Home» Online Test » Civil Engineering » Construction Management Online Test » Paper 1 » Paper 2 » Paper 3 0% Sorry, time's up. To complete the online test, please restart it. Created by Vikash chaudhary This is a FREE online test. Beware of scammers who ask for money to attend this test. Get fresh, new questions in each attempt. Total Questions: 30 Time Allotted: 30 minutes Passing Score: 50% Randomization: Yes Certificate: No Do not refresh the page! 👍 All the best! 1 / 30 1. A golden rule for the procurement of construction work suggests: a) 100% at the site b) 67% at the site and 33% under procurement c) 50% at the site and 50% under procurement d) 33% at the site and 67% under procurement 2 / 30 2. Gantt chart is used for: a) Scheduling a project b) Planning a project c) Implementation of a project d) None of the above 3 / 30 3. The main advantage of line organization is: a) Effective command and control defined responsibilities at all levels b) Ability to make quick decisions at all levels c) Strict discipline in the Organization d) All of the above 4 / 30 4. A construction schedule is prepared after collecting: a) Number of operations b) Output of labor and machinery c) Quantity of various items d) All of the above 5 / 30 5. Which of the following is an activity in a CPM network: a) Concrete cured b) Walls plastered c) Excavation for foundation d) All of the above 6 / 30 6. Which of the following is an event in a CPM network: a) Concrete cured b) Walls plastering c) Excavation for foundation d) Fixing of the door 7 / 30 7. Float is: a) The earliest time by which an activity may commence b) Latest time by which an activity can be delayed without hampering the completion of the project c) Latest allowable time-earliest expected time d) Time available-time required for an activity 8 / 30 8. A contractor can start the construction works following the receipt of: a) Award of construct b) Contract agreement c) Notice to proceed d) Variation order 9 / 30 9. The reduction in project time normally results in: a) Decreasing the direct cost and increasing indirect cost b) Increasing the direct cost and decreasing the indirect cost c) Increasing the direct cost and indirect cost both d) Decreasing the direct cost and indirect cost both 10 / 30 10. When the times of earliest finish and the latest finish are equal in an operation, the operation is called: a) Critical b) Float c) Free float d) All of the above 11 / 30 11. The main responsibility of an overseer/Sub-Engineer is: a) To teach the subordinates b) To plan and execute the work c) To understand the duties d) All of the above 12 / 30 12. Railway projects are treated as: a) Light construction b) Heavy construction c) Industrial construction d) None of the above 13 / 30 13. Critical activities having total float are: a) Positive b) Negative c) Zero d) Equal 14 / 30 14. Earliest finish time of an activity is always: a) Equal to or more than the earliest event time of the following node b) Equal to or less than the earliest event time of the following node c) More than the earliest time of the following node d) None of the above 15 / 30 15. Critical path is: a) Shortest path for the earliest completion of the project b) Longest path of the network from the first event to the last event c) Ideal path by preceding along which the project can be completed as per the schedule. d) The path that takes into account the completion of all the parallel activities 16 / 30 16. If the height of the frequency-distribution underneath it is equal to unity, then the curve is known as: a) Normal distribution curve b) Skew curve c) Probability distribution curve d) All of the above 17 / 30 17. For a curve, larger the variance: a) Greater will be the uncertainty b) Smaller will be the uncertainty c) Not related to uncertainty d) All of the above 18 / 30 18. The total cost versus time curve of an activity is: a) A straight line b) A parabola c) U-shaped curve d) Γê⌐-shaped curve 19 / 30 19. In CPM analysis: a) Emphasis is given to activities b) Uncertainties are not allowed c) Activities are represented by arrows d) All of the above 20 / 30 20. The area under the B-curve is divided into two equal parts by: a) Expected time b) Optimistic time c) Pessimistic time d) Most likely time 21 / 30 21. Which of the following techniques is advanced and more indicative in modern construction progress review? a) Earned value b) S-curve c) Histogram d) Milestones 22 / 30 22. The difference between the total float and the free float is termed as: a) Start float b) Finish float c) Independent float d) Interfering float 23 / 30 23. PERT is: a) Activity-oriented b) Event-oriented c) Time-oriented d) Resources-oriented 24 / 30 24. Which of the following time estimates is related to PERT? a) Most likely time estimate b) Pessimistic time estimate c) Optimistic time estimate d) All of the above 25 / 30 25. The pictorial representation of activities and events of a project is known as: a) Net work b) Flow net c) Flow chart d) Algorithm 26 / 30 26. PERT technique of network analysis is useful for: a) Small projects b) Large projects c) Research and development projects d) All of the above 27 / 30 27. In CPM: a) Time optimization is given prime importance b) Cost optimization is given prime importance c) Cost is directly proportional to time d) All of the above 28 / 30 28. Choose the incorrect statement: a) Arrow representing activity in CPM network is drawn without any scale b) Head of an activity represents the finish of an activity c) Tail of an activity represents the start of an activity d) None of the above 29 / 30 29. Indirect cost of the project: a) Decreases with duration b) Decreases up to optimum duration and then increases with duration c) Increases with duration d) All of the above 30 / 30 30. If D is the duration, ES and EF are the earliest start and earliest finish time, LS and LF are the latest start and latest finish time, then the following relation holds good: a) EF = ES + D b) LS = LF - D c) LF = LS + D d) All of the above Please provide accurate information so we can send your Achievement Certificate by mail. NameEmailPhone Number Your score isShare your achievement! LinkedIn Facebook 0% Restart Test Please provide your feedback. Thank you for your valuable feedback. Send feedback Buy Construction Management MCQ PDF for Offline Study