Home» Online Test » Civil Engineering » Construction Management Online Test » Paper 1 » Paper 2 » Paper 3 0% Sorry, time's up. To complete the online test, please restart it. Created by Vikash chaudhary This is a FREE online test. Beware of scammers who ask for money to attend this test. Get fresh, new questions in each attempt. Total Questions: 30 Time Allotted: 30 minutes Passing Score: 50% Randomization: Yes Certificate: No Do not refresh the page! 👍 All the best! 1 / 30 1. An EPC contract means: a) End of planning and construction b) Evaluation, planning, and construction c) Engineering, planning, and construction d) Engineering, procurement, and construction 2 / 30 2. A construction schedule is prepared after collecting: a) Number of operations b) Output of labor and machinery c) Quantity of various items d) All of the above 3 / 30 3. Time and progress chart of construction is known as: a) Bar chart b) Gantt chart c) CPM d) All of the above 4 / 30 4. CPM family includes: a) Critical Path Analysis (CPA) b) Critical Path Plotted (CPP) c) Critical Path Scheduling (CPS) d) All of the above 5 / 30 5. The figure indicates: a) An event b) Activity c) Burst d) Merge 6 / 30 6. In PERT, optimistic time is: a) The minimum time in which any activity can possibly be accomplished b) The maximum time which an activity might require c) The time which has the highest probability of occurrence d) None of the above 7 / 30 7. Which of the following is an activity in a CPM network: a) Concrete cured b) Walls plastered c) Excavation for foundation d) All of the above 8 / 30 8. When the times of earliest finish and the latest finish are equal in an operation, the operation is called: a) Critical b) Float c) Free float d) All of the above 9 / 30 9. The time with which direct cost does not reduce with the increase in time is known as: a) Normal time b) Crash time c) Optimistic time d) Standard time 10 / 30 10. The owner gets assurance of work progress and quality from: a) Supervisor b) Contractor c) Engineer d) Labours 11 / 30 11. The occurrence of the starting of an activity is called its: a) Head event b) Tail event c) Dual-role event d) All of the above 12 / 30 12. A drawback of a bar chart is: a) It is difficult to judge whether an activity is completed or not b) All the activities represented are independent of each other c) The sequence of activities is not clearly defined d) It is not possible to judge whether the activity is ahead or behind the schedule. 13 / 30 13. Total project cost: a) Increases with time b) Decreases with time c) Initially reduces with time and then increases with further increases d) Constant 14 / 30 14. Henry Gantt developed the bar chart technique in: a) 1900 AD b) 1940 AD c) 1957 AD d) 1974 AD 15 / 30 15. The number of pre-operations associated with an operation may be: a) One only b) Two only c) More than one d) Three only 16 / 30 16. In CPM method, the earliest finish is indicated by time on: a) Top right, outside the circle, in a triangle b) Top right, outside the circle, in a rectangle c) Both of the above d) None of the above 17 / 30 17. In PERT technique, completion of an activity is called: a) Head activity b) Head event c) Tail activity d) Tail event 18 / 30 18. In resource leveling, the main constraint would be: a) On the resources b) Project duration time c) Both of the above d) None of the above 19 / 30 19. Negative float can occur when it is: a) Sub-critical activity b) Critical activity c) Super-critical activity d) Normal activity 20 / 30 20. An example of a parallel activity is: a) Completing ground floor and starting first floor construction b) Wall construction and carpentry work of doors and windows c) Completion of flooring and initiating whitewashing d) Digging of a well and construction of a septic tank 21 / 30 21. Assuming that the cost varies with time, the cost-slope is defined as: a) Crash cost - Normal cost / Crash time b) Crash cost - Normal cost / Normal time c) Crash cost - Normal cost / Normal time - Crash time d) None of the above 22 / 30 22. In PERT analysis, the start and end of activity are represented by: a) Activity b) Event c) Task d) Work 23 / 30 23. A fictitious activity with zero duration and no cost used to maintain the sequential order of the activities in the network is known as a: a) Restraint b) Dummy activity c) Event d) All of the above 24 / 30 24. Critical activities having total float are: a) Positive b) Negative c) Zero d) Equal 25 / 30 25. In CPM analysis: a) Emphasis is given to activities b) Uncertainties are not allowed c) Activities are represented by arrows d) All of the above 26 / 30 26. The most critical stage of construction is the construction of: a) Foundation b) Plinth level c) Beam and slab d) All of the above 27 / 30 27. Which method is known as the minimum cost or maximum time schedule method: a) PERT b) CPM c) Bar chart d) All of the above 28 / 30 28. Power stations are generally treated as: a) Light construction b) Heavy construction c) Industrial construction d) None of the above 29 / 30 29. The relation between jobs of a particular type and various durations they have consumed for completion is expressed by: a) Normal distribution curve b) Beta distribution curve c) Frequency distribution curve d) None of the above 30 / 30 30. For a safe working environment in the working site, "Tool Box Talk" is conducted: a) During the work b) At the end of the day's work c) Before the start of the day's work d) During lunch hour Please provide accurate information so we can send your Achievement Certificate by mail. NameEmailPhone Number Your score isShare your achievement! LinkedIn Facebook 0% Restart Test Please provide your feedback. Thank you for your valuable feedback. Send feedback Buy Construction Management MCQ PDF for Offline Study