Construction Management Online Test – Paper 3

0%
Created by 83a36dcfd5c4caff12bc80f0020c9c749e12cbbbdb7c406dc1dd39996cb85836?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get New Questions in Each Attempt

  • Total Questions: 50
  • Time Allotted: 50 minutes
  • Passing Score: 70%
  • Randomization: Yes
  • Certificate: Yes
  • Do not refresh the page!
  • 👍 All the best!

1 / 50

1. The district rate finalizing committee does not include the representative of:

2 / 50

2. Residential buildings are treated as:

3 / 50

3. Crashing of the project means:

4 / 50

4. The salient feature of functional organization is:

5 / 50

5. The benefit of the PERT network is taken by the management in:

6 / 50

6. In PERT analysis, the actual performance of the task is known as:

7 / 50

7. Probability factor in PERT is given by:

8 / 50

8. The overall in-charge of an organization at the site responsible for the execution of works is:

9 / 50

9. If the height of the frequency-distribution underneath it is equal to unity, then the curve is known as:

10 / 50

10. Critical path network helps the engineer to:

11 / 50

11. Force majeure in a contract is:

12 / 50

12. In resource leveling, the main constraint would be:

13 / 50

13. Which of the following techniques is advanced and more indicative in modern construction progress review?

14 / 50

14. Free float for any activity is defined as the difference between:

15 / 50

15. The main disadvantage of line organization is:

16 / 50

16. Crash project duration is obtained by adding the:

17 / 50

17. Negative slack indicates:

18 / 50

18. The activity which neither takes time nor cost for its completion but is logically required to start the succeeding activity is known as:

19 / 50

19. If, for an activity, the optimistic time is 1 day, pessimistic time is 11 days, and the most likely time is 3 days, then the expected time is:

20 / 50

20. Codes used in Nepal for building construction/design are:

21 / 50

21. For completion of a project, the critical path of the network represents:

22 / 50

22. Whenever an activity has zero total float, then:

23 / 50

23. A contractor can start the construction works following the receipt of:

24 / 50

24. Completion of an activity on the CPM network diagram is generally known as:

25 / 50

25. In PERT analysis, the start and end of activity are represented by:

26 / 50

26. CPM family includes:

27 / 50

27. The occurrence of the starting of an activity is called its:

28 / 50

28. Float is:

29 / 50

29. Slack time in PERT analysis:

30 / 50

30. The meaning of modular coordination in construction is:

31 / 50

31. In a CPM/PERT network, the number of events is:

32 / 50

32. The direct cost of a project with respect to normal time is:

33 / 50

33. Which of the following is an event in a CPM network:

34 / 50

34. In PERT technique, completion of an activity is called:

35 / 50

35. When all the paths are arranged according to the descending order of the float, the path which is next to the critical path is known as:

36 / 50

36. The expected project duration in CPM follows:

37 / 50

37. The weakness in bar charts is:

38 / 50

38. The estimated time required to complete an activity is termed as:

39 / 50

39. Who is responsible for accidents occurring at the site?

40 / 50

40. Latest finish time in CPM technique is indicated by:

41 / 50

41. For the construction of a project, a contractor is a:

42 / 50

42. Inspection of construction works for quality control is carried out and covers:

43 / 50

43. What are the key dates of a standard contracting procedure for a project?

44 / 50

44. Which of the following is an activity in a CPM network:

45 / 50

45. The square root of the variance is known as:

46 / 50

46. The 1st stage of construction is:

47 / 50

47. PERT means:

48 / 50

48. Milestone charts are developed in:

49 / 50

49. The relation between jobs of a particular type and various durations they have consumed for completion is expressed by:

50 / 50

50. The time by which the particular activity can be delayed without affecting the preceding and succeeding activities is known as:

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook Twitter
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments
Scroll to Top
0
Join Discussionsx
()
x