Estimating & Costing Online Test - Paper 3 » Ultimate Challenge
GK Aim: A Treasure of MCQs

Estimating & Costing Online Test – Paper 3

0%
Created by 83a36dcfd5c4caff12bc80f0020c9c749e12cbbbdb7c406dc1dd39996cb85836?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get fresh, new questions in each attempt.

  • Total Questions: 50
  • Time Allotted: 50 minutes
  • Passing Score: 70%
  • Randomization: Yes
  • Certificate: Yes
  • Do not refresh the page!
  • 👍 All the best!

1 / 50

1. Evaluation of building is done based on

2 / 50

2. The unit of measurement for electric wiring or electrification light, fan plug points is

3 / 50

3. Payment of the steel is done by

4 / 50

4. The tender is:

5 / 50

5. The value of property that can be obtained when the property is put for sale is known as:

6 / 50

6. The unit rate of items written by the contractor in BOQ is in numeral as well as alphabetical form. Which one is preferred?

7 / 50

7. The essential requirements to prepare a good estimate are

8 / 50

8. During the excavation of soil, some portion is left without disturbing, which is known as

9 / 50

9. The most reliable estimate is:

10 / 50

10. The unit of payment for fixing of glass panes or cleaning is in

11 / 50

11. If valuable properties are found during excavation, it becomes the property of

12 / 50

12. The chairman of the material rate fixation committee in the district is

13 / 50

13. The method of valuation of a building as used by commercial banks is based on:

14 / 50

14. The value shown in the account book after allowing necessary depreciation is known as

15 / 50

15. During the calculation of RCC, the amount of steel deducted is

16 / 50

16. Which of the following is the most correct estimate

17 / 50

17. The unit of PVC pipe used in water supply pipeline is

18 / 50

18. Steel formwork can be used up to about.........times.

19 / 50

19. Which one area must be greater at any floor of a building?

20 / 50

20. The appropriate cost to the complete labor as a percentage of the total cost of the building is

21 / 50

21. The order of booking dimension is:

22 / 50

22. The actual size of the modular brick (as per IS Code) is

23 / 50

23. In CGI sheet roofing, the overlap along the length of the sheet should not be less than?

24 / 50

24. The minimum space left from the property line (In Kathmandu valley) for the provision of window/door is

25 / 50

25. End lap provided in asbestos cements is equal to

26 / 50

26. The depreciation of the value of the building costs are generally not considered for the initial:

27 / 50

27. When additional works are added to the original works, the estimate is called:

28 / 50

28. Method of calculating the quantity if which out to out and in to in lengths are considered regardless of calculating through the total center line of the walls, and useful of different thicknesses is called:

29 / 50

29. Whenever color washing on A.C. corrugated sheets is done, in the estimation, the plan area of the sheets is increased by

30 / 50

30. The unit of payment for roadside brick edging to increase the pavement width is

31 / 50

31. A fixed stipulated sum of penalty payable by the contractor having no relationship with real damage is known as

32 / 50

32. Which method is easiest for the estimation of the quantity of material?

33 / 50

33. The actual weight of cement bag is more in case of

34 / 50

34. The number of skilled and unskilled manpower required for the fabrication of one metric ton steel (Norms prepared by DoR) is

35 / 50

35. Normally which one contract gives the maximum value of the project

36 / 50

36. In the long and short wall method of estimation, the length of the long wall is the center to center space between walls plus

37 / 50

37. Of the total estimated cost of a building, the cost of electrification usually accounts for

38 / 50

38. The expenses of items that do not come under any regular head of items and the cost of unforeseen items are called

39 / 50

39. Minimum size of the pipe connected to the septic tank is

40 / 50

40. In a sanitary pipeline for 3 m length, how many skilled labor are required

41 / 50

41. Arrange the specific weights of wood (w), cement (c), steel (s), and coarse aggregate (A) in increasing order

42 / 50

42. Providing and assembling in position false work for the construction of RCC superstructure is measured in:

43 / 50

43. If the payment of annuity begins after some years in the future, it is known as

44 / 50

44. When not specified, the volume of steel in R.C.C work is taken as

45 / 50

45. A document showing the list of quantity of various items of works required for the completion of any project is known as

46 / 50

46. In the case of unsewered areas, an additional provision for a septic tank is usually

47 / 50

47. The unit of measurement for earthwork in excavation in ordinary soils, earthwork in mixed soil with kankar, bajri, etc., when the depth of excavation does not exceed 30 cm, is

48 / 50

48. The unit of payment for A.C. sheet roofing is in

49 / 50

49. The explosive for blasting is usually expressed in terms of

50 / 50

50. Plinth area estimate is an approximate estimate mostly used for the estimation of:

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook Twitter
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments
Scroll to Top