Home» Online Test » Civil Engineering » Construction Management Online Test » Paper 1 » Paper 2 » Paper 3 0% Sorry, time's up. To complete the online test, please restart it. Created by Vikash chaudhary This is a FREE online test. Beware of scammers who ask for money to attend this test. Get fresh, new questions in each attempt. Total Questions: 30 Time Allotted: 30 minutes Passing Score: 50% Randomization: Yes Certificate: No Do not refresh the page! 👍 All the best! 1 / 30 1. The pictorial representation of activities and events of a project is known as: a) Net work b) Flow net c) Flow chart d) Algorithm 2 / 30 2. The mean of squared deviation from the mean of the distribution is known as: a) Mode b) Standard deviation c) Deviation d) Variance 3 / 30 3. Free float for any activity is defined as the difference between: a) Its latest start time and earliest start time for its successor activity b) Its latest start time and earliest start time c) Its latest finish time and earliest start time for its successor activity d) Its earliest finish time and earliest start time for its successor activity 4 / 30 4. The probability of completion of any activity within its expected time in PERT is: a) 0% b) 50% c) 75% d) 100% 5 / 30 5. Aggregate planning is planning for: a) Single activity b) Double activities c) Whole project d) Events 6 / 30 6. For a safe working environment in the working site, "Tool Box Talk" is conducted: a) During the work b) At the end of the day's work c) Before the start of the day's work d) During lunch hour 7 / 30 7. Earliest finish time of an activity is always: a) Equal to or more than the earliest event time of the following node b) Equal to or less than the earliest event time of the following node c) More than the earliest time of the following node d) None of the above 8 / 30 8. The figure indicates: a) An event b) Activity c) Burst d) Merge 9 / 30 9. The owner gets assurance of work progress and quality from: a) Supervisor b) Contractor c) Engineer d) Labours 10 / 30 10. The direct cost of a project with respect to normal time is: a) Maximum b) Minimum c) Zero d) Infinite 11 / 30 11. A dummy activity in CPM: a) Has no tail event but has only a head event b) Has only a head event but no tail event c) Does not require any resources or any time d) Has no sequence and can be fitted anywhere 12 / 30 12. In PERT analysis, the start and end of activity are represented by: a) Activity b) Event c) Task d) Work 13 / 30 13. Performance security is necessary: a) After contract agreement to a successful bidder b) Before bid opening to all bidders c) During bid opening to all bidders d) Before contract agreement to successful bidders 14 / 30 14. In PERT analysis, the time estimates of activities and the probability of their occurrence follow: a) Normal distribution curve b) Beta distribution curve c) Poisson distribution curve d) Binomial distribution curve 15 / 30 15. Gantt chart is used for: a) Scheduling a project b) Planning a project c) Implementation of a project d) None of the above 16 / 30 16. The occurrence of the starting of an activity is called its: a) Head event b) Tail event c) Dual-role event d) All of the above 17 / 30 17. The minimum number of consulting firms for the direct purchase of services is: a) 2 b) 3 c) 4 d) 5 18 / 30 18. Residential buildings are treated as: a) Light construction b) Heavy construction c) Industrial construction d) None of the above 19 / 30 19. Henry Gantt developed the bar chart technique in: a) 1900 AD b) 1940 AD c) 1957 AD d) 1974 AD 20 / 30 20. Whenever an activity has zero total float, then: a) Free float of the activity must be zero but independent float need not be zero b) Independent float must be zero but free float need not be zero c) Free float and independent float both must be zero d) Free float and independent float both need not be zero. 21 / 30 21. Which of the following is not a part of a contract agreement? a) Price schedule b) Work schedule c) Manning schedule d) Cost Estimate 22 / 30 22. Critical path: a) Is the shortest path b) Is the bad path c) Has the maximum slack d) Has the minimum slack 23 / 30 23. Which of the following does not represent an activity? a) Site located b) Foundation is being dug c) The office area is being cleaned d) The invitations are being sent 24 / 30 24. The activity that consumes maximum time is called: a) Event b) Node c) Critical d) None of the above 25 / 30 25. According to Fulkerson's, the correct event numbers corresponding to events A, B, C, D, E of the network shown in figure 1 are: a) 1, 2, 3, 4, 5, 6, and 7, respectively b) 1, 3, 2, 4, 5, 6, and 7, respectively c) 1, 3, 2, 5, 6, 4 and 6, respectively d) None of the above 26 / 30 26. Power stations are generally treated as: a) Light construction b) Heavy construction c) Industrial construction d) None of the above 27 / 30 27. In CPM analysis: a) Emphasis is given to activities b) Uncertainties are not allowed c) Activities are represented by arrows d) All of the above 28 / 30 28. In PERT, pessimistic time is: a) The minimum time in which any activity can possibly be accomplished b) The maximum time which an activity might require c) The time which has the highest probability of occurrence d) None of the above 29 / 30 29. The time with which direct cost does not reduce with the increase in time is known as: a) Normal time b) Crash time c) Optimistic time d) Standard time 30 / 30 30. The time by which the particular activity can be delayed without affecting the preceding and succeeding activities is known as: a) Interfering float b) Independent float c) Total float d) Free float Please provide accurate information so we can send your Achievement Certificate by mail. NameEmailPhone Number Your score isShare your achievement! LinkedIn Facebook 0% Restart Test Please provide your feedback. Thank you for your valuable feedback. Send feedback Buy Construction Management MCQ PDF for Offline Study