Estimating & Costing Online Test - Paper 3 » Ultimate Challenge

Estimating & Costing Online Test – Paper 3

0%
Created by 83a36dcfd5c4caff12bc80f0020c9c749e12cbbbdb7c406dc1dd39996cb85836?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get fresh, new questions in each attempt.

  • Total Questions: 50
  • Time Allotted: 50 minutes
  • Passing Score: 70%
  • Randomization: Yes
  • Certificate: Yes
  • Do not refresh the page!
  • 👍 All the best!

1 / 50

1. In CGI sheet roofing, the overlap along the length of the sheet should not be less than?

2 / 50

2. In which of the following works, the work turned in cu.m per mason per day will be the least?

3 / 50

3. The minimum number of hinges provided in a door and window shutter should be

4 / 50

4. The unit of measurement for concrete work in R.C.C. is

5 / 50

5. The unit of measurement for electric wiring or electrification light, fan plug points is

6 / 50

6. When engineering departments undertake the works of other departments, the amount charged toward design, supervision, and execution, etc., is called

7 / 50

7. A document containing a detailed description of all types of work (but their quantities are not mentioned) together with their current rates is called

8 / 50

8. The amount of money deposited along with the submission of tender is known as

9 / 50

9. Tender does not contain

10 / 50

10. Which one area must be greater at any floor of a building?

11 / 50

11. Method of calculating the quantity if which out to out and in to in lengths are considered regardless of calculating through the total center line of the walls, and useful of different thicknesses is called:

12 / 50

12. Carpet area does not include the area of

13 / 50

13. Which of the following is known as general overhead?

14 / 50

14. Which of the followings is not an essential part of the general specification of public works?

15 / 50

15. Providing and assembling in position false work for the construction of RCC superstructure is measured in:

16 / 50

16. The unit of payment for A.C. sheet roofing is in

17 / 50

17. The standard width of the galvanized iron sheet is

18 / 50

18. As per norms prepared by the ministry of transport & works, one porter can carry a weight of

19 / 50

19. The rate of an item of work depends

20 / 50

20. If valuable properties are found during excavation, it becomes the property of

21 / 50

21. A document showing the list of quantity of various items of works required for the completion of any project is known as

22 / 50

22. The essential requirements to prepare a good estimate are

23 / 50

23. Following items of earthwork are not measured separately

24 / 50

24. The necessary elements of the estimate are:

25 / 50

25. Working out the exact quantities of various items of work is known as

26 / 50

26. The unit of payment for roadside brick edging to increase the pavement width is

27 / 50

27. Which of the following is not an essential part of the general specification of public works?

28 / 50

28. According to ISI method of measurement, the order of sequence is:

29 / 50

29. The net annual letting out value of a property, which is obtained after deducting the amount of yearly repairs from the gross income, is known as

30 / 50

30. Whenever color washing on A.C. corrugated sheets is done, in the estimation, the plan area of the sheets is increased by

31 / 50

31. Plinth area of a building does not include:

32 / 50

32. Payment of the steel is done by

33 / 50

33. The number of skilled and unskilled manpower required for the fabrication of one metric ton steel (Norms prepared by DoR) is

34 / 50

34. Contractor tax

35 / 50

35. The area of the segmental portion of an arch with span I and rise r is approximately given by

36 / 50

36. The technique of finding the fair price of an existing building or property is known as

37 / 50

37. Specification deals with:

38 / 50

38. Normally which one contract gives the maximum value of the project

39 / 50

39. Work-charged establishment

40 / 50

40. The value of the dismantled material less the cost of dismantling is called

41 / 50

41. Which one information is not found in specification?

42 / 50

42. For electric wiring such as a fan, light, plug, etc., the estimate is made in terms of

43 / 50

43. 1 He=......Ropani.

44 / 50

44. The fundamental units in the metric system are:

45 / 50

45. The unit rate of items written by the contractor in BOQ is in numeral as well as alphabetical form. Which one is preferred?

46 / 50

46. Compound amount of Rs. 100 in 4 years @ 4% interest

47 / 50

47. Full payment of the contractor is done

48 / 50

48. Plinth area estimate is an approximate estimate mostly used for the estimation of:

49 / 50

49. The useful part of the livable area of a building is also known as

50 / 50

50. During the calculation of RCC, the amount of steel deducted is

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook Twitter
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments
Scroll to Top