Estimating & Costing Online Test – Paper 3

0%
Created by 83a36dcfd5c4caff12bc80f0020c9c749e12cbbbdb7c406dc1dd39996cb85836?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get New Questions in Each Attempt

  • Total Questions: 50
  • Time Allotted: 50 minutes
  • Passing Score: 70%
  • Randomization: Yes
  • Certificate: Yes
  • Do not refresh the page!
  • 👍 All the best!

1 / 50

1. The information that can't be included in drawings is conveyed to the estimator through

2 / 50

2. End lap provided in asbestos cements is equal to

3 / 50

3. The value of the property (without being disassembled) at the end of the useful life period is known as

4 / 50

4. For brick construction, the lime-sand mortar is

5 / 50

5. In the long and short wall method of estimation, the length of the long wall is the center to center space between walls plus

6 / 50

6. Specifications of any works are required only when the work is carried out by:

7 / 50

7. Contractor profit is added to

8 / 50

8. Working out the exact quantities of various items of work is known as

9 / 50

9. The value of the dismantled material less the cost of dismantling is called

10 / 50

10. What is the minimum period for which the lime concrete in the foundation be left wet without the construction of masonry over it?

11 / 50

11. The thickness of slabs and beams must be measured to the nearest

12 / 50

12. The unit of measurement for woodwork in door and window frame, rafters, beams, roof trusses, etc., is

13 / 50

13. The number of corrugations in an asbestos cement sheet is usually

14 / 50

14. Due to a change in the price level, a revised estimate is prepared if the sanctioned estimate exceeds:

15 / 50

15. For electric wiring such as a fan, light, plug, etc., the estimate is made in terms of

16 / 50

16. According to ISI method of measurement, the order of sequence is:

17 / 50

17. An estimate is:

18 / 50

18. The amount of cement required per cubic meter having mix (1:3:6) is

19 / 50

19. The quantity of work of any item which is the output of a skilled labor in a day is known as

20 / 50

20. The portion which is wrongly excavated by the contractor is to be filled

21 / 50

21. In the specification of earthwork in foundation trenches, drains, etc. lead specified is (IS code)

22 / 50

22. Contractor tax

23 / 50

23. Arrange the specific weights of wood (w), cement (c), steel (s), and coarse aggregate (A) in increasing order

24 / 50

24. Minimum size of the pipe connected to the septic tank is

25 / 50

25. According to ISI method of measurement, the order is in the sequence

26 / 50

26. A document containing a detailed description of all types of work (but their quantities are not mentioned) together with their current rates is called

27 / 50

27. The unit of measurement for steel works in trussed and its parts is

28 / 50

28. The thickness of 25 gauge sheet is

29 / 50

29. The gradual accumulation of amounts by way of annual periodic deposits, which is meant for the replacement of the structure at the end of its useful life period, is known as

30 / 50

30. The actual weight of cement bag is more in case of

31 / 50

31. In the case of a roof truss made of steel, rivets, bolts, nuts, etc., normally account for

32 / 50

32. The essential requirements to prepare a good estimate are

33 / 50

33. The method of valuation of a building as used by commercial banks is based on:

34 / 50

34. The appropriate cost to the complete labor as a percentage of the total cost of the building is

35 / 50

35. The number of corrugations in a galvanized corrugated sheet is usually

36 / 50

36. Which of the following is the most correct estimate

37 / 50

37. The explosive for blasting is usually expressed in terms of

38 / 50

38. A document showing the list of quantity of various items of works required for the completion of any project is known as

39 / 50

39. Specification is the

40 / 50

40. Which of the following is known as job overhead?

41 / 50

41. How many kilo-liters are in one cubic meter?

42 / 50

42. The area of the segmental portion of an arch with span I and rise r is approximately given by

43 / 50

43. Evaluation of building is done based on

44 / 50

44. The weight of cement in one bag is

45 / 50

45. In the case of unsewered areas, an additional provision for a septic tank is usually

46 / 50

46. Generally, the unit of measurement for partition walls is

47 / 50

47. Demolition means

48 / 50

48. The unit rate of items written by the contractor in BOQ is in numeral as well as alphabetical form. Which one is preferred?

49 / 50

49. Which of the followings is not an essential part of the general specification of public works?

50 / 50

50. In the center line method of working out volumes, for cross walls, what deductions must be made from the center line length at each junction?

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook Twitter
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments
0
Join Discussionsx
()
x
Scroll to Top