Home» Online Test » Civil Engineering » Construction Management Online Test » Paper 1 » Paper 2 » Paper 3 0% Sorry, time's up. To complete the online test, please restart it. Created by Vikash chaudhary This is a FREE online test. Beware of scammers who ask for money to attend this test. Get fresh, new questions in each attempt. Total Questions: 30 Time Allotted: 30 minutes Passing Score: 50% Randomization: Yes Certificate: No Do not refresh the page! 👍 All the best! 1 / 30 1. Updating may result in: a) Change of the critical path b) Decrease of project completion time c) Increase of project completion time d) All of the above 2 / 30 2. PERT is: a) Activity-oriented b) Event-oriented c) Time-oriented d) Resources-oriented 3 / 30 3. The technique for establishing and maintaining priorities among various jobs of a project is known as: a) Event flow scheduling technique b) Critical ratio scheduling c) Slotting technique for scheduling d) Short interval scheduling 4 / 30 4. The post-operations in CPM are marked: a) Right to an operation b) Left to an operation c) In the middle d) At the end 5 / 30 5. Negative slack indicates: a) Ahead of schedule condition b) Behind the schedule condition c) On schedule condition d) None of the above 6 / 30 6. Critical path network helps the engineer to: a) Concentrate his attention on critical activities b) Divert the different resources from non-critical activities to critical activities c) Be cautious for avoiding any delay in the critical activities d) All of the above 7 / 30 7. The maximum amount for the approval of tender by Gazetted 3rd class officer is: a) Three crore b) Seven crore c) Fifteen crore d) More than fifteen crore 8 / 30 8. The interrelationship between the functional elements of a program is achieved through: a) Work Breakdown Structure b) Bar charts c) Gantt chart d) All of the above 9 / 30 9. Henry Gantt developed the bar chart technique in: a) 1900 AD b) 1940 AD c) 1957 AD d) 1974 AD 10 / 30 10. In CPM, the actual performance of a task is called: a) An event b) An activity c) A duration d) Critical task 11 / 30 11. The district rate finalizing committee does not include the representative of: a) Nepal Engineer's Association, district unit b) District Development Committee c) Contractor's Association d) District Technical Office 12 / 30 12. The Force Account or AMANAT, a method of carrying out the construction work is done by: a) Contractor using his own tools, staff, equipment, etc. b) Owner using his own tools, staff, equipment, etc. c) Sub-contractor using his own tools, staff, equipment, etc. d) None of the above 13 / 30 13. A golden rule for the procurement of construction work suggests: a) 100% at the site b) 67% at the site and 33% under procurement c) 50% at the site and 50% under procurement d) 33% at the site and 67% under procurement 14 / 30 14. In CPM analysis: a) Emphasis is given to activities b) Uncertainties are not allowed c) Activities are represented by arrows d) All of the above 15 / 30 15. A fictitious activity with zero duration and no cost used to maintain the sequential order of the activities in the network is known as a: a) Restraint b) Dummy activity c) Event d) All of the above 16 / 30 16. Restraint is a restriction having: a) Both (a) and (b) above b) Zero duration c) Positive duration d) Negative duration 17 / 30 17. In PERT analysis, the start and end of activity are represented by: a) Activity b) Event c) Task d) Work 18 / 30 18. Free float for any activity is defined as the difference between: a) Its latest start time and earliest start time for its successor activity b) Its latest start time and earliest start time c) Its latest finish time and earliest start time for its successor activity d) Its earliest finish time and earliest start time for its successor activity 19 / 30 19. Total cost of the project is: a) Direct cost and outage loss of project b) Direct cost and overheads c) Direct cost and indirect cost d) None of the above 20 / 30 20. The figure indicates: a) An event b) Activity c) Burst d) Merge 21 / 30 21. On a bar chart, the various activities of a project are shown by: a) Shaded area b) Horizontal lines c) Vertical lines d) Dot marks 22 / 30 22. The dual-role event is: a) Head as well as tail event b) Sum of head and tail event c) Any event other than head and tail event d) None of the above 23 / 30 23. Most of the works related to measurement of items and making entry to the measurement book is initiated by: a) Site supervisor b) Site engineer c) Resident engineer d) Project in charge 24 / 30 24. A frequency distribution curve: a) Having a single lump is called a uninodal curve b) If symmetrical is called a normal curve c) If unsymmetrical is called a skew curve d) All of the above 25 / 30 25. Choose the most correct statement from the following: a) Muster Roll is a document showing the payment record of workers b) Daywork is a means by which a contractor is paid for specifically instructed work-cost of labor, materials, and plant c) As per PPA/PPR, the bid security shall be 15% if the bid is 33% below. d) Expression of interest is a call for a financial proposal from contractors 26 / 30 26. The difference between total float and free float is called interfering float which is nothing but the: a) Float of the head event b) Float of the tail event c) Slack of the head event d) Slack of the tail event 27 / 30 27. Which of the following is not a part of a contract agreement? a) Price schedule b) Work schedule c) Manning schedule d) Cost Estimate 28 / 30 28. The amount of money paid to the contractor by the client after the agreement and before the execution of work is known as: a) Advance b) Mobilization c) Security money d) 1st bill payment 29 / 30 29. The upper portion of horizontal bars in a bar chart indicates: a) Total duration for completion of an activity b) Progress of work in the specified time c) Due duration for the completion of an activity d) All of the above 30 / 30 30. For completion of a project, the critical path of the network represents: a) Minimum time b) Maximum time c) Maximum cost d) Minimum cost Please provide accurate information so we can send your Achievement Certificate by mail. NameEmailPhone Number Your score isShare your achievement! LinkedIn Facebook 0% Restart Test Please provide your feedback. Thank you for your valuable feedback. Send feedback Buy Construction Management MCQ PDF for Offline Study