Construction Management Online Test – Paper 3

0%
Created by 05ee5296782fad7019cdf7681b0f8797 gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get New Questions in Each Attempt

  • Total Questions: 50
  • Time Allotted: 50 minutes
  • Passing Score: 70%
  • Randomization: Yes
  • Certificate: Yes
  • Do not refresh the page!
  • 👍 All the best!

1 / 50

1. In time cost optimization using CPM, the crashing of activities along the critical path is done starting with the activity having:

2 / 50

2. Float is:

3 / 50

3. Performance security is necessary:

4 / 50

4. For a curve, larger the variance:

5 / 50

5. Most of the works related to measurement of items and making entry to the measurement book is initiated by:

6 / 50

6. For the construction of a project, a contractor is a:

7 / 50

7. The term CPM in construction management is an abbreviation of:

8 / 50

8. The time with which direct cost does not reduce with the increase in time is known as:

9 / 50

9. Bar chart is drawn for:

10 / 50

10. The constraint in the case of resource smoothing operation would be:

11 / 50

11. The estimated time required to complete an activity is termed as:

12 / 50

12. The main disadvantage of line organization is:

13 / 50

13. Line organization is mostly suitable for:

14 / 50

14. According to Fulkerson's, the correct event numbers corresponding to events A, B, C, D, E of the network shown in figure 1 are:

15 / 50

15. Total float for any activity is defined as the difference between:

16 / 50

16. The occurrence of the completion of an activity is called its:

17 / 50

17. In PERT analysis, the time estimates of activities and the probability of their occurrence follow:

18 / 50

18. The main principle of an organization is:

19 / 50

19. The 1st stage of construction is:

20 / 50

20. Which of the following does not represent an activity?

21 / 50

21. Muster rolls are used for:

22 / 50

22. The most critical stage of construction is the construction of:

23 / 50

23. CPM network is:

24 / 50

24. Total project cost:

25 / 50

25. The meaning of modular coordination in construction is:

26 / 50

26. Negative float can occur when it is:

27 / 50

27. An event is:

28 / 50

28. The expected project duration in CPM follows:

29 / 50

29. Which method is known as the minimum cost or maximum time schedule method:

30 / 50

30. Standard deviation when the optimistic time is 1 day, pessimistic time is 11 days, and most likely time is 3 days:

31 / 50

31. Indirect cost of the project:

32 / 50

32. Mobilization advance up to 10% of the cost of work is given to a contractor:

33 / 50

33. Assuming that the cost varies with time, the cost-slope is defined as:

34 / 50

34. The time by which the particular activity can be delayed without affecting the preceding and succeeding activities is known as:

35 / 50

35. The figure indicates:

36 / 50

36. In CPM analysis:

37 / 50

37. Power stations are generally treated as:

38 / 50

38. For a safe working environment in the working site, "Tool Box Talk" is conducted:

39 / 50

39. Crash project duration is obtained by adding the:

40 / 50

40. In CPM:

41 / 50

41. Which of the following is an event in a CPM network:

42 / 50

42. In PERT, pessimistic time is:

43 / 50

43. Which of the following is not a part of a contract agreement?

44 / 50

44. PERT means:

45 / 50

45. If the height of the frequency-distribution underneath it is equal to unity, then the curve is known as:

46 / 50

46. The duration of time which an activity can be delayed without affecting the succeeding activity is called free float which affects only:

47 / 50

47. Aggregate planning is planning for:

48 / 50

48. Gantt chart indicates:

49 / 50

49. Free float for any activity is defined as the difference between:

50 / 50

50. Gantt chart is used for:

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook Twitter
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments
0
Join Discussionsx
()
x
Scroll to Top