Estimating & Costing Online Test - Paper 3 » Ultimate Challenge
GK Aim: A Treasure of MCQs

Estimating & Costing Online Test – Paper 3

0%
Created by 83a36dcfd5c4caff12bc80f0020c9c749e12cbbbdb7c406dc1dd39996cb85836?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get fresh, new questions in each attempt.

  • Total Questions: 50
  • Time Allotted: 50 minutes
  • Passing Score: 70%
  • Randomization: Yes
  • Certificate: Yes
  • Do not refresh the page!
  • 👍 All the best!

1 / 50

1. The nominal lead and lift allowed for the earthwork in the excavations of the foundations are

2 / 50

2. Which one information is found through specification?

3 / 50

3. Salvage value of any structure is

4 / 50

4. During the excavation of soil, some portion is left without disturbing, which is known as

5 / 50

5. The expenses of items that do not come under any regular head of items and the cost of unforeseen items are called

6 / 50

6. The chairman of the material rate fixation committee in the district is

7 / 50

7. The value of the dismantled material less the cost of dismantling is called

8 / 50

8. Normally which one contract gives the maximum value of the project

9 / 50

9. The capacity of a flushing cistern is normally

10 / 50

10. The gradual accumulation of amounts by way of annual periodic deposits, which is meant for the replacement of the structure at the end of its useful life period, is known as

11 / 50

11. Method of calculating the quantity if which out to out and in to in lengths are considered regardless of calculating through the total center line of the walls, and useful of different thicknesses is called:

12 / 50

12. The unit of payment for excavation trenches for pipes, cables, etc., up to 1.5 m depth in ordinary rock/hard rock is

13 / 50

13. An estimate is:

14 / 50

14. Plinth area of a building does not include:

15 / 50

15. In a sanitary pipeline for 3 m length, how many skilled labor are required

16 / 50

16. In the case of steel rolling shutters, for the estimation of the painted area, the plain area is multiplied by

17 / 50

17. Contractor profit is added to

18 / 50

18. Compound amount of Rs. 100 in 4 years @ 4% interest

19 / 50

19. The standard width of the galvanized iron sheet is

20 / 50

20. The depreciation of the value of the building costs are generally not considered for the initial:

21 / 50

21. Tender does not contain

22 / 50

22. When additional works are added to the original works, the estimate is called:

23 / 50

23. Liquidated damage is directly related to

24 / 50

24. The weight of 10 mm diameter mild steel rod per meter length is equal to

25 / 50

25. Plinth area estimate is an approximate estimate mostly used for the estimation of:

26 / 50

26. The unit of payment for fixing of glass panes or cleaning is in

27 / 50

27. According to ISI method of measurement, the order of sequence is:

28 / 50

28. When it is not specified, the number of holdfasts for a door is usually taken as

29 / 50

29. For estimating painting area for iron grillwork over a door or window opening, the area measured will be:

30 / 50

30. Payment of the steel is done by

31 / 50

31. The building material brick

32 / 50

32. End lap provided in asbestos cements is equal to

33 / 50

33. How many kilo-liters are in one cubic meter?

34 / 50

34. The number of corrugations in an asbestos cement sheet is usually

35 / 50

35. One metric horsepower is equal to

36 / 50

36. Working out the exact quantities of various items of work is known as

37 / 50

37. The actual weight of cement bag is more in case of

38 / 50

38. The amount of money deposited along with the submission of tender is known as

39 / 50

39. The value shown in the account book after allowing necessary depreciation is known as

40 / 50

40. For electric wiring such as a fan, light, plug, etc., the estimate is made in terms of

41 / 50

41. The unit of PVC pipe used in water supply pipeline is

42 / 50

42. Which of the following is not considered while preparing the item rate estimate?

43 / 50

43. In the specification of earthwork in foundation trenches, drains, etc. lead specified is (IS code)

44 / 50

44. The most reliable estimate is:

45 / 50

45. Which of the following is the most correct estimate

46 / 50

46. In the case of a roof truss made of steel, rivets, bolts, nuts, etc., normally account for

47 / 50

47. Pick up the correct statement

48 / 50

48. The unit of measurement for earthwork in excavation in ordinary soils, earthwork in mixed soil with kankar, bajri, etc., when the depth of excavation does not exceed 30 cm, is

49 / 50

49. The approximate weight of one cubic meter of mild steel is

50 / 50

50. The area of the segmental portion of an arch with span I and rise r is approximately given by

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook Twitter
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments
Scroll to Top