Construction Management Online Test - Paper 3 » Quiz Test
GK Aim: A Treasure of MCQs

Construction Management Online Test – Paper 3

0%
Created by 83a36dcfd5c4caff12bc80f0020c9c749e12cbbbdb7c406dc1dd39996cb85836?s=32&d=monsterid&r=g gkaimVikash chaudhary

This is a FREE online test. Beware of scammers who ask for money to attend this test.

Get fresh, new questions in each attempt.

  • Total Questions: 50
  • Time Allotted: 50 minutes
  • Passing Score: 70%
  • Randomization: Yes
  • Certificate: Yes
  • Do not refresh the page!
  • 👍 All the best!

1 / 50

1. The occurrence of the starting of an activity is called its:

2 / 50

2. Float is:

3 / 50

3. Most of the works related to measurement of items and making entry to the measurement book is initiated by:

4 / 50

4. The mean of squared deviation from the mean of the distribution is known as:

5 / 50

5. If D is the duration, ES and EF are the earliest start and earliest finish time, LS and LF are the latest start and latest finish time, then the following relation holds good:

6 / 50

6. No agreement is between:

7 / 50

7. Critical path is:

8 / 50

8. Mobilization advance up to 10% of the cost of work is given to a contractor:

9 / 50

9. Tender documents do not contain:

10 / 50

10. Which method is known as the minimum cost or maximum time schedule method:

11 / 50

11. The independent float affects only:

12 / 50

12. Critical activities having total float are:

13 / 50

13. Which of the following is an activity in a CPM network:

14 / 50

14. The estimated time required to complete an activity is termed as:

15 / 50

15. The number of pre-operations associated with an operation may be:

16 / 50

16. Which of the following is not a part of a contract agreement?

17 / 50

17. The minimum number of critical paths in a network should be:

18 / 50

18. The difference between total float and free float is called interfering float which is nothing but the:

19 / 50

19. The Force Account or AMANAT, a method of carrying out the construction work is done by:

20 / 50

20. Which operation must complete first?

21 / 50

21. Restraint is a restriction having:

22 / 50

22. Slack time in PERT analysis:

23 / 50

23. The technique for establishing and maintaining priorities among various jobs of a project is known as:

24 / 50

24. Whenever an activity has zero total float, then:

25 / 50

25. PERT technique of network analysis is useful for:

26 / 50

26. The reduction in project time normally results in:

27 / 50

27. The probability of completion of any activity within its expected time in PERT is:

28 / 50

28. Bar chart is drawn for:

29 / 50

29. The upper portion of horizontal bars in a bar chart indicates:

30 / 50

30. Total cost of the project is:

31 / 50

31. Jobs going ahead of schedule are conveniently shown in:

32 / 50

32. The direct cost of a project with respect to normal time is:

33 / 50

33. Railway projects are treated as:

34 / 50

34. The district rate finalizing committee does not include the representative of:

35 / 50

35. In resource leveling, the main constraint would be:

36 / 50

36. Of the following, the PERT event is:

37 / 50

37. If the probability factor is zero, the chances of completing the project in scheduled time are:

38 / 50

38. The dispute in construction is resolved through discussion of all parties on their respective stands leading to consensus. The process is called:

39 / 50

39. Milestone charts are developed in:

40 / 50

40. Force majeure in a contract is:

41 / 50

41. Frederick W. Taylor introduced a system of working known as:

42 / 50

42. Bar chart is used for minor projects, CPM is used for repetitive work while PERT is used for:

43 / 50

43. Earliest finish time of an activity is always:

44 / 50

44. It means the offering, giving, receiving, or soliciting, directly or indirectly, anything of value to influence improperly the actions of another party:

45 / 50

45. When all the paths are arranged according to the descending order of the float, the path which is next to the critical path is known as:

46 / 50

46. The interrelationship between the functional elements of a program is achieved through:

47 / 50

47. Bar charts are considered suitable for:

48 / 50

48. The most critical stage of construction is the construction of:

49 / 50

49. Crash project duration is obtained by adding the:

50 / 50

50. The main advantage of line organization is:

Please provide accurate information so we can send your Achievement Certificate by mail.

Your score is

Share your achievement!

LinkedIn Facebook Twitter
0%

Please provide your feedback.

Thank you for your valuable feedback.

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments
Scroll to Top