Construction Management Online Test - Paper 3 » Quiz Test

Construction Management Online Test – Paper 3

0%
Created by 83a36dcfd5c4caff12bc80f0020c9c749e12cbbbdb7c406dc1dd39996cb85836?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get fresh, new questions in each attempt.

  • Total Questions: 50
  • Time Allotted: 50 minutes
  • Passing Score: 70%
  • Randomization: Yes
  • Certificate: Yes
  • Do not refresh the page!
  • 👍 All the best!

1 / 50

1. Negative slack occurs:

2 / 50

2. CPM family includes:

3 / 50

3. Critical path connecting the start and end events timewise is:

4 / 50

4. In PERT analysis, the actual performance of the task is known as:

5 / 50

5. Which of the following is not a part of a contract agreement?

6 / 50

6. The dispute in construction is resolved through discussion of all parties on their respective stands leading to consensus. The process is called:

7 / 50

7. Most of the works related to measurement of items and making entry to the measurement book is initiated by:

8 / 50

8. An event is indicated on the network by a number enclosed in:

9 / 50

9. Earliest finish time of an activity is always:

10 / 50

10. Muster rolls are used for:

11 / 50

11. The maximum amount of project cost after the price adjustment should not exceed:

12 / 50

12. In time cost optimization using CPM, the crashing of activities along the critical path is done starting with the activity having:

13 / 50

13. In PERT, pessimistic time is:

14 / 50

14. At an event other than the final event, if no activity emerges, it results in an error called:

15 / 50

15. The benefit of the PERT network is taken by the management in:

16 / 50

16. Choose the incorrect statement:

17 / 50

17. Standard deviation when the optimistic time is 1 day, pessimistic time is 11 days, and most likely time is 3 days:

18 / 50

18. The overall in-charge of an organization at the site responsible for the execution of works is:

19 / 50

19. Updating may result in:

20 / 50

20. Critical path network helps the engineer to:

21 / 50

21. The objective of technical planning is:

22 / 50

22. An event is:

23 / 50

23. Policy is:

24 / 50

24. Milestone charts are developed in:

25 / 50

25. The scheduled completion time of an operation in CPM chart is mentioned on:

26 / 50

26. Performance security is necessary:

27 / 50

27. The independent float affects only:

28 / 50

28. Which type of tender generally prefers the schedule of rate?

29 / 50

29. In PERT, the most likely time is:

30 / 50

30. Bar chart is drawn for:

31 / 50

31. The amount of earnest money deposited at the time of submission of tender is:

32 / 50

32. The time by which the particular activity can be delayed without affecting the preceding and succeeding activities is known as:

33 / 50

33. Frederick W. Taylor introduced a system of working known as:

34 / 50

34. Gantt chart indicates:

35 / 50

35. Aggregate planning is planning for:

36 / 50

36. Economic saving of time is obtained by crashing:

37 / 50

37. Float is:

38 / 50

38. A fictitious activity with zero duration and no cost used to maintain the sequential order of the activities in the network is known as a:

39 / 50

39. The area under the B-curve is divided into two equal parts by:

40 / 50

40. The district rate finalizing committee does not include the representative of:

41 / 50

41. The variance will be zero if:

42 / 50

42. If the probability factor is zero, the chances of completing the project in scheduled time are:

43 / 50

43. Which of the following does not represent an activity?

44 / 50

44. The activity which neither takes time nor cost for its completion but is logically required to start the succeeding activity is known as:

45 / 50

45. Residential buildings are treated as:

46 / 50

46. The weakness in bar charts is:

47 / 50

47. Which of the following time estimates is related to PERT?

48 / 50

48. Direct cost of a project is due to:

49 / 50

49. For the execution of work in time, a work plan is prepared by:

50 / 50

50. The figure indicates:

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook Twitter
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments
Scroll to Top