Home» Online Test » Civil Engineering » Construction Management Online Test » Paper 1 » Paper 2 » Paper 3 0% Sorry, time's up. To complete the online test, please restart it. Created by Vikash chaudhary This is a FREE online test. Beware of scammers who ask for money to attend this test. Get fresh, new questions in each attempt. Total Questions: 50 Time Allotted: 50 minutes Passing Score: 70% Randomization: Yes Certificate: Yes Do not refresh the page! 👍 All the best! 1 / 50 1. A project is: a) A large dam constructed across a river to earn profit b) Any job involving many people and large money c) A work of major importance involving huge men and investment d) An organized teamwork to achieve a set task within the time limit 2 / 50 2. Total project cost: a) Increases with time b) Decreases with time c) Initially reduces with time and then increases with further increases d) Constant 3 / 50 3. In CPM: a) Time optimization is given prime importance b) Cost optimization is given prime importance c) Cost is directly proportional to time d) All of the above 4 / 50 4. Time and progress chart of construction is known as: a) Bar chart b) Gantt chart c) CPM d) All of the above 5 / 50 5. The relation between jobs of a particular type and various durations they have consumed for completion is expressed by: a) Normal distribution curve b) Beta distribution curve c) Frequency distribution curve d) None of the above 6 / 50 6. Which operation must complete first? a) Right of the line joining two circles b) Left of the line joining two circles c) Both of the above d) None of the above 7 / 50 7. Mobilization advance up to 10% of the cost of work is given to a contractor: a) On commencement of work at the site for payment of a loan taken by him b) For the purchase of construction materials c) For the payment of advances to labor and staff d) For all activities required to start the work at the site 8 / 50 8. Latest finish time in CPM technique is indicated by: a) Triangle b) Circle c) Rectangle d) Line 9 / 50 9. Probability factor in PERT is given by: a) (Scheduled time - Earliest expected time) / Standard deviation b) (Scheduled time - Latest allowable time) / Standard deviation c) (Latest allowable time - Scheduled time) / Standard deviation d) (Latest allowable time - Earliest expected time) / Variance 10 / 50 10. Most of the works related to measurement of items and making entry to the measurement book is initiated by: a) Site supervisor b) Site engineer c) Resident engineer d) Project in charge 11 / 50 11. The time corresponding to the minimum total project cost is: a) Normal time b) Crash time c) Optimistic time d) Between normal and crash time 12 / 50 12. The number of pre-operations associated with an operation may be: a) One only b) Two only c) More than one d) Three only 13 / 50 13. In CPM method, the earliest finish is indicated by time on: a) Top right, outside the circle, in a triangle b) Top right, outside the circle, in a rectangle c) Both of the above d) None of the above 14 / 50 14. The Force Account or AMANAT, a method of carrying out the construction work is done by: a) Contractor using his own tools, staff, equipment, etc. b) Owner using his own tools, staff, equipment, etc. c) Sub-contractor using his own tools, staff, equipment, etc. d) None of the above 15 / 50 15. A milestone chart: a) Shows the interdependence of various jobs b) Depicts the delay of jobs c) Shows the events in chronological but not in a logical sequence d) All of the above 16 / 50 16. The independent float affects only: a) Preceding activities b) Succeeding activities c) The particular activity d) None of the above 17 / 50 17. If, for an activity, the optimistic time is 1 day, pessimistic time is 11 days, and the most likely time is 3 days, then the expected time is: a) 3 days b) 4 days c) 5 days d) 6 days 18 / 50 18. Type of organization used in the construction industry is: a) Line organization b) Line and staff organization c) Functional organization d) None of the above 19 / 50 19. The scheduled completion time of an operation in CPM chart is mentioned on: a) Left top corner outside the circle b) Left top corner inside the circle c) Both of the above d) None of the above 20 / 50 20. An EPC contract means: a) End of planning and construction b) Evaluation, planning, and construction c) Engineering, planning, and construction d) Engineering, procurement, and construction 21 / 50 21. Positive float can occur when it is: a) Sub-critical activity b) Critical activity c) Super-critical activity d) Normal activity 22 / 50 22. For a curve, larger the variance: a) Greater will be the uncertainty b) Smaller will be the uncertainty c) Not related to uncertainty d) All of the above 23 / 50 23. The occurrence of the completion of an activity is called its: a) Head event b) Tail event c) Dual-role event d) All of the above 24 / 50 24. The variance will be zero if: a) Each individual deviation is zero b) Sum of deviation is zero c) Standard deviation is zero d) None of the above 25 / 50 25. In a CPM/PERT network, the number of events is: a) Less than the number of activities b) More than the number of activities c) Equal to the number of activities d) All of the above 26 / 50 26. Bar chart is drawn for: a) Time versus activity b) Activity versus resources c) Resources versus progress d) Progress versus time 27 / 50 27. Latest start time is the: a) Latest time by which an activity can be started without delaying the project b) Latest time by which an activity can be completed without delaying the project c) Latest time the event can occur d) Any of the above 28 / 50 28. If an activity has its optimistic, most likely, and pessimistic times as 2, 4, and 6, respectively, then its expected time and variance are respectively: a) 4 and 2/3 b) 4 and 4/9 c) 5 and 4/9 d) 5 and 2/3 29 / 50 29. An event is: a) A definite job b) A definite time interval c) The terminals of an activity d) A definite position of an activity 30 / 50 30. A construction schedule is prepared after collecting: a) Number of operations b) Output of labor and machinery c) Quantity of various items d) All of the above 31 / 50 31. Codes used in Nepal for building construction/design are: a) National Building Codes (NBC) b) Indian Standard Codes (ISC) c) American Standard Codes (ASC) d) British Standard Codes (BSC) 32 / 50 32. Bar chart is used for minor projects, CPM is used for repetitive work while PERT is used for: a) Repetitive types of work b) Limited time and unlimited resources types of work c) Uncertainty time and resources types of work d) All of the above 33 / 50 33. Henry Gantt developed the bar chart technique in: a) 1900 AD b) 1940 AD c) 1957 AD d) 1974 AD 34 / 50 34. Direct cost of a project is due to: a) Establishment charges such as salaries to administrative staff b) Loss or gain of revenue c) Penalty imposed d) Cost of materials and wages of labor 35 / 50 35. Construction team means: a) An engineer b) An owner c) A contractor d) All of the above 36 / 50 36. Choose the incorrect statement: a) Arrow representing activity in CPM network is drawn without any scale b) Head of an activity represents the finish of an activity c) Tail of an activity represents the start of an activity d) None of the above 37 / 50 37. In PERT analysis, the start and end of activity are represented by: a) Activity b) Event c) Task d) Work 38 / 50 38. The objective of technical planning is: a) Preparation of specifications and estimates b) Initiating the procurement action of resources c) Taking remedial action about bottleneck in execution d) All of the above 39 / 50 39. PERT technique of network analysis is useful for: a) Small projects b) Large projects c) Research and development projects d) All of the above 40 / 50 40. The weakness in bar charts is: a) The various activities are interdependent b) Uncertainty in duration for various activities c) The sequence of activities is not very clear d) All of the above 41 / 50 41. In PERT, the most likely time is: a) The minimum time in which any activity can possibly be accomplished b) The maximum time which an activity might require c) The time which has the highest probability of occurrence d) None of the above 42 / 50 42. Which of the following is an event in a CPM network: a) Concrete cured b) Walls plastering c) Excavation for foundation d) Fixing of the door 43 / 50 43. Updating may result in: a) Change of the critical path b) Decrease of project completion time c) Increase of project completion time d) All of the above 44 / 50 44. CPM network is: a) Event-oriented b) Activity-oriented c) Slack-oriented d) Float-oriented 45 / 50 45. For the execution of work in time, a work plan is prepared by: a) Contractor b) Consultant c) Petty contractor d) Financial institution 46 / 50 46. CPM family includes: a) Critical Path Analysis (CPA) b) Critical Path Plotted (CPP) c) Critical Path Scheduling (CPS) d) All of the above 47 / 50 47. Float is: a) The earliest time by which an activity may commence b) Latest time by which an activity can be delayed without hampering the completion of the project c) Latest allowable time-earliest expected time d) Time available-time required for an activity 48 / 50 48. Restraint is a restriction having: a) Both (a) and (b) above b) Zero duration c) Positive duration d) Negative duration 49 / 50 49. Crashing of the project means: a) Reducing the completion time by expending more resources b) Reducing the project cost by delaying the completion time c) Reducing the project size to save resources d) Reducing the project cost by reducing the completion time 50 / 50 50. In PERT, pessimistic time is: a) The minimum time in which any activity can possibly be accomplished b) The maximum time which an activity might require c) The time which has the highest probability of occurrence d) None of the above Please provide accurate information so we can send your Achievement Certificate by mail. NameEmailPhone Number Your score is Share your achievement! LinkedIn Facebook Twitter 0% Restart Test Please provide your feedback. Thank you for your valuable feedback. Send feedback Buy Construction Management MCQ PDF for Offline Study