Estimating & Costing Online Test – Paper 3

0%
Created by 83a36dcfd5c4caff12bc80f0020c9c749e12cbbbdb7c406dc1dd39996cb85836?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get New Questions in Each Attempt

  • Total Questions: 50
  • Time Allotted: 50 minutes
  • Passing Score: 70%
  • Randomization: Yes
  • Certificate: Yes
  • Do not refresh the page!
  • 👍 All the best!

1 / 50

1. Minimum size of the pipe connected to the septic tank is

2 / 50

2. One metric horsepower is equal to

3 / 50

3. During the calculation of RCC, the amount of steel deducted is

4 / 50

4. The explosive for blasting is usually expressed in terms of

5 / 50

5. The unit of measurement for steel works in trussed and its parts is

6 / 50

6. Rate analysis prepared by the ministry of transport and work includes

7 / 50

7. The depreciation of the value of the building costs are generally not considered for the initial:

8 / 50

8. The amount of cement required per cubic meter having mix (1:3:6) is

9 / 50

9. The thickness of slabs and beams must be measured to the nearest

10 / 50

10. Which one area must be greater at any floor of a building?

11 / 50

11. The gradual accumulation of amounts by way of annual periodic deposits, which is meant for the replacement of the structure at the end of its useful life period, is known as

12 / 50

12. According to ISI method of measurement, the order is in the sequence

13 / 50

13. The unit of measurement for beading provided in door and window frame, rafters, etc., is

14 / 50

14. A document containing a detailed description of all types of work (but their quantities are not mentioned) together with their current rates is called

15 / 50

15. The unit of measurement for concrete work in R.C.C. is

16 / 50

16. The types of work done by the use of labor but not material, equipment, etc., are known as:

17 / 50

17. The process of calculating the amount of material, labor, and equipment for a unit of work together with overhead and profit for the contractor is:

18 / 50

18. In the analysis of rates, the profit and overhead for the contractor are generally taken as

19 / 50

19. Due to a change in the price level, a revised estimate is prepared if the sanctioned estimate exceeds:

20 / 50

20. As per norms prepared by the ministry of transport & works, one porter can carry a weight of

21 / 50

21. Specification deals with:

22 / 50

22. 1 He=......Ropani.

23 / 50

23. The standard width of the galvanized iron sheet is

24 / 50

24. The standard width of an asbestos cement corrugated sheet is

25 / 50

25. Bill of quantities is prepared based on:

26 / 50

26. The weight of 10 mm diameter mild steel rod per meter length is equal to

27 / 50

27. The useful part of the livable area of a building is also known as

28 / 50

28. In the case of steel rolling shutters, for the estimation of the painted area, the plain area is multiplied by

29 / 50

29. If valuable properties are found during excavation, it becomes the property of

30 / 50

30. The rate of an item of work depends

31 / 50

31. A fixed stipulated sum of penalty payable by the contractor having no relationship with real damage is known as

32 / 50

32. The unit rate of items written by the contractor in BOQ is in numeral as well as alphabetical form. Which one is preferred?

33 / 50

33. How many kilo-liters are in one cubic meter?

34 / 50

34. In the analysis of rates, what percentage of total cost is provided towards water charges?

35 / 50

35. 1 British gallon=.........litres.

36 / 50

36. The chairman of the material rate fixation committee in the district is

37 / 50

37. Steel formwork can be used up to about.........times.

38 / 50

38. The unit of payment for excavation trenches for pipes, cables, etc., up to 1.5 m depth in ordinary rock/hard rock is

39 / 50

39. The actual size of the modular brick (as per IS Code) is

40 / 50

40. Which of the following is known as job overhead?

41 / 50

41. The quantity of work of any item which is the output of a skilled labor in a day is known as

42 / 50

42. The unit of PVC pipe used in water supply pipeline is

43 / 50

43. The unit of payment for roadside brick edging to increase the pavement width is

44 / 50

44. The value of the property or structures becomes less by its becoming out of date in style is known as

45 / 50

45. Which of the following is not a common size of reinforcement bars?

46 / 50

46. The portion which is wrongly excavated by the contractor is to be filled

47 / 50

47. Providing and assembling in position false work for the construction of RCC superstructure is measured in:

48 / 50

48. Specifications for the holdfasts are given in terms of

49 / 50

49. Carpet area does not include the area of

50 / 50

50. Volume is measured correct to the nearest:

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook Twitter
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments
Scroll to Top
0
Join Discussionsx
()
x