Home» Online Test » Civil Engineering » Construction Management Online Test » Paper 1 » Paper 2 » Paper 3 0% Sorry, time's up. To complete the online test, please restart it. Created by Vikash chaudhary This is a FREE online test. Beware of scammers who ask for money to attend this test. Get fresh, new questions in each attempt. Total Questions: 30 Time Allotted: 30 minutes Passing Score: 50% Randomization: Yes Certificate: No Do not refresh the page! 👍 All the best! 1 / 30 1. In resource leveling, the main constraint would be: a) On the resources b) Project duration time c) Both of the above d) None of the above 2 / 30 2. The probability of completion of any activity within its expected time in PERT is: a) 0% b) 50% c) 75% d) 100% 3 / 30 3. Performance security is necessary: a) After contract agreement to a successful bidder b) Before bid opening to all bidders c) During bid opening to all bidders d) Before contract agreement to successful bidders 4 / 30 4. In CPM: a) Time optimization is given prime importance b) Cost optimization is given prime importance c) Cost is directly proportional to time d) All of the above 5 / 30 5. Most of the works related to measurement of items and making entry to the measurement book is initiated by: a) Site supervisor b) Site engineer c) Resident engineer d) Project in charge 6 / 30 6. SLACK time refers to: a) Activity b) Event c) Both d) None of the above 7 / 30 7. Which of the following does not represent an activity? a) Site located b) Foundation is being dug c) The office area is being cleaned d) The invitations are being sent 8 / 30 8. The mean of squared deviation from the mean of the distribution is known as: a) Mode b) Standard deviation c) Deviation d) Variance 9 / 30 9. An example of a parallel activity is: a) Completing ground floor and starting first floor construction b) Wall construction and carpentry work of doors and windows c) Completion of flooring and initiating whitewashing d) Digging of a well and construction of a septic tank 10 / 30 10. The expected project duration in CPM follows: a) Normal distribution curve b) Beta distribution curve c) Poisson's distribution curve d) Binomial distribution curve 11 / 30 11. CPM network is: a) Event-oriented b) Activity-oriented c) Slack-oriented d) Float-oriented 12 / 30 12. An EPC contract means: a) End of planning and construction b) Evaluation, planning, and construction c) Engineering, planning, and construction d) Engineering, procurement, and construction 13 / 30 13. In PERT, optimistic time is: a) The minimum time in which any activity can possibly be accomplished b) The maximum time which an activity might require c) The time which has the highest probability of occurrence d) None of the above 14 / 30 14. Milestone charts are developed in: a) 1900 AD b) 1940 AD c) 1957 AD d) 1974 AD 15 / 30 15. Which of the following is an activity in a CPM network: a) Concrete cured b) Walls plastered c) Excavation for foundation d) All of the above 16 / 30 16. No agreement is between: a) Client, engineer b) Engineer, contractor c) Client, contractor d) Contractor, sub-contractor 17 / 30 17. A golden rule for the procurement of construction work suggests: a) 100% at the site b) 67% at the site and 33% under procurement c) 50% at the site and 50% under procurement d) 33% at the site and 67% under procurement 18 / 30 18. At an event other than the final event, if no activity emerges, it results in an error called: a) Looping b) Dangling c) Interfacing d) Splicing 19 / 30 19. For the construction of a project, a contractor is a: a) A person b) A firm c) An agency d) All of the above 20 / 30 20. Military organization is known as: a) Line organization b) Line and staff organization c) Functional organization d) None of the above 21 / 30 21. The time with which direct cost does not reduce with the increase in time is known as: a) Normal time b) Crash time c) Optimistic time d) Standard time 22 / 30 22. Choose the incorrect statement: a) Arrow representing activity in CPM network is drawn without any scale b) Head of an activity represents the finish of an activity c) Tail of an activity represents the start of an activity d) None of the above 23 / 30 23. The dual-role event is: a) Head as well as tail event b) Sum of head and tail event c) Any event other than head and tail event d) None of the above 24 / 30 24. The occurrence of the starting of an activity is called its: a) Head event b) Tail event c) Dual-role event d) All of the above 25 / 30 25. Tender documents do not contain: a) Tender form b) BOQ c) Amount of earnest money d) Unit rate 26 / 30 26. Policy is: a) A rule or a set of rules never to be violated b) A definite rule along which one has to proceed c) A procedure for preparing the project report d) A set of broad guidelines stipulated by management 27 / 30 27. The duration of time which an activity can be delayed without affecting the succeeding activity is called free float which affects only: a) Preceding activities b) Succeeding activities c) The particular activity d) None of the above 28 / 30 28. The constraint in the case of resource smoothing operation would be: a) On the resources b) Project duration time c) Both (a) and (b) above d) None of the above 29 / 30 29. The owner gets assurance of work progress and quality from: a) Supervisor b) Contractor c) Engineer d) Labours 30 / 30 30. Free float is mainly used to: a) Identify the activities which can be delayed without affecting the total float of preceding activity b) Identify the activities which can be delayed without affecting the total float of succeeding activity c) Establish priorities d) Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities Please provide accurate information so we can send your Achievement Certificate by mail. NameEmailPhone Number Your score isShare your achievement! LinkedIn Facebook 0% Restart Test Please provide your feedback. Thank you for your valuable feedback. Send feedback Buy Construction Management MCQ PDF for Offline Study