Estimating & Costing Online Test – Paper 3

0%
Created by 37fdd4228dab83e2f2bdee26b19f1560?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get New Questions in Each Attempt

  • Total Questions: 50
  • Time Allotted: 50 minutes
  • Passing Score: 70%
  • Randomization: Yes
  • Certificate: Yes
  • Do not refresh the page!
  • 👍 All the best!

1 / 50

1. A layer of dry bricks put below the foundation concrete, in the case of soft soils, is called

2 / 50

2. The amount of money deposited along with the submission of tender is known as

3 / 50

3. The process of calculating the amount of material, labor, and equipment for a unit of work together with overhead and profit for the contractor is:

4 / 50

4. The capacity of a flushing cistern is normally

5 / 50

5. For electric wiring such as a fan, light, plug, etc., the estimate is made in terms of

6 / 50

6. The nominal lead and lift allowed for the earthwork in the excavations of the foundations are

7 / 50

7. Estimate is

8 / 50

8. The tender is:

9 / 50

9. The measurement of steel grills is taken in terms of

10 / 50

10. Which of the following is not considered while preparing the item rate estimate?

11 / 50

11. The weight of cement in one bag is

12 / 50

12. Specifications of any works are required only when the work is carried out by:

13 / 50

13. Centre line method is specially adopted for estimating... Buildings.

14 / 50

14. A fixed stipulated sum of penalty payable by the contractor having no relationship with real damage is known as

15 / 50

15. Specification deals with:

16 / 50

16. The explosive for blasting is usually expressed in terms of

17 / 50

17. Specification is the

18 / 50

18. The standard width of the galvanized iron sheet is

19 / 50

19. At present, the approximate cost of a Residential building per square foot in Kathmandu is

20 / 50

20. End lap provided in asbestos cements is equal to

21 / 50

21. Which of the following is the most correct estimate

22 / 50

22. Plinth area estimate is an approximate estimate mostly used for the estimation of:

23 / 50

23. Contractor tax

24 / 50

24. The volume of concrete for a reinforced concrete isolated sloped footing with top and bottom areas equal to A1 and A2 and with a height equal to h is given by:

25 / 50

25. Indicating works left in excavated trenches to facilitate the measurement of borrow pits are known as

26 / 50

26. When not specified, the volume of steel in R.C.C work is taken as

27 / 50

27. The technique of finding the fair price of an existing building or property is known as

28 / 50

28. The value of the property (without being disassembled) at the end of the useful life period is known as

29 / 50

29. In the case of unsewered areas, an additional provision for a septic tank is usually

30 / 50

30. The weight of 10 mm diameter mild steel rod per meter length is equal to

31 / 50

31. During the calculation of RCC, the amount of steel deducted is

32 / 50

32. Valuation is done for:

33 / 50

33. Full payment of the contractor is done

34 / 50

34. For brick construction, the lime-sand mortar is

35 / 50

35. The depreciation of the value of the building costs are generally not considered for the initial:

36 / 50

36. For estimating painting area for iron grillwork over a door or window opening, the area measured will be:

37 / 50

37. Which of the followings is not an essential part of the general specification of public works?

38 / 50

38. Rate analysis prepared by the ministry of transport and work includes

39 / 50

39. The concealed faces of the frames of doors and windows are painted with

40 / 50

40. Contractor profit is added to

41 / 50

41. The unit of payment for roadside brick edging to increase the pavement width is

42 / 50

42. Which one area must be greater at any floor of a building?

43 / 50

43. The actual size of the modular brick (as per IS Code) is

44 / 50

44. Working out the exact quantities of various items of work is known as

45 / 50

45. According to ISI method of measurement, the order is in the sequence

46 / 50

46. Which one information is found through specification?

47 / 50

47. The necessary elements of the estimate are:

48 / 50

48. Pick up the correct statement

49 / 50

49. The number of standard bricks in one cubic meter of masonry is:

50 / 50

50. In which of the following works, the work turned in cu.m per mason per day will be the least?

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook Twitter
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments
0
Join Discussionsx
()
x
Scroll to Top