Estimating & Costing Online Test – Paper 3

0%
Created by 37fdd4228dab83e2f2bdee26b19f1560?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get New Questions in Each Attempt

  • Total Questions: 50
  • Time Allotted: 50 minutes
  • Passing Score: 70%
  • Randomization: Yes
  • Certificate: Yes
  • Do not refresh the page!
  • 👍 All the best!

1 / 50

1. The nominal lead and lift allowed for the earthwork in the excavations of the foundations are

2 / 50

2. If the payment of annuity begins after some years in future, it is known as

3 / 50

3. The minimum number of hinges provided in a door and window shutter should be

4 / 50

4. Payment of the steel is done by

5 / 50

5. The standard width of an asbestos cement corrugated sheet is

6 / 50

6. According to ISI method of measurement, the order is in the sequence

7 / 50

7. A document containing a detailed description of all types of work (but their quantities are not mentioned) together with their current rates is called

8 / 50

8. The area of the segmental portion of an arch with span I and rise r is approximately given by

9 / 50

9. In detailed measurement, the sequence of dimensions is written:

10 / 50

10. What is the minimum period for which the lime concrete in the foundation be left wet without the construction of masonry over it?

11 / 50

11. In which of the following works, the work turned in cu.m per mason per day will be the least?

12 / 50

12. Approximate weight of 1 cubic meter of sand is

13 / 50

13. Generally, the unit of measurement for partition walls is

14 / 50

14. In the center line method of working out volumes, for cross walls, what deductions must be made from the center line length at each junction?

15 / 50

15. Which one area must be greater at any floor of a building?

16 / 50

16. A layer of dry bricks put below the foundation concrete, in the case of soft soils, is called

17 / 50

17. Compound amount of Rs. 100 in 4 years @ 4% interest

18 / 50

18. The unit of measurement for woodwork in door and window frame, rafters, beams, roof trusses, etc., is

19 / 50

19. The minimum space left from the property line (In Kathmandu valley) for the provision of window/door is

20 / 50

20. In the analysis of rates, the profit and overhead for the contractor are generally taken as

21 / 50

21. In the long and short wall method of estimation, the length of the long wall is the center to center space between walls plus

22 / 50

22. Working out the exact quantities of various items of work is known as

23 / 50

23. Contractor profit is added to

24 / 50

24. The fundamental units in the metric system are:

25 / 50

25. The most reliable estimate is:

26 / 50

26. The number of corrugations in a galvanized corrugated sheet is usually

27 / 50

27. The portion which is wrongly excavated by the contractor is to be filled

28 / 50

28. In a sanitary pipeline for 3 m length, how many skilled labor are required

29 / 50

29. During the excavation of soil, some portion is left without disturbing, which is known as

30 / 50

30. Method of calculating the quantity if which out to out and in to in lengths are considered regardless of calculating through the total center line of the walls, and useful of different thicknesses is called:

31 / 50

31. 1 British gallon=.........litres.

32 / 50

32. The weight of cement in one bag is

33 / 50

33. In the case of steel rolling shutters, for the estimation of the painted area, the plain area is multiplied by

34 / 50

34. The weight of 10 mm diameter mild steel rod per meter length is equal to

35 / 50

35. Which of the followings is not an essential part of the general specification of public works?

36 / 50

36. For brick construction, the lime-sand mortar is

37 / 50

37. The useful part of the livable area of a building is also known as

38 / 50

38. In the case of laying gullies, intercepting traps, the cost includes:

39 / 50

39. Providing and assembling in position false work for the construction of RCC superstructure is measured in:

40 / 50

40. The estimated quantity of cement required in cement mortar (1:6) per cubic meter will be

41 / 50

41. Arrange the specific weights of wood (w), cement (c), steel (s), and coarse aggregate (A) in increasing order

42 / 50

42. Contractor tax

43 / 50

43. One metric horsepower is equal to

44 / 50

44. Work-charged establishment

45 / 50

45. Normally which one contract gives the maximum value of the project

46 / 50

46. The gradual accumulation of amounts by way of annual periodic deposits, which is meant for the replacement of the structure at the end of its useful life period, is known as

47 / 50

47. Of the total estimated cost of a building, the cost of electrification usually accounts for

48 / 50

48. The number of corrugations in an asbestos cement sheet is usually

49 / 50

49. Which of the following is not an essential part of the general specification of public works?

50 / 50

50. Which of the following is known as general overhead?

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook Twitter
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments
0
Join Discussionsx
()
x
Scroll to Top