Estimating & Costing Online Test – Paper 3

0%
Created by 83a36dcfd5c4caff12bc80f0020c9c749e12cbbbdb7c406dc1dd39996cb85836?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get New Questions in Each Attempt

  • Total Questions: 50
  • Time Allotted: 50 minutes
  • Passing Score: 70%
  • Randomization: Yes
  • Certificate: Yes
  • Do not refresh the page!
  • 👍 All the best!

1 / 50

1. The standard width of an asbestos cement corrugated sheet is

2 / 50

2. The essential requirements to prepare a good estimate are

3 / 50

3. Centre line method is specially adopted for estimating... Buildings.

4 / 50

4. Due to a change in the price level, a revised estimate is prepared if the sanctioned estimate exceeds:

5 / 50

5. Working out the exact quantities of various items of work is known as

6 / 50

6. In the center line method of working out volumes, for cross walls, what deductions must be made from the center line length at each junction?

7 / 50

7. The unit of measurement for concrete work in R.C.C. is

8 / 50

8. Actual cost of construction plus certain profit is paid to the contractor. Such a contract is known as

9 / 50

9. When additional works are added to the original works, the estimate is called:

10 / 50

10. Demolition means

11 / 50

11. When not specified, the volume of steel in R.C.C work is taken as

12 / 50

12. The expenses of items that do not come under any regular head of items and the cost of unforeseen items are called

13 / 50

13. 1 British gallon=.........litres.

14 / 50

14. The minimum space left from the property line (In Kathmandu valley) for the provision of window/door is

15 / 50

15. Minimum size of the pipe connected to the septic tank is

16 / 50

16. The area of the segmental portion of an arch with span I and rise r is approximately given by

17 / 50

17. During the excavation of soil, some portion is left without disturbing, which is known as

18 / 50

18. The number of corrugations in a galvanized corrugated sheet is usually

19 / 50

19. Work-charged establishment

20 / 50

20. The actual size of the modular brick (as per IS Code) is

21 / 50

21. Generally, the unit of measurement for partition walls is

22 / 50

22. The main target of a contractor is to

23 / 50

23. The value shown in the account book after allowing necessary depreciation is known as

24 / 50

24. End lap provided in asbestos cements is equal to

25 / 50

25. Liquidated damage is directly related to

26 / 50

26. Tender does not contain

27 / 50

27. Minimum side lap required for asbestos cement sheets is

28 / 50

28. If the payment of annuity begins after some years in future, it is known as

29 / 50

29. In a sanitary pipeline for 3 m length, how many skilled labor are required

30 / 50

30. The nominal lead and lift allowed for the earthwork in the excavations of the foundations are

31 / 50

31. Specifications of any works are required only when the work is carried out by:

32 / 50

32. Full payment of the contractor is done

33 / 50

33. The gradual accumulation of amounts by way of annual periodic deposits, which is meant for the replacement of the structure at the end of its useful life period, is known as

34 / 50

34. The portion which is wrongly excavated by the contractor is to be filled

35 / 50

35. The quantity of work of any item which is the output of a skilled labor in a day is known as

36 / 50

36. Salvage value of any structure is

37 / 50

37. In detailed measurement, the sequence of dimensions is written:

38 / 50

38. In the analysis of rates, what percentage of total cost is provided towards water charges?

39 / 50

39. The value of the property (without being disassembled) at the end of the useful life period is known as

40 / 50

40. The unit of measurement for steel works in trussed and its parts is

41 / 50

41. Providing and assembling in position false work for the construction of RCC superstructure is measured in:

42 / 50

42. Normally which one contract gives the maximum value of the project

43 / 50

43. The full form of VAT is

44 / 50

44. The explosive for blasting is usually expressed in terms of

45 / 50

45. The unit of payment for roadside brick edging to increase the pavement width is

46 / 50

46. In the specification of earthwork in foundation trenches, drains, etc. lead specified is (IS code)

47 / 50

47. As per norms prepared by the ministry of transport & works, one porter can carry a weight of

48 / 50

48. At present, the approximate cost of a Residential building per square foot in Kathmandu is

49 / 50

49. In which of the following works, the work turned in cu.m per mason per day will be the least?

50 / 50

50. Evaluation of building is done based on

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook Twitter
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments
Scroll to Top
0
Join Discussionsx
()
x