c) The sequence of activities is not clearly defined d) It is not possible to judge whether the activity is ahead or behind the schedule. 19 / 30 19. The total cost versus time curve of an activity is: a) A straight line b) A parabola c) U-shaped curve d) Γê⌐-shaped curve 20 / 30 20. For the execution of work in time, a work plan is prepared by: a) Contractor b) Consultant c) Petty contractor d) Financial institution 21 / 30 21. Force majeure in a contract is: a) Occurrence of an act beyond the control of both the parties in contract agreement b) Preventing both parties to perform the respective obligation agreed c) Both of the above d) None of the above 22 / 30 22. The scheduled completion time of an operation in CPM chart is mentioned on: a) Left top corner outside the circle b) Left top corner inside the circle c) Both of the above d) None of the above 23 / 30 23. Float is: a) The earliest time by which an activity may commence b) Latest time by which an activity can be delayed without hampering the completion of the project c) Latest allowable time-earliest expected time d) Time available-time required for an activity 24 / 30 24. A frequency distribution curve: a) Having a single lump is called a uninodal curve b) If symmetrical is called a normal curve c) If unsymmetrical is called a skew curve d) All of the above 25 / 30 25. The reduction in project time normally results in: a) Decreasing the direct cost and increasing indirect cost b) Increasing the direct cost and decreasing the indirect cost c) Increasing the direct cost and indirect cost both d) Decreasing the direct cost and indirect cost both 26 / 30 26. Inspection of construction works for quality control is carried out and covers: a) Sampling, examination, and field testing of materials b) Testing specimens in the laboratory c) Observation of construction equipment and plant d) All of the above 27 / 30 27. Which of the following is not a part of a contract agreement? a) Price schedule b) Work schedule c) Manning schedule d) Cost Estimate 28 / 30 28. Higher standard deviations mean: a) Lower uncertainty b) Higher uncertainty c) Medium uncertainty d) All of the above 29 / 30 29. Choose the incorrect statement: a) Arrow representing activity in CPM network is drawn without any scale b) Head of an activity represents the finish of an activity c) Tail of an activity represents the start of an activity d) None of the above 30 / 30 30. The direct cost of a project with respect to normal time is: a) Maximum b) Minimum c) Zero d) Infinite Your score is Share your achievement! LinkedIn Facebook Twitter 0% Restart Test Please provide your feedback. Thank you for your valuable feedback. Send feedback Buy Construction Management MCQ PDF for Offline Study Share the above MCQs: Click to share on Facebook (Opens in new window) Facebook Click to share on WhatsApp (Opens in new window) WhatsApp Click to share on X (Opens in new window) X Click to share on LinkedIn (Opens in new window) LinkedIn Click to share on Reddit (Opens in new window) Reddit