Construction Management Online Test - Paper 3 » Quiz Test
GK Aim: A Treasure of MCQs

Construction Management Online Test – Paper 3

0%
Created by 83a36dcfd5c4caff12bc80f0020c9c749e12cbbbdb7c406dc1dd39996cb85836?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get fresh, new questions in each attempt.

  • Total Questions: 50
  • Time Allotted: 50 minutes
  • Passing Score: 70%
  • Randomization: Yes
  • Certificate: Yes
  • Do not refresh the page!
  • 👍 All the best!

1 / 50

1. If the height of the frequency-distribution underneath it is equal to unity, then the curve is known as:

2 / 50

2. If the path of activities leads back into itself, the resulting error in the network is known as:

3 / 50

3. On a bar chart, the various activities of a project are shown by:

4 / 50

4. The expected project duration in CPM follows:

5 / 50

5. The amount of VAT for the purchase of steel having an amount of NRs. 6000/- should be:

6 / 50

6. Critical activities having total float are:

7 / 50

7. Which operation must complete first?

8 / 50

8. According to Fulkerson's, the correct event numbers corresponding to events A, B, C, D, E of the network shown in figure 1 are:

9 / 50

9. In PERT technique, completion of an activity is called:

10 / 50

10. Negative float can occur when it is:

11 / 50

11. If, for an activity, the optimistic time is 1 day, pessimistic time is 11 days, and the most likely time is 3 days, then the expected time is:

12 / 50

12. The square root of the variance is known as:

13 / 50

13. An example of a parallel activity is:

14 / 50

14. Gantt chart is used for:

15 / 50

15. Which of the following does not represent an activity?

16 / 50

16. An event is indicated on the network by a number enclosed in:

17 / 50

17. Negative slack occurs:

18 / 50

18. At an event other than the final event, if no activity emerges, it results in an error called:

19 / 50

19. The area under the B-curve is divided into two equal parts by:

20 / 50

20. Updating may result in:

21 / 50

21. Negative slack indicates:

22 / 50

22. What are the key dates of a standard contracting procedure for a project?

23 / 50

23. Float is:

24 / 50

24. The reduction in project time normally results in:

25 / 50

25. The overall in-charge of an organization at the site responsible for the execution of works is:

26 / 50

26. Total project time is the:

27 / 50

27. Total float for any activity is defined as the difference between:

28 / 50

28. Latest finish time in CPM technique is indicated by:

29 / 50

29. Performance security is necessary:

30 / 50

30. Jobs going ahead of schedule are conveniently shown in:

31 / 50

31. PERT technique of network analysis is useful for:

32 / 50

32. When the times of earliest finish and the latest finish are equal in an operation, the operation is called:

33 / 50

33. Most of the works related to measurement of items and making entry to the measurement book is initiated by:

34 / 50

34. A project is:

35 / 50

35. The objective of technical planning is:

36 / 50

36. The maximum amount for the approval of tender by Gazetted 3rd class officer is:

37 / 50

37. A construction schedule is prepared after collecting:

38 / 50

38. Gantt chart is drawn for:

39 / 50

39. Economic saving of time is obtained by crashing:

40 / 50

40. Critical path:

41 / 50

41. A frequency distribution curve:

42 / 50

42. PERT is:

43 / 50

43. The weakness in bar charts is:

44 / 50

44. The amount of money paid to the contractor by the client after the agreement and before the execution of work is known as:

45 / 50

45. Line organization is mostly suitable for:

46 / 50

46. The time with which direct cost does not reduce with the increase in time is known as:

47 / 50

47. Standard deviation when the optimistic time is 1 day, pessimistic time is 11 days, and most likely time is 3 days:

48 / 50

48. Time and progress chart of construction is known as:

49 / 50

49. The 1st stage of construction is:

50 / 50

50. For the execution of work in time, a work plan is prepared by:

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Scroll to Top