Estimating & Costing Online Test - Paper 3 » Ultimate Challenge
GK Aim: A Treasure of MCQs

Estimating & Costing Online Test – Paper 3

0%
Created by 83a36dcfd5c4caff12bc80f0020c9c749e12cbbbdb7c406dc1dd39996cb85836?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get fresh, new questions in each attempt.

  • Total Questions: 50
  • Time Allotted: 50 minutes
  • Passing Score: 70%
  • Randomization: Yes
  • Certificate: Yes
  • Do not refresh the page!
  • 👍 All the best!

1 / 50

1. Working out the exact quantities of various items of work is known as

2 / 50

2. The life of teak wood doors and windows is usually taken to be

3 / 50

3. For small residential buildings, the cost installation and electrification are made as:

4 / 50

4. The annual periodic payments made for the repayment of the capital invested are known as

5 / 50

5. 1 He=......Ropani.

6 / 50

6. Evaluation of building is done based on

7 / 50

7. Actual cost of construction plus certain profit is paid to the contractor. Such a contract is known as

8 / 50

8. In the long and short wall method of estimation, the length of the long wall is the center to center space between walls plus

9 / 50

9. In detailed measurement, the sequence of dimensions is written:

10 / 50

10. In the case of a roof truss made of steel, rivets, bolts, nuts, etc., normally account for

11 / 50

11. Work-charged establishment

12 / 50

12. The nominal lead and lift allowed for the earthwork in the excavations of the foundations are

13 / 50

13. Which of the following is not a common size of reinforcement bars?

14 / 50

14. The information that can't be included in drawings is conveyed to the estimator through

15 / 50

15. During the calculation of RCC, the amount of steel deducted is

16 / 50

16. In the specification of earthwork in foundation trenches, drains, etc. lead specified is (IS code)

17 / 50

17. In the analysis of rates, the profit and overhead for the contractor are generally taken as

18 / 50

18. The most reliable estimate is:

19 / 50

19. The unit of payment for fixing of glass panes or cleaning is in

20 / 50

20. Centre line method is specially adopted for estimating... Buildings.

21 / 50

21. The method of valuation of a building as used by commercial banks is based on:

22 / 50

22. Arrange the specific weights of wood (w), cement (c), steel (s), and coarse aggregate (A) in increasing order

23 / 50

23. The unit rate of items written by the contractor in BOQ is in numeral as well as alphabetical form. Which one is preferred?

24 / 50

24. Due to a change in the price level, a revised estimate is prepared if the sanctioned estimate exceeds:

25 / 50

25. In the specification of earthwork in foundation trenches, drains, etc. lift ordinarily specified is

26 / 50

26. Payment of the steel is done by

27 / 50

27. The net annual letting out value of a property, which is obtained after deducting the amount of yearly repairs from the gross income, is known as

28 / 50

28. Tender does not contain

29 / 50

29. The full form of VAT is

30 / 50

30. Pick up the correct statement

31 / 50

31. The gradual accumulation of amounts by way of annual periodic deposits, which is meant for the replacement of the structure at the end of its useful life period, is known as

32 / 50

32. The actual size of the modular brick (as per IS Code) is

33 / 50

33. Providing and assembling in position false work for the construction of RCC superstructure is measured in:

34 / 50

34. The portion which is wrongly excavated by the contractor is to be filled

35 / 50

35. The value of the property (without being disassembled) at the end of the useful life period is known as

36 / 50

36. If valuable properties are found during excavation, it becomes the property of

37 / 50

37. Steel formwork can be used up to about.........times.

38 / 50

38. Liquidated damage is directly related to

39 / 50

39. Of the total estimated cost of a building, the cost of electrification usually accounts for

40 / 50

40. In the case of laying gullies, intercepting traps, the cost includes:

41 / 50

41. The estimated quantity of cement required in cement mortar (1:6) per cubic meter will be

42 / 50

42. Minimum size of the pipe connected to the septic tank is

43 / 50

43. The number of corrugations in a galvanized corrugated sheet is usually

44 / 50

44. The quantity of work of any item which is the output of a skilled labor in a day is known as

45 / 50

45. The unit of measurement for woodwork in door and window frame, rafters, beams, roof trusses, etc., is

46 / 50

46. In the analysis of rates, what percentage of total cost is provided towards water charges?

47 / 50

47. The useful part of the livable area of a building is also known as

48 / 50

48. End lap provided in asbestos cements is equal to

49 / 50

49. Bill of quantities is prepared based on:

50 / 50

50. Indicating works left in excavated trenches to facilitate the measurement of borrow pits are known as

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook Twitter
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments
Scroll to Top