Home» Online Test » Civil Engineering » Construction Management Online Test » Paper 1 » Paper 2 » Paper 3 0% Sorry, time's up. To complete the online test, please restart it. Created by Vikash chaudhary This is a FREE online test. Beware of scammers who ask for money to attend this test. Get New Questions in Each Attempt Total Questions: 30 Time Allotted: 30 minutes Passing Score: 50% Randomization: Yes Certificate: No Do not refresh the page! 👍 All the best! 1 / 30 1. Latest start time is the: a) Latest time by which an activity can be started without delaying the project b) Latest time by which an activity can be completed without delaying the project c) Latest time the event can occur d) Any of the above 2 / 30 2. Free float is the: a) Portion of independent float b) Portion of positive total float c) Portion of interfering float d) All of the above 3 / 30 3. PERT is: a) Activity-oriented b) Event-oriented c) Time-oriented d) Resources-oriented 4 / 30 4. In resource leveling, the main constraint would be: a) On the resources b) Project duration time c) Both of the above d) None of the above 5 / 30 5. The pictorial representation of activities and events of a project is known as: a) Net work b) Flow net c) Flow chart d) Algorithm 6 / 30 6. Mobilization advance up to 10% of the cost of work is given to a contractor: a) On commencement of work at the site for payment of a loan taken by him b) For the purchase of construction materials c) For the payment of advances to labor and staff d) For all activities required to start the work at the site 7 / 30 7. The scheduled completion time of an operation in CPM chart is mentioned on: a) Left top corner outside the circle b) Left top corner inside the circle c) Both of the above d) None of the above 8 / 30 8. For a safe working environment in the working site, "Tool Box Talk" is conducted: a) During the work b) At the end of the day's work c) Before the start of the day's work d) During lunch hour 9 / 30 9. The amount of money paid to the contractor by the client after the agreement and before the execution of work is known as: a) Advance b) Mobilization c) Security money d) 1st bill payment 10 / 30 10. On a bar chart, the various activities of a project are shown by: a) Shaded area b) Horizontal lines c) Vertical lines d) Dot marks 11 / 30 11. A construction schedule is prepared after collecting: a) Number of operations b) Output of labor and machinery c) Quantity of various items d) All of the above 12 / 30 12. The minimum number of critical paths in a network should be: a) 0 b) 1 c) 2 d) 3 13 / 30 13. Performance security is necessary: a) After contract agreement to a successful bidder b) Before bid opening to all bidders c) During bid opening to all bidders d) Before contract agreement to successful bidders 14 / 30 14. PERT technique of network analysis is useful for: a) Small projects b) Large projects c) Research and development projects d) All of the above 15 / 30 15. CPM network is: a) Event-oriented b) Activity-oriented c) Slack-oriented d) Float-oriented 16 / 30 16. The relation between jobs of a particular type and various durations they have consumed for completion is expressed by: a) Normal distribution curve b) Beta distribution curve c) Frequency distribution curve d) None of the above 17 / 30 17. Critical path is: a) Shortest path for the earliest completion of the project b) Longest path of the network from the first event to the last event c) Ideal path by preceding along which the project can be completed as per the schedule. d) The path that takes into account the completion of all the parallel activities 18 / 30 18. The time below which the duration cannot be further reduced is known as: a) Normal time b) Crash time c) Optimistic time d) Standard time 19 / 30 19. The total cost versus time curve of an activity is: a) A straight line b) A parabola c) U-shaped curve d) Γê⌐-shaped curve 20 / 30 20. The occurrence of the starting of an activity is called its: a) Head event b) Tail event c) Dual-role event d) All of the above 21 / 30 21. In CPM analysis: a) Emphasis is given to activities b) Uncertainties are not allowed c) Activities are represented by arrows d) All of the above 22 / 30 22. A contractor can start the construction works following the receipt of: a) Award of construct b) Contract agreement c) Notice to proceed d) Variation order 23 / 30 23. The completion report includes: a) The details of the final bill paid to the contractor b) The details of all the bills paid to the contractor c) The details of all the bills, variations along with as-built drawings d) The compilation of all the documents during project implementation 24 / 30 24. The probability of completion of any activity within its expected time in PERT is: a) 0% b) 50% c) 75% d) 100% 25 / 30 25. For the execution of work in time, a work plan is prepared by: a) Contractor b) Consultant c) Petty contractor d) Financial institution 26 / 30 26. Negative slack indicates: a) Ahead of schedule condition b) Behind the schedule condition c) On schedule condition d) None of the above 27 / 30 27. A fictitious activity with zero duration and no cost used to maintain the sequential order of the activities in the network is known as a: a) Restraint b) Dummy activity c) Event d) All of the above 28 / 30 28. Which of the following is an event in a CPM network: a) Concrete cured b) Walls plastering c) Excavation for foundation d) Fixing of the door 29 / 30 29. The figure indicates: a) An event b) Activity c) Burst d) Merge 30 / 30 30. Total project cost: a) Increases with time b) Decreases with time c) Initially reduces with time and then increases with further increases d) Constant Your score is Share your achievement! LinkedIn Facebook Twitter 0% Restart Test Please provide your feedback. Thank you for your valuable feedback. Send feedback Buy Construction Management MCQ PDF for Offline Study