Construction Management Online Test - Paper 3 » Quiz Test
GK Aim: A Treasure of MCQs

Construction Management Online Test – Paper 3

0%
Created by 83a36dcfd5c4caff12bc80f0020c9c749e12cbbbdb7c406dc1dd39996cb85836?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get fresh, new questions in each attempt.

  • Total Questions: 50
  • Time Allotted: 50 minutes
  • Passing Score: 70%
  • Randomization: Yes
  • Certificate: Yes
  • Do not refresh the page!
  • 👍 All the best!

1 / 50

1. A project is:

2 / 50

2. Which operation must complete first?

3 / 50

3. Time and progress chart of construction is known as:

4 / 50

4. Total project cost:

5 / 50

5. Jobs going ahead of schedule are conveniently shown in:

6 / 50

6. Which of the following is an activity in a CPM network:

7 / 50

7. A milestone chart:

8 / 50

8. A construction schedule is prepared after collecting:

9 / 50

9. Line of balance technique is used for:

10 / 50

10. CPM network is:

11 / 50

11. Total float for any activity is defined as the difference between:

12 / 50

12. The independent float affects only:

13 / 50

13. Policy is:

14 / 50

14. At an event other than the final event, if no activity emerges, it results in an error called:

15 / 50

15. The maximum amount of project cost after the price adjustment should not exceed:

16 / 50

16. The difference between the total float and the free float is termed as:

17 / 50

17. In CPM, the actual performance of a task is called:

18 / 50

18. Gantt chart is used for:

19 / 50

19. For the construction of a project, a contractor is a:

20 / 50

20. For a safe working environment in the working site, "Tool Box Talk" is conducted:

21 / 50

21. If the height of the frequency-distribution underneath it is equal to unity, then the curve is known as:

22 / 50

22. For completion of a project, the critical path of the network represents:

23 / 50

23. The probability of completion of any activity within its expected time in PERT is:

24 / 50

24. Indirect cost of the project:

25 / 50

25. Standard deviation when the optimistic time is 1 day, pessimistic time is 11 days, and most likely time is 3 days:

26 / 50

26. It means the offering, giving, receiving, or soliciting, directly or indirectly, anything of value to influence improperly the actions of another party:

27 / 50

27. Float is:

28 / 50

28. The objective of technical planning is:

29 / 50

29. When all the paths are arranged according to the descending order of the float, the path which is next to the critical path is known as:

30 / 50

30. A frequency distribution curve:

31 / 50

31. The activity which neither takes time nor cost for its completion but is logically required to start the succeeding activity is known as:

32 / 50

32. In CPM analysis:

33 / 50

33. Critical activities having total float are:

34 / 50

34. The difference between total float and free float is called interfering float which is nothing but the:

35 / 50

35. The activity that consumes maximum time is called:

36 / 50

36. Critical path network helps the engineer to:

37 / 50

37. If the probability factor is zero, the chances of completing the project in scheduled time are:

38 / 50

38. Type of organization used in the construction industry is:

39 / 50

39. Free float is mainly used to:

40 / 50

40. Railway projects are treated as:

41 / 50

41. The constraint in the case of resource smoothing operation would be:

42 / 50

42. The dispute in construction is resolved through discussion of all parties on their respective stands leading to consensus. The process is called:

43 / 50

43. Restraint is a restriction having:

44 / 50

44. The estimated time required to complete an activity is termed as:

45 / 50

45. The mean of squared deviation from the mean of the distribution is known as:

46 / 50

46. The minimum number of consulting firms for the direct purchase of services is:

47 / 50

47. The meaning of modular coordination in construction is:

48 / 50

48. For a curve, larger the variance:

49 / 50

49. The square root of the variance is known as:

50 / 50

50. A contractor can start the construction works following the receipt of:

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook Twitter
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments
Scroll to Top