Home» Online Test » Civil Engineering » Construction Management Online Test » Paper 1 » Paper 2 » Paper 3 0% Sorry, time's up. To complete the online test, please restart it. Created by Vikash chaudhary This is a FREE online test. Beware of scammers who ask for money to attend this test. Get fresh, new questions in each attempt. Total Questions: 30 Time Allotted: 30 minutes Passing Score: 50% Randomization: Yes Certificate: No Do not refresh the page! 👍 All the best! 1 / 30 1. The most critical stage of construction is the construction of: a) Foundation b) Plinth level c) Beam and slab d) All of the above 2 / 30 2. No agreement is between: a) Client, engineer b) Engineer, contractor c) Client, contractor d) Contractor, sub-contractor 3 / 30 3. It means the offering, giving, receiving, or soliciting, directly or indirectly, anything of value to influence improperly the actions of another party: a) Corrupt practice b) Fraudulent practice c) Coercive practice d) Collusive practice 4 / 30 4. If a is the optimistic time, b is the pessimistic time, and m is the most likely time, then the average time is equal to: a) (a + b + m) / 6 b) (a + 2b + m) / 6 c) (a + 2b + 4m) / 6 d) (a + 4m + b) / 6 5 / 30 5. The independent float affects only: a) Preceding activities b) Succeeding activities c) The particular activity d) None of the above 6 / 30 6. Whenever an activity has zero total float, then: a) Free float of the activity must be zero but independent float need not be zero b) Independent float must be zero but free float need not be zero c) Free float and independent float both must be zero d) Free float and independent float both need not be zero. 7 / 30 7. Which method is known as the minimum cost or maximum time schedule method: a) PERT b) CPM c) Bar chart d) All of the above 8 / 30 8. Inspection of construction works for quality control is carried out and covers: a) Sampling, examination, and field testing of materials b) Testing specimens in the laboratory c) Observation of construction equipment and plant d) All of the above 9 / 30 9. Insurance provision in GCC is applicable for: a) Loss of damaged material, plants b) Loss of damaged equipment c) Personal death or injury d) All of the above 10 / 30 10. The dispute in construction is resolved through discussion of all parties on their respective stands leading to consensus. The process is called: a) Amicable settlement b) Arbitration c) Dispute resolution board d) Dispute adjudication board 11 / 30 11. Residential buildings are treated as: a) Light construction b) Heavy construction c) Industrial construction d) None of the above 12 / 30 12. In CPM, the actual performance of a task is called: a) An event b) An activity c) A duration d) Critical task 13 / 30 13. Total float for any activity is defined as the difference between: a) Its latest finish time and earliest start time for its successor activity b) Its latest start time and earliest start time c) Its latest start time and earliest finish time d) Its earliest finish time and earliest start time for its successor activity 14 / 30 14. If an activity has its optimistic, most likely, and pessimistic times as 2, 4, and 6, respectively, then its expected time and variance are respectively: a) 4 and 2/3 b) 4 and 4/9 c) 5 and 4/9 d) 5 and 2/3 15 / 30 15. Construction team means: a) An engineer b) An owner c) A contractor d) All of the above 16 / 30 16. The maximum amount for the approval of tender by Gazetted 3rd class officer is: a) Three crore b) Seven crore c) Fifteen crore d) More than fifteen crore 17 / 30 17. The overall in-charge of an organization at the site responsible for the execution of works is: a) Executive engineer b) Engineer c) Junior engineer d) Sub-overseer 18 / 30 18. For a safe working environment in the working site, "Tool Box Talk" is conducted: a) During the work b) At the end of the day's work c) Before the start of the day's work d) During lunch hour 19 / 30 19. Gantt chart is used for: a) Scheduling a project b) Planning a project c) Implementation of a project d) None of the above 20 / 30 20. If, for an activity, the optimistic time is 1 day, pessimistic time is 11 days, and the most likely time is 3 days, then the expected time is: a) 3 days b) 4 days c) 5 days d) 6 days 21 / 30 21. The maximum amount of project cost after the price adjustment should not exceed: a) 15% b) 20% c) 25% d) 30% 22 / 30 22. For a curve, larger the variance: a) Greater will be the uncertainty b) Smaller will be the uncertainty c) Not related to uncertainty d) All of the above 23 / 30 23. The occurrence of the starting of an activity is called its: a) Head event b) Tail event c) Dual-role event d) All of the above 24 / 30 24. According to Fulkerson's, the correct event numbers corresponding to events A, B, C, D, E of the network shown in figure 1 are: a) 1, 2, 3, 4, 5, 6, and 7, respectively b) 1, 3, 2, 4, 5, 6, and 7, respectively c) 1, 3, 2, 5, 6, 4 and 6, respectively d) None of the above 25 / 30 25. Critical path: a) Is the shortest path b) Is the bad path c) Has the maximum slack d) Has the minimum slack 26 / 30 26. Standard deviation when the optimistic time is 1 day, pessimistic time is 11 days, and most likely time is 3 days: a) 2 days b) 3.5 days c) 3 days d) 1.67 days 27 / 30 27. Aggregate planning is planning for: a) Single activity b) Double activities c) Whole project d) Events 28 / 30 28. An EPC contract means: a) End of planning and construction b) Evaluation, planning, and construction c) Engineering, planning, and construction d) Engineering, procurement, and construction 29 / 30 29. The minimum number of consulting firms for the direct purchase of services is: a) 2 b) 3 c) 4 d) 5 30 / 30 30. For the execution of work in time, a work plan is prepared by: a) Contractor b) Consultant c) Petty contractor d) Financial institution Please provide accurate information so we can send your Achievement Certificate by mail. NameEmailPhone Number Your score isShare your achievement! LinkedIn Facebook 0% Restart Test Please provide your feedback. Thank you for your valuable feedback. Send feedback Buy Construction Management MCQ PDF for Offline Study