Construction Management Online Test – Paper 3

0%
Created by 37fdd4228dab83e2f2bdee26b19f1560?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get New Questions in Each Attempt

  • Total Questions: 50
  • Time Allotted: 50 minutes
  • Passing Score: 70%
  • Randomization: Yes
  • Certificate: Yes
  • Do not refresh the page!
  • 👍 All the best!

1 / 50

1. In PERT, pessimistic time is:

2 / 50

2. Choose the most correct statement from the following:

3 / 50

3. Which of the following is not a part of a contract agreement?

4 / 50

4. The maximum amount for the approval of tender by Gazetted 3rd class officer is:

5 / 50

5. The amount of money paid to the contractor by the client after the agreement and before the execution of work is known as:

6 / 50

6. Updating may result in:

7 / 50

7. Which of the following time estimates is related to PERT?

8 / 50

8. The time with which direct cost does not reduce with the increase in time is known as:

9 / 50

9. Whenever an activity has zero total float, then:

10 / 50

10. Which operation must complete first?

11 / 50

11. The dispute in construction is resolved through discussion of all parties on their respective stands leading to consensus. The process is called:

12 / 50

12. The pictorial representation of activities and events of a project is known as:

13 / 50

13. Negative slack occurs:

14 / 50

14. Latest finish time in CPM technique is indicated by:

15 / 50

15. The direct cost of a project with respect to normal time is:

16 / 50

16. A golden rule for the procurement of construction work suggests:

17 / 50

17. The district rate finalizing committee does not include the representative of:

18 / 50

18. Critical activities having total float are:

19 / 50

19. 'Wait' in CPM belongs to the category of:

20 / 50

20. Critical path is:

21 / 50

21. Total project time is the:

22 / 50

22. Gantt chart is drawn for:

23 / 50

23. The main disadvantage of line organization is:

24 / 50

24. Construction team means:

25 / 50

25. The benefit of the PERT network is taken by the management in:

26 / 50

26. The maximum amount of project cost after the price adjustment should not exceed:

27 / 50

27. The constraint in the case of resource smoothing operation would be:

28 / 50

28. The final technical authority of a project is:

29 / 50

29. Positive float can occur when it is:

30 / 50

30. Latest start of the activity is always:

31 / 50

31. Direct cost of a project is due to:

32 / 50

32. Policy is:

33 / 50

33. PERT is:

34 / 50

34. Free float is the:

35 / 50

35. Total cost of the project is:

36 / 50

36. In a CPM/PERT network, the number of events is:

37 / 50

37. Negative float can occur when it is:

38 / 50

38. Jobs going ahead of schedule are conveniently shown in:

39 / 50

39. The dual-role event is:

40 / 50

40. Most of the works related to measurement of items and making entry to the measurement book is initiated by:

41 / 50

41. The most critical stage of construction is the construction of:

42 / 50

42. Power stations are generally treated as:

43 / 50

43. The figure indicates:

44 / 50

44. In CPM method, the earliest finish is indicated by time on:

45 / 50

45. Force majeure in a contract is:

46 / 50

46. The estimated time required to complete an activity is termed as:

47 / 50

47. For a safe working environment in the working site, "Tool Box Talk" is conducted:

48 / 50

48. A stage or point where all previous jobs merging in it are completed and all further jobs bursting out are still to be completed is known as:

49 / 50

49. Time and progress chart of construction is known as:

50 / 50

50. The total cost versus time curve of an activity is:

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook Twitter
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments
0
Join Discussionsx
()
x
Scroll to Top